|
---|
Category:Letter
MONTHYEARRS-24-098, Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality2024-10-23023 October 2024 Units 1 and 2 - Supplement to License Amendment Request to Revise Technical Specifications 3.7.15, Spent Fuel Pool Boron Concentration, 3.7.16, Spent Fuel Assembly Storage, 4.3.1, Fuel Storage, Criticality ML24291A0012024-10-17017 October 2024 Submittal of Core Operating Limits Report, Cycle 25 RS-24-095, Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals2024-10-10010 October 2024 Relief Request I4R-19 and I4R-26, Associated with the Fourth and Fifth Inservice Inspection Intervals RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary IR 05000456/20240112024-09-12012 September 2024 Biennial Problem Identification and Resolution Inspection Report 05000456/2024011 and 05000457/2024011 ML24164A0032024-09-10010 September 2024 Issuance of Amendment Nos. 235 and 235 Revision of Technical Specifications for the Ultimate Heat Sink IR 05000456/20240052024-08-29029 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2024005 and 05000457/2024005) ML24227A0522024-08-29029 August 2024 Audit Plan for LAR to Remove ATWS Mtc Limit ML24225A1112024-08-13013 August 2024 Notification of NRC Fire Protection Team Inspection Request for Information ML24222A6772024-08-0909 August 2024 Response to Request for Additional Information for Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition IR 05000456/20240022024-08-0808 August 2024 Integrated Inspection Report 05000456/2024002 and 05000457/2024002 ML24172A1252024-07-26026 July 2024 Environmental Assessment and Finding of No Significant Impact Related to a Requested Increase in Ultimate Heat Sink Temperature (EPID L-2024-LLA-0075) - Transmittal Letter ML24179A3262024-07-23023 July 2024 LTR - Constellation - SG Welds and Nozzles (L-2023-LLR-0053, L-2023-LLR-0054, L-2023-LLR-0055, L-2023-LLR-0056) ML24163A3922024-06-25025 June 2024 Individual Notice of Consideration of Issuance of Amendments to Renewed Facility Operating Licenses, Proposed No Significant Hazards Consideration Determination, & Opportunity for a Hearing (EPID L-2024-LLA-0075)- Letter RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations ML24164A2132024-06-13013 June 2024 Information Request to Support Upcoming Problem Identification and Resolution (Pi&R) Inspection at Braidwood Nuclear Plant RS-24-057, License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink2024-06-0404 June 2024 License Amendment to Technical Specification 3.7.9, Ultimate Heat Sink IR 05000456/20240102024-05-31031 May 2024 License Renewal Phase 1 Report 05000456/2024010 RS-24-044, License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed2024-05-28028 May 2024 License Amendment to Transition to Framatome Gaia Fuel and Exemptions to 10 CFR 50.46 and 10 CFR 50 Appendix K. Attachments 1 to 11 Enclosed RS-24-043, Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications2024-05-24024 May 2024 Application to Remove Power Distribution Monitoring System (Pdms) Details from Technical Specifications ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report ML24136A0132024-05-15015 May 2024 2023 Annual Radiological Environmental Operating Report ML24136A2452024-05-15015 May 2024 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000457/2024004 ML24128A1212024-05-0707 May 2024 Response to Braidwood and Dresden FOF Dates Change Request (2025) ML24122A6522024-05-0101 May 2024 Submittal of 2023 Annual Radioactive Effluent Release Report RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests IR 05000456/20243012024-04-29029 April 2024 NRC Initial License Examination Report 05000456/2024301; 05000457/2024301 RS-24-026, License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR)2024-04-25025 April 2024 License Amendment to Braidwood Station, Units 1 and 2, and Byron Station, Units 1 and 2, Technical Specifications 5.6.5, Core Operating Limits Report (COLR) ML24116A0052024-04-25025 April 2024 Transmittal of Braidwood Station, Unit 1, Core Operating Limits Report, Braidwood Unit 1 Cycle 25 IR 05000456/20240012024-04-24024 April 2024 Integrated