Advises of Planned Insp Effort Resulting from Plant PPR Review on 961002
ML17354A333
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 11/08/1996
From: Landis K
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To: Plunkett T
FLORIDA POWER & LIGHT CO.
References
NUDOCS 9611150292
Download: ML17354A333 (5)


Text

November 8, 1996 Florida Power and Light Company ATTN:

Hr. T. F. Plunkett President

- Nuclear Division P. 0.

Box 14000 Juno Beach, FL 33408-0420

SUBJECT:

PLANT PERFORMANCE REVIEW (PPR)

- TURKEY POINT 3 and 4

Dear Mr. Plunkett:

On October

2. 1996, the regional staff completed the semiannual Plant Performance Review (PPR) of Turkey Point 3 and 4.

The staff conducts these reviews for all operating nuclear power plants to develop an integrated understanding of safety performance.

The results are used by regional management to facilitate planning and allocation of inspection resources.

The PPR for Turkey Point 3 and 4 involved the participation of all technical divisions in evaluating inspection results and safety performance information for the period from March 1996 to September 1996.

PPRs provide regional management with a current summary of licensee performance and serve as inputs to the NRC Systematic Assessment of Licensee Performance (SALP) and senior management meeting (SMM) reviews.

This letter advises you of'ur planned inspection effort resulting from the Turkey Point 3 and 4 PPR review.

It is provided in an attempt to minimize the resource impact on your staff and to allow for scheduling conflicts to be resolved in advance of inspection dates.

The enclosure presents our inspection plan for the next six months.

Specific dates are included for near term inspections.

Long term inspection dates will be announced prior to the inspections and any scheduling conflicts will be resolved with your staff.

The rational or basis for each inspection outside the core inspection program is provided so that you are aware of the reasons for emphasis in these program areas.

Resident inspections are not listed due to their ongoing and continuous nature, nor are region based inspections which accomplish Resident Core Hodules to compensate for Resident Inspector absences due to training.

During each NRC inspection planned during this period, specitic attention will continue to be given to the verification of selected Updated Final Safety Analysis Report (UFSAR) commitments.

Applicable portion(s) of the UFSAR that relate to the inspection activities will be reviewed and verification made that the UFSAR commitments have been properly implemented into plant practices, procedures and/or parameters.

OFFICIAL COPY 9biii50292 96ii08 PDR ADOCK 05000250 G

PDR tl

FP8L We will inform you of any changes to the inspection plan.

If you have any questions.

please contact Kerry Landis at 404-331-5509.

Sincerely, Orig signed by Kerry D. Landis Kerry D. Landis, Chief Reactor Projects Branch 3 Division of Reactor Projects Docket No. 50-250 and 251 License Nos.

DPR-31 and DPR 41

Enclosure:

Inspection Plan cc w/encl:

H.

N. Paduano, Manager Licensing 8 Special Programs Florida Power and Light Company P. 0.

Box 14000 Juno Beach, FL 33408-0420 Plant General Manager Turkey Point Nuclear Plant P. 0.

Box 029100 Miami. FL 33102 R. J.

Hovey Site Vice President Turkey Point Nuclear Plant P. 0.

Box 029100 Miami, FL 33102 G.

E. Hollinger Licensing Manager Turkey Point Nuclear Plant P. 0.

Box 4332 Miami, FL 33032-4332 M. S.

Ross, Attorney Florida Power 5 Light 11770 US Highway 1

North Palm Beach, FL 33408 John T. Butler, Esq.

Steel.

Hector and Davis 4000 Southeast Financial Center Miami.

FL 33131-2398

FP8L Attorney General Department of Legal Affairs The Capitol Tallahassee.

FL 32304 Bill Passetti Office of Radiation Control Department of Health and Rehabilitative Services 1317 Winewood Boulevard Tallahassee.

FL 32399-0700 Armando Vidal County Manager of Metropolitan Dade County ill NW 1st Street, 29th Floor Miami, FL 33128 Joe Myers, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, FL 32399-2100 Distribution w/encl:

R. Croteau.

NRR B. Crowley, RII G. Hopper, RII G. Hallstrom, RII PUBLIC Thomas P. Johnson Senior Resident Inspector U.S. Nuclear Regulatory Commission P. 0.

Box 1448 Homestead, FL 33090 SENO TO PUBLIC OOCUNENT ROON?

OFFICE SIGNATUHE HChr1stensen YES NO PFredr1ekson KBarr TPe b es DATE COPY?

ll /

/ 96 1

/

I 96 11 / ~ I 96 YE HO I 96 11 / I I 96 11 /

I 96 SIGNATURE EHerschoff SEbneter DATE COPY?

11 I I 96 11 /

/ 96 11 /

I 96 YES HO YES HO UM N::

U 11 /

I 96 YES HO 11 /

/ 96 YES NO 11 I I 96 YES NO

TURKEY POINT INSPECTION PLAN INSPECTION PROCEDURE/

TEMPORARY INSTRUCTION IP 37550 IP 62700 TITLE/PROGRAM AREA POWER CURVES AND UPRATE CURVES INSPECTION REMOTE SAFE SHUTDOWN PANEL NUMBER OF INSPECTORS PLANNED INSPECTION DATES 9/29/96-10/27/96 11/4-8/96 TYPE OF INSPECTION

- COMMENTS:,"

Oe

~

REGIONAL INITIATIVE - TO MONITOR EQUIPMENT RECALIBRATION AND REVIEW POWER CURVES RELATED TO POWER UPRATE.

REGIONAL INITIATIVE-TO REVIEW MAINTENANCE AND TESTING OF SAFE SHUTDOWN PANELS IP 81700 IP 71001 IP 81700 SECURITY PROGRAH LICENSED OPERATOR REQUALIFICATION PROGRAM EVALUATION SECURITY PROGRAM/RA 2/3-7/97 REGIONAL INITIATIVEWITH NRR ASSIST TO EXERCISE SECURITY SYSTEHS AND EQUIPMENT.

12/16-20/96 CORE-SECURITY AUDITS. CORRECTIVE

ACTIONS, MANAGEMENT SUPPORT AND EFFECTIVENESS.

AND REVIEW PROTECTED AREA DETECTION EQUIPMENT.

1/13-16/97 REQUALIFCATION PROGRAM INSPECTION IP 82301/82302 IP 73753 TI2515/109 IP 62700 BIENNIAL EXERCISE FEMA EVALUATED INSERVICE INSPECTION HOV INSPECTION OUTAGE MAINTENANCE AND STEAM RELIEF VALVES INSPECTION 2/3-7/97 CORE -

EP 3/24-28/97 CORE-MAINTENANCE 3/24-28/97 REGIONAL INITIATIVE 3/31-4/4/97 REGIONAL INITIATIVE - TO REVIEW MAINTENANCE AND TESTING OF HAIN STEAN RELIEFS

~ L