ML17342A647
| ML17342A647 | |
| Person / Time | |
|---|---|
| Site: | Turkey Point |
| Issue date: | 07/10/1986 |
| From: | Falconer D, Stadler S, Wilson B NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION II) |
| To: | |
| Shared Package | |
| ML17342A639 | List: |
| References | |
| 50-250-86-24, 50-251-86-24, NUDOCS 8608110623 | |
| Download: ML17342A647 (42) | |
See also: IR 05000250/1986024
Text
gp8 AECy,
C+ 'po
Cy
ClO
IIh
t
+i*++
UNITED STATES
NUCLEAR REGULATORY COMMISSION
REGION II
101 MARIETTASTREET, N.W.
ATLANTA,GEORGIA 30323
Report Nos.
50-250/86-24
aIId 50-251/86-24
Licensee;
Florida Power and Light Company
9250 West Flagler Street
Miami,
FL
33102
Docket Nos.
50-250
and 50-251
License
Nos.
and
Facility Name:
Turkey Point
3 and
4
Inspection
Conducted:
April 3-6 and April 16-18,
1986
Inspectors:
i
~
Cvv~
D.
P.
Fal
ner
Date Signed
S.
D. Sta ler
Date Signed
H. 0. Christensen
C. Casto
D. Vander iet
Approved by:
Bruce A.
lson, Actin
ection Chief
Operational
Programs
S ction
Division of Reactor Safety
Dat
Signed
,.
SUMMARY
Scope:
This special
inspection
involved the areas
of accelerated
requalification
training,
emergency
operating
procedures,
and
the
emergency
diesel
generator
loading safety evaluation
and associated
Confirmation of Action letter.
Results:
Two violations
and
one deviation were identified:
1
a.
Deviation (250, 251/86-24-04)
Failure to revise procedures
to assure that
diesel
generator
loading
remained
no
more
than
2845
KW as
committed
by
Confirmation of Action letter;
see
paragraphs
6 and 9.
b.
Violation (250, 251/86-24-06) -
Failure
to
provide
adequate
corrective
actions to preclude repetition of training deficiencies
on the
Gamma Metrics
neutron flux monitor;
see
paragraph
8.
Violation (250, 251/86-24-08) - Failure to perform
10 CFR 50.59 evaluation
of
loads
beyond
those
analyzed
in
JPE-L-86-59,
Revi sion
1;
see
paragraph
9.
No Notice of Violation for this item will be
included in the
report as this matter is being considered for enforcement
action
as part of
a separate
report.
8608110623
860714
ADOCK 05000250
8
'1
r
X
'4
0
REPORT DETAILS
1.
Persons
Contacted
Licensee
Employees
- ¹C. H. Methy, Site Vice President
~ C. Baker, Plant Manager (Nuclear)
"¹D. Grandage,
Operations
Superintendent
(Nuclear)
¹W. Hiller, Training Superintendent
"¹V. Kaminskas,
Operations
Supervisor
'¹J. Arias, Regulations
and Compliance Supervisor
¹D. Jones,
Procedure
Upgrade
Program
(PUP) Supervisor
¹J. Strong, Electrical Supervisor
Other licensee
employees
contacted
included engineers,
operators,
and office
personnel.
NRC Resident
Inspectors
t
~¹T. Peebles
R. Brewer
~Attended exit interview on April 6,
1986.
¹Attended exit interview on April 18,
1986.
2.
Exit Interview
The inspection
scope
and findings were
summarized
on April 6 and 18,
1986,
with those
per sons indicated in paragraph
1 above.
The inspector
described
the
areas
inspected
and discussed
in detai
1 the inspection
findings.
No
dissenting
comments
were received
from the licensee.
The licensee
did not
identify as proprietary
any of the materials
provided to or reviewed
by the
inspector during this inspection.
The licensee
made
the following commit-
ments at the exit interview:
a.