Inspection Report 05000456/2024001 and 05000457/2024001 ML24113A1272024-04-22022 April 2024 Audit Plan in Support of Review of LAR Revision of TS 3.7.15, 3.7.16, and 4.3.1 (EPID: L-2023-LLA-0136) (Non-Proprietary) IR 05000457/20240902024-04-19019 April 2024 Final Significance Determination for 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Dilution Issue - NRC Inspection Report 05000457/2024090 ML24103A2042024-04-12012 April 2024 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-591-A, Revise Risk Informed Completion Time (RICT) Program Revision 0 and Revise 10 CFR 50.69 License Condition RS-24-034, Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors2024-04-10010 April 2024 Annual 10 CFR 50.46 Report of Emergency Core Cooling System Evaluation Model Changes and Errors ML24094A2692024-04-0303 April 2024 Notification of Deviation from Pressurized Water Reactor Owners Group (PWROG) Report, WCAP-17451-P, Revision 2, Reactor Internals Guide Tube Wear Westinghouse Domestic Fleet Operational Projections RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report ML24057A0372024-03-26026 March 2024 Proposed Alternative from Certain Requirements Contained in the American Society of Mechanical Engineers Boiler and Pressure Vessel Code, Section XI RS-24-024, Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-22022 March 2024 Response to Request for Additional Information Regarding Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds ML24067A3252024-03-0707 March 2024 U.S. Department of Energy, Office of Legacy Management, 2023 Annual Site Inspection and Monitoring Report for Uranium Mill Tailings Radiation Control Act Title I Disposal Sites ML24066A0122024-03-0606 March 2024 Operator Licensing Examination Approval Braidwood Station, Units 1 and 2, March 2024 IR 05000456/20244012024-03-0505 March 2024 Cyber Security Inspection Report 05000456/2024401 and 05000457/2024401 (Public) IR 05000456/20230062024-02-28028 February 2024 Annual Assessment Letter for Braidwood Station, Units 1 and 2 (Report 05000456/2023006 and 05000457/2023006) ML24057A3022024-02-26026 February 2024 Regulatory Conference Supplemental Information ML24047A2382024-02-20020 February 2024 Regulatory Conference to Discuss Risk Associated with 2b Auxiliary Feedwater Pump Diesel Engine Fuel Oil Leak RS-24-013, Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators2024-02-13013 February 2024 Response to Request for Additional Information Regarding Proposed Alternative to Distribution Requirements of ASME Code Table IWC-2411-1 for the Steam Generators IR 05000456/20230042024-02-0202 February 2024 Integrated Inspection Report 05000456/2023004 and 05000457/2023004 2024-09-23
[Table view] Category:Request for Additional Information (RAI)
MONTHYEARML24263A1272024-09-23023 September 2024 – Request for Additional Information (EPID 2023-LLA-0136) - Non-Proprietary ML24197A0162024-07-12012 July 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - License Amendment Request to Adopt TSTF-591 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24053A3382024-02-22022 February 2024 NRR E-mail Capture - Final RAI - Constellation Energy Generation, LLC - Fleet Request - Proposed Alternative for Examination of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds (L-2023-LLR-0062) ML24039A0412024-01-30030 January 2024 NRR E-mail Capture - Request for Additional Information Regarding Braidwood Request for Alternative (I4R-18) ML23339A0452023-12-0505 December 2023 Request for Information for an NRC Post-Approval Site Inspection for License Renewal Inspection Report 05000546/2024010 ML23191A8442023-07-10010 July 2023 05000456; 05000457 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML23110A3202023-04-21021 April 2023 Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes Inspection ML23094A1352023-04-0404 April 2023 Request for Information for Nrc Commercial Grade Dedication Inspection Inspection Report 05000456/2023010 05000457/2023010 ML23069A0342023-03-0606 March 2023 Unit 1 Lr Commitment 10 RAI Set 1 - (Non-Proprietary) ML23069A0332023-03-0606 March 2023 Email to K. Lueshen Byron