Notice of Deviation/Nonconformance from Insp on 881029-1123. Deviation/Nonconformance Noted:No Test Program Established to Show Conformance to Design & Sys Readiness Requirements as Shown by Inability to Isolate & Repair Hole in Piping
ML17345A597
Person / Time
Site: Turkey Point  NextEra Energy icon.png
Issue date: 12/16/1988
From: Wilson B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II)
To:
Shared Package
ML17345A595 List:
References
50-250-88-36, 50-251-88-36, NUDOCS 8812290046
Download: ML17345A597 (2)


Text

e ENCLOSURE 2

NOTICE OF DEVIATION Florida Power and Light Company Turkey Point Units 3 and 4

Docket Nos.

50-250, 50-251 License Nos.

DPR-31, DPR-41 The following deviation was identified during a Nuclear Regulatory Commission (NRC) inspection conducted on October 29, through November 23, 1988.

The Final Safety Analysis Report

( FSAR),

Appendix 9.6A, paragraph

3. 1.2(c),

states in part that control valves shall be capable of isolating portions of the fire main for maintenance or repair without shutting off the entire system.

Paragraph 2.4, Conformance to Branch Technical Position 9.5-1 Guidelines, Item A.4, states that the piping and valving is arranged such that a single break will not prevent the water supply from reaching a possible fire, and Item C.5, states that testing is conducted in accordance with procedures and verified by inspection and audit to demonstrate conformance to design and system readiness requirements.

Test results are evaluated and acted upon.

Contrary to the

above, as of October 29,
1988, no test program had been established to demonstrate conformance to design and system readiness requirements as demonstrated by the inability to isolate and repair a hole in the fire main piping.

Please provide to the U.

S.

Nuclear Regulatory Commission, ATTN:

Document Control Desk, Washington, DC 20555, with a copy to the Regional Administrator, Region II, in writing, within 30 days of the date of this notice, the reasons for the deviation, the corrective steps which have been taken and the results

achieved, the corrective steps which will be taken to avoid further deviations, and the date when your corrective action will be completed.

Where good cause is shown, consideration will be given to extending the response time.

FOR THE NUCLEAR REGULATORY COMMISSION Bruce A. Wilson, hief Reactor Projects Branch 2

Division of Reactor Projects Dated at Atlanta, Georgia this 16th day of December 1988 88i2290046 88i2i6 PDR ADOCK 05000250 PNU