Revised Monthly Operating Rept for June 1990 for Turkey Point Unit 3
ML17348A508
Person / Time
Site: Turkey Point NextEra Energy icon.png
Issue date: 06/30/1990
From: Tierney R
FLORIDA POWER & LIGHT CO.
To:
Shared Package
ML17348A506 List:
References
NUDOCS 9008210124
Download: ML17348A508 (2)


Text

c'EVISED COPY

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO. 50-250 UNIT Turke Point 3

DATE'u ust 10 1990 COMPLETED BY R. A. Tierne TELEPHONE 305 246-6970 REPORT MONTH June 1990 Unit 3 was returned to service on June 3,

1990 from a scheduled refueling and maintenance outage that, began on February 3,

1990.

On June 4 Unit 3 was removed from service to repair the Feedwater Heater Relief Valve and Feedwater Heater Outlet Valve.

The unit was returned to service on June 9.

On June 9 Unit 3 tripped due to a Hi-Hi Steam Generator Water Level condition caused by failure of a

feedwater valve controller hand/auto station.

Unit 3

was returned to service on June 11.

On June 11, during a Turbine Overspeed Trip Test problems associated with the test were noted keeping the Unit off line until June 12.

On June 15 Unit 3 was removed from service to repair a leak in a condenser tube.

During the process of shutting down Unit 3 the reactor was tripped due to personnel error.

Unit 3 returned to service on June 17, 1990.

900S210124 900Sl5 PDR ADOCK 05000250