and Braidwood Commitment 10 - Request for Additional Information Set 1 ML23018A1632023-01-18018 January 2023 Notification of NRC Baseline Inspection and Request for Information ML22241A0522022-08-29029 August 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000456/2022004 05000457/2022004 ML22129A0132022-05-0606 May 2022 NRR E-mail Capture - Draft RAIs for Requests for Alternatives I4R-17, I4R-23, ISI-05-018, I6R-10 ML22271A0772022-05-0606 May 2022 NRR E-mail Capture - Final RAIs 9.1.2021 Constellation Relief Request ML22091A0852022-04-0101 April 2022 NRR E-mail Capture - Braidwood and Byron - Final RAI Regarding Proposed Alternative for Various Pressurizer Welds (EPID L-2021-LLR-0035 and 0036) ML22041B5362022-02-10010 February 2022 NRR E-mail Capture - Constellation Energy Generation, LLC - Request for Additional Information Regarding Fleet License Amendment Request to Adopt TSTF-541 IR 05000456/20224022022-02-0404 February 2022 Information Request for the Cyber-Security Baseline Inspection, Notification to Perform Inspection 05000456/2022402 05000457/2022402 ML21350A4372021-12-16016 December 2021 Request for Information for an NRC Triennial Baseline Design Bases Assurance Inspection (Team) Inspection Report 05000456/2022010 and 05000457/2022010 ML21256A1902021-09-10010 September 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21228A2352021-08-17017 August 2021 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000457/2021004 ML21193A0942021-07-12012 July 2021 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21189A1602021-07-0808 July 2021 NRR E-mail Capture - Request for Additional Information - Braidwood, Byron, and Ginna - Amendment to Address the Issues in Westinghouse NSALs ML21144A2132021-05-24024 May 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding License Transfer Application ML21117A0342021-05-0505 May 2021 Request for Additional Information Regarding Proposed Alternative to Use ASME Code Case N-893 ML21062A0652021-03-0101 March 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Proposed Fleet Alternative to Documentation Requirements for Pressure Retaining Bolting ML21057A1022021-02-25025 February 2021 Notification of NRC Fire Protection Team Inspection Request for Information; Inspection Report 05000456/2021010; 05000457/2021010 ML21049A2572021-02-18018 February 2021 Request for Additional Information Byron/Dresden Proposed Changes to Site Emergency Plans to Support Post-Shutdown and Permanently Defueled Conditions (EPID-2020-LLA-0240 & EPID-2020-LLA-0237) ML21029A3302021-01-29029 January 2021 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Fleet Alternative Request to Use ASME Code Case N-885 ML21020A1292021-01-20020 January 2021 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000456/2021002; 05000457/2021002 ML21004A1452020-12-30030 December 2020 NRR E-mail Capture - Request for Additional Information Regarding Relief Requests Braidwood I4R-11 and Byron I4R-18 ML20289A1142020-10-0909 October 2020 NRR E-mail Capture - Preliminary RAIs for LAR Regarding Non-conservative TS EDG Frequency Tolerance ML20153A7042020-06-0101 June 2020 NRR E-mail Capture - Preliminary RAI for Fleet Request to Use Alternative OMN-26 ML20104C1452020-04-10010 April 2020 NRR E-mail Capture - Preliminary RAIs for Exelon'S April 6, 2020, Application to Defer Braidwood, Unit 2, Steam Generator Inspections ML20023A0812020-01-23023 January 2020 NRR E-mail Capture - RAIs for L-2019-LLA-0201 - Braidwood, Units 1 and 2, LAR to Revise TS 3.7.9, Ultimate Heat Sink ML19350B2952019-12-16016 December 2019 NRR E-mail Capture - Draft Request for Additional Information Regarding Braidwood Station, Units 1 and 2, Impractical Inservice Inspection Requirements (L-2019-LLA-0081) ML19275H1362019-10-0202 October 2019 NRR E-mail Capture - Exelon Generation Company, LLC - Request for Additional Information Regarding Request to Use ASME Code Case N-879 ML19252C1542019-08-22022 August 2019 NRR E-mail Capture - Issuance of the Remainder of Preliminary RAIs for Braidwood/Byron TSTF-505 Application ML19232A2242019-08-0707 August 2019 NRR E-mail Capture - Partial Issuance of Final RAIs for Braidwood/Byron TSTF-505 Application ML19207A0672019-07-26026 July 2019 NRR E-mail Capture - Partial Issuance of Preliminary RAIs for Braidwood/Byron TSTF-505 Application ML19179A0612019-07-19019 July 2019 Three Mile Point 1 - Supplemental Information Needed to Proposed Alternative to Use ASME Code Case N-879 ML19128A2362019-05-0202 May 2019 NON- PROPRIETARY- Request for Additional Information- Amendment Request Regarding Utilization of Tvel TVS-K Lead Test Assemblies Braidwood Station, Units 1 and 2 ML19066A0432019-03-0707 March 2019 NRR E-mail Capture - Preliminary RAIs for Quality Assurance Review of Braidwood Tvel LTA Application ML18324A8072018-12-12012 December 2018 Supplemental Information Needed for Acceptance of Requested Licensing Action One-Time Extension of Technical Specification 3.8.1, AC Sources-Operating, A2 Completion Time ML18192C1712018-07-11011 July 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Braidwood Station, Units 1 and 2, Relief Request IR4-03 ML18190A4072018-07-0505 July 2018 NRR E-mail Capture - Preliminary Request for Additional Information Regarding Braidwood Station, Units 1 and 2, Relief Request IR4-06 ML18150A6902018-05-30030 May 2018 NRR E-mail Capture - Preliminary RAIs Regarding Braidwood TORMIS Amendment Request ML18149A2842018-05-24024 May 2018 NRR E-mail Capture - B/B 50.69 RAI - Potential Typo ML18135A2202018-05-15015 May 2018 NRR E-mail Capture - Preliminary RAIs for Braidwood Relief Request IR4-05 ML18129A1082018-05-0909 May 2018 NRR E-mail Capture - Preliminary RAIs for Braidwood and Byron Stations 50.69 Amendment 2024-09-23
[Table view] |
See also: IR 05000456/2018012
Text
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION III
2443 WARRENVILLE RD. SUITE 210
LISLE, ILLINOIS 60532-4352
January 8, 2018
Mr. Bryan C. Hanson
Senior VP, Exelon Generation Company, LLC
President and CNO, Exelon Nuclear
4300 Winfield Road
Warrenville, IL 60555
SUBJECT: BRAIDWOOD STATION UNITS 1 AND 2REQUEST FOR INFORMATION
FOR AN NRC DESIGN BASES ASSURANCE INSPECTION (PROGRAM):
IMPLEMENTATION OF THE ENVIRONMENTAL QUALIFICATION PROGRAM
INSPECTION REPORT 05000456/2018012; 05000457/2018012
Dear Mr. Hanson:
On March 12, 2018, the U. S. Nuclear Regulatory Commission (NRC) will begin a Triennial
Baseline Design Bases Assurance Inspection (Program) at your Braidwood Station, Units 1
and 2. This inspection will be performed in accordance with NRC Baseline Inspection
Procedure 71111.21N, Attachment 1.
The Design Bases Assurance Inspection will focus on the implementation of the Electrical
Equipment Environmental Qualification (EQ) Program to verify you are maintaining the qualified
status of equipment during the life of the plant. The EQ components to be reviewed during this
baseline inspection will be identified during the in-office preparation week that occurs prior to the
onsite inspection week.
The inspection will include a bagman trip to support selection of components and 2 weeks of
onsite inspection. The inspection team will consist of three NRC inspectors. The current
inspection schedule is as follows:
Bagman trip onsite week: February 12-15, 2018;
Preparation week: March 5-9, 2018;
Onsite inspection weeks: March 12-16, 2018; and March 26-30, 2018.
Experience with previous baseline design inspections of similar depth and length has shown
that this type of inspection is extremely resource intensive, both for the NRC inspectors and the
licensee staff. In order to minimize the inspection impact on the site and to ensure a productive
inspection for both parties, we have enclosed a request for information needed for the
inspection.
It is important that all of these documents are up-to-date and complete in order to minimize the
number of additional documents requested during the preparation and/or the onsite portions of
the inspection. Insofar as possible, this information should be provided electronically to the lead
inspector. The information request has been divided into four groups:
B. Hanson -2-
The first group lists information necessary for our initial inspection scoping activities.
