December 15, 1994 LICENSEE:
Florida Power
& Light Company (FPL)
FACILITY:
Turkey Point Units 3 and 4
SUBJECT:
MEETING HELD TO DISCUSS PROPOSED FPL TECHNICAL SPECIFICATION ON DIESEL GENERATOR LOAD SEQUENCER On December 8,
The meeting was held at FPL request to discuss a proposed license amendment to add a limiting condition of operation (LCO) to the Technical Specifications (TS) regarding diesel generator load sequencers.
Mr. C.
Mowrey and Mr. D. Baker of FPL discussed the proposed LCO, the basis for the
- LCO, and the design of the plants.
Turkey Point TS currently do not address the actions to be taken by the operators when these sequencers are inoperable.
This lack of guidance to the operators is undesirable.
FPL is considering requesting a 48-hour LCO with one sequencer inoperable which is based on the allowable outage times of components of equivalent significance and a probabilistic safety analysis.
The meeting resulted in an understanding of the FPL basis for the proposed change and the NRR positions in this area.
FPL expects to submit the proposed change within the next 90 days.
Enclosure 1 contains a list of attendees.
(Original Signed By)
Richard P. Croteau, Project Manager Project Directorate II-2 Division of Reactor Projects I/II Office of Nuclear Reactor Regulation Docket Nos.
50-250 and 50-251
Enclosure:
As stated cc w/enclosure:
See next page Distribution Docket File PUBLIC PDII-2 RF WRussell/FMiraglia RZimmerman ETomlinson
DVerrelli, RII OFC LA:PDI I-2 PM:PDII-2 D:P I NAME Ounnin Ion RCroteau MTha ani DATE 12 94 12 //+ 94 12/
/94 OFFICIAL REC RD COPY - FILENAME: G:(NE TSUM. TP2 94i22iOi34 94i2i5 PDR ADOCK 05000250 P
11 I
'I
'lT'
Encl osur e 1
Turkey Point Units 3 and 4 DIESEL GENERATOR SEQUENCER AMENDMENTMEETING December 8, 1994 A en ees Name Office R. Croteau D. Baker C. Howrey M. Waterman D. Nguyen E. Tomlinson NRR FPL FPL NRR NRR NRR
Florida Power and Light Company CC:
Harold F. Reis, Esquire Newman and Holtzinger, P.C.
1615 L Street, N.W.
Washington, DC 20036 Jack Shreve, Public Counsel Office of the Public Counsel c/o The Florida Legislature 111 West Madison Avenue, Room 812 Tallahassee, Florida 32399-1400 John T. Butler, Esquire
- Steel, Hector and Davis 4000 Southeast Financial Center Hiami, Florida 33131-2398 Mr. Thomas F. Plunkett, Site Vice President Turkey Point Nuclear Plant Florida Power and Light Company P.O.
Box 029100 Miami, Florida 33102 Joaquin Avino County Manager of Hetropolitan Dade County 111 NW 1st Street, 29th Floor Miami, Florida 33128 Senior Resident Inspector Turkey Point Nuclear Generating Station U.S. Nuclear Regulatory Commission P.O.
Box 1448 Homestead, Florida 33090 Hr. Bill Passetti Office of Radiation Control Department of Health and Rehabilitative Services 1317 Winewood Blvd.
Tallahassee, Florida 32399-0700 Turkey Point Plant Mr. Joe Myers, Director Division of Emergency Preparedness Department of Community Affairs 2740 Centerview Drive Tallahassee, Florida 32399-2100 Regional Administrator, Region II U.S. Nuclear Regulatory Commission 101 Marietta Street, N.W. Suite 2900 Atlanta, Georgia 30323 Attorney General Department of Legal Affairs The Capitol Tallahassee, Florida 32304 Plant Manager Turkey Point Nuclear Plant Florida Power and Light Company P.O.
Box 029100 Miami, Florida 33102 Hr. H. N. Paduano, Manager Licensing
& Special Programs Florida Power and Light Company P.O.
Box 14000 Juno
- Beach, Florida 33408-0420 Hr. J.
H. Goldberg President Nuclear Division Florida Power and Light Company P.O.
Box 14000 Juno
- Beach, Florida 33408-0420 Hr. Edward J.
Weinkam Licensing Manager Turkey Point Nuclear Plant P.O.
Box 4332 Princeton, Florida 33032-4332