This information should be provided to the lead inspector no later than January 23, 2018.
Prior to the bagman trip on January 31, 2018, the lead inspector will communicate the
initial selected set of approximately 12 EQ components.
The second group of documents requested is those items needed to support the
bagman trip. This set of documents should be available to the lead inspector onsite
on February 12, 2018.
The third group of documents requested is those items needed to support our
in-office preparation activities for the selected set of 6-9 EQ components. This set of
documents should be provided to the lead inspector at the Regional Office no later than
February 28, 2018. During the in-office preparation activities, the team may identify
additional information needed to support the inspection.
The last group includes the additional information above as well as plant specific
reference material. This information should be available to the team onsite on
March 12, 2018. It is also requested that corrective action documents and/or
questions developed during the inspection be provided to the lead inspector as
the documents are generated.
The lead inspector for this inspection is Mr. John V. Bozga. We understand that our licensing
contact for this inspection is Mr. Richard Schliessmann of your organization. If there are any
questions about the inspection or the material requested in the enclosure, please contact the
lead inspector at 630-829-9613.
This letter does not contain new or amended information collection requirements subject to the
Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection
requirements were approved by the Office of Management and Budget, Control Number 3150-0011.
The NRC may not conduct or sponsor, and a person is not required to respond to, a request for
information or an information collection requirement unless the requesting document displays a
currently valid Office of Management and Budget Control Number.
This letter and its enclosure will be made available for public inspection and copying at
http://www.nrc.gov/reading-rm/adams.html and at the NRC Public Document Room in
accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding.
Sincerely,
/RA Andrew Dunlop Acting for/
John V. Bozga, Senior Reactor Inspector
Engineering Branch 1
Division of Reactor Safety
Docket Nos. 50-456; 50-457
License Nos. NPF-72; NPF-77
Enclosure:
Design Bases Assurance Inspection
EQ Program Document Request
cc: Distribution via LISTSERV
B. Hanson -3-
Letter to Bryan C. Hanson from John V. Bozga dated January 8, 2018
SUBJECT: BRAIDWOOD STATION UNITS 1 AND 2REQUEST FOR INFORMATION
FOR AN NRC DESIGN BASES ASSURANCE INSPECTION (PROGRAM):
IMPLEMENTATION OF THE ENVIRONMENTAL QUALIFICATION PROGRAM
INSPECTION REPORT 05000456/2018012; 05000457/2018012
DISTRIBUTION:
Jeremy Bowen
RidsNrrDorlLpl3
RidsNrrPMBraidwood Resource
RidsNrrDirsIrib Resource
Steven West
Kenneth OBrien
Richard Skokowski
Allan Barker
Carole Ariano
Linda Linn
DRPIII
DRSIII
ADAMS Accession number ML18009B001
OFFICE RIII RIII RIII RIII
NAME ADunlop for
JBozga:cl
DATE 01/08/18
OFFICIAL RECORD COPY
DESIGN BASES ASSURANCE INSPECTION EQ PROGRAM DOCUMENT REQUEST
Inspection Report: 05000456/2018012; 05000457/2018012
Bagman Dates: February 12-15, 2018
Inspection Dates: March 12-16, 2018, and March 26-30, 2018
Inspection Procedure: IP 71111.21N, Design Bases Assurance Inspection (Program),
Attachment 1, Environmental Qualification (EQ) under
10 CFR 50.49 Programs, Processes, and Procedures
Lead Inspector: John V. Bozga
Senior Reactor Inspector, DRS
630-829-9613
I. Information Requested Prior to the Onsite Information Gathering/Bagman Week
The following information is requested by January 23, 2018, or sooner, to facilitate
inspection preparation. If you have any questions regarding this information, please call
the team leader as soon as possible. (Please provide the information electronically in
pdf files, Excel, or other searchable formats, preferably on some portable electronic
media (e.g., CD-ROM, DVD, etc.). The portable electronic media should contain
descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information
in lists should contain enough information to be easily understood by someone who
has knowledge of light water reactor technology).
1. Risk-ranking of top 250 components required to meet environmental
qualifications (EQ) from your site specific probabilistic safety analysis sorted
by Fussell Vesely Importance.
2. Probabilistic safety analysis listing of top 10 risk significant systems.
3. U.S. Nuclear Regulatory Commission Safety Evaluation Report(s) associated
with EQ.
4. Electronic copies of Updated Final Safety Analysis Report, Technical
Specifications, and Technical Specifications Bases. Specifically identify which
Updated Final Safety Analysis Report sections address EQ (including seismic).
5. Identify the various EQ standards (including year, edition, or revision) that the
station is committed to.
6. Site (and corporate if applicable) procedures associated with the Title 10 of the
Code of Federal Regulations, Part 50.49, EQ Program for electrical components.
Include procedures for procurement of qualified equipment, maintenance of
qualified equipment, modification to qualified equipment (including Equivalency
or Commercial Grade Dedication (CGD) Programs), and material storage and
shelf life controls.
Enclosure
7. Copy of EQ Design Basis Document, if applicable.
8. Copy of any open licensing commitments related to EQ, if applicable.
9. Equipment Qualification Master List. Specific issues to be identified include:
safety classification (safety-related or nonsafety-related), Regulatory Guide 1.97
instrumentation, EQ qualification (e.g., DOR, NUREG 588, 50.49), original or
replaced after implementation of 50.49, and plant location.
10. List of any installed equipment removed from the Equipment Qualification Master
List and basis for removal.
11. List of EQ solenoid valves that are normally continuously energized.
12. List or drawings of plant areas that are subjected to EQ, identifying design
(limiting) temperature, both normal and accident, high energy line break,
radiation levels, etc. that the associated equipment will have to be qualified to
meet EQ. If unit has obtained a power uprate (greater than 5 percent) provide
same information pre-update (earliest available if multiple uprates).
13. List of CGD evaluations performed, for which the dedicated parts have been
issued for installation (parts issued for the last 10 years) on EQ applications in
the plant. Include CGD evaluation number, name of part, component ID or
description of the component the part was issued to repair, work order, and date
issued or installed.
14. List of Corrective Action Documents related to the EQ Program or EQ of specific
components for the last 5 years.
15. Current management and engineering organizational chart.
II. Information Requested (for the approximate 9-12 selected components) to be
Available by the Bagman Trip on February 12, 2018
1. EQ summary report for each component/subcomponent.
2. Qualification Maintenance Requirement Sheet or equivalent.
3. List of corrective action documents associated with each of the selected
components for the last 5 years.
4. Photos of any component in containment or high radiation areas, if available.
III. Information Requested (for the approximate 6-9 selected components) to be
Available by February 28, 2018, (will be reviewed by the team in the Regional
office during the week of March 5-9, 2018)
This information should be separated for each selected component, especially if
provided electronically (e.g., folder with component name that includes EQ files,
Qualification Test Reports, calculations, corrective action documents, maintenance
history, etc.).
1. EQ file, including associated Qualification Test Reports.
2
2. Vendor manual (electronic copy or availability of hard copy during inspection).
3. Preventive maintenance template.
4. Last performed work order (WO) for each associated EQ preventive
maintenance.
5. List of corrective maintenance WOs for the last 10 years. Include WO number,
date performed, and brief one line description.
6. If repair work (e.g., a motor rewind) was performed under a purchase order,
provide copy of the purchase order.
7. Thermal life calculation.
8. Any self-assessments of the EQ program in the last 3 years.
IV. Additional Information to be Provided on March 12, 2018, Onsite
1. During the in-office preparation activities, the team may identify additional
information needed to support the inspection. The lead inspector will provide a
list of the additional information needed during the week of March 5-9, 2018.
V. Information Requested to be Provided Throughout the Inspection
1. Copies of any corrective action documents generated as a result of the teams
questions or queries during this inspection.
2. Copies of the list of questions submitted by the team members and the
status/resolution of the information requested (provide daily by 2:00 p.m.
during the inspection to each team member).
If you have questions regarding the information requested, please contact the lead inspector.
3