To revise
emergency
operating
procedure
(EOP) attachments
as necessary
to resolve identified deficiencies
which
have
the potential
to allow
overloading the emergency diesel
generators
(EDG's).
b.
To revise the
EOPs to reflect
a maximum
EDG loading of 2845
KM.
C.
To revise training brief 122 on
EDG loading precautions
to reflect the
significant changes
due to Revision
1 to JPE-L-86-59.
The revisions
to this training brief were to be provided to all licensed
personnel.
To
provide
locking
mechanisms
for intake
cooling
water/component
cooling water
(ICW/CCW) heat
exchanger
isolation valves throttled to
ensure that combined
ICW/CCW pump
EDG loads are maintained
below 500
KW.
t
ll
e.
To provide additional training to licensed
personnel
in the following
areas:
Integrated use'f
the
EOP's
and
attachments
related
to
loading.
This training
was to include in-plant walkthroughs of
the
procedures
and
attachments
for
each
licensed
operator.
Licensed
individuals participating in,accelerated
requalification
training were
to receive
the additional
EOP training prior to
resuming shift responsibilities.
Placing
the, control
room chillers in service
as required
by the
EOP's.
Gamma
Metrics
post accident flux monitoring instrumentation
for
licensee
personnel
from Hot License
Class
10.
This training was
to be conducted
immediately
as licensed
personnel
from this class
had
primary
responsibility
for
operation
of
Unit 3
pending
completion of additional
NRC requalification examinations.
3.
Licensee Action on Previous
Enforcement Matters
(Closed)
UNR (250,251/85-22-02):
The
licensee
was
unable
to retrieve
records relating to a specific plant work order
(PWO) maintenance activity.
The inspector
reviewed several
PWOs and requested
the clearances
associated
with these
PWOs.
The licensee
was able to retrieve all clearances
requested.
The inability to retrieve
the
clearance
associated
with this
UNR is
considered
an isolated incident.
This
UNR is closed.
(Closed) Violation (250,251/85-22-03):
Item a.
The licensee
failed to establish
adequate
maintenance
procedures
to ensure
the proper wiring of the
DC input filter circuit of 4A
static inverter
which resulted
in the
mi swiring of the filter
circuit and contributed to reactor trips on September
20,
1984 and
October 9,
1984.
Item b.
The licensee failed to implement Administrative Procedure
0190. 19,
Control
of
Maintenance
on
Nuclear
Safety
Related
and
Fire
Protection
Systems,
in the rewiring of the input filter section of
the
4A inverter.
This rewiring was
performed
under
a
PWO which
did not define the work to be done or any
QC inspections
or hold
points.
e
The inspector
reviewed revised
procedure
AP 0190. 19,
Control of
Maintenance
on
Safety
Related
and
Quality
Related
Systems,
revision dated January
8,
1986,
O-ADM-701,
PWO Preparation,
revision
dated
March 25,
1986,
and several
inter-office correspondences
on
administrative
guidelines
to
nuclear
electrical
maintenance
personnel.
These
procedures
and electrical
department
guidelines
provide
more
detailed
instructions,
and
increase
the
use
of
supervisory
holds
in preparing
PWO work descriptions.
Violation
examples
a.
and b.
are
adequately
addressed,
and
these
examples
are closed.
The licensee failed to establish
abnormal
operating
procedures
to
contend
with the
loss
of the
4A motor control
center.
This
resulted
in the
4AA05 and
4AB05 bus
supply fans
being
rendered
due
to operators
failing to close
breaker
40521
on
May 17,
1985.
The inspector
reviewed 3/4-0P-007,
480 Volt Motor Control Centers,
revision dated August 30,
1985.
The procedures
have
been
revised
to require
the operator
to verify that all motor control center
breakers
are reset.
Additionally, this
requirement
is
indepen-
dently verified.
Violation example c. is closed.
The licensee
failed to implement Administrative Procedure
0103.3,
Use of Temporary
System Alterations (TSA),
on July 6,
1984, for a
temporary
system
alteration
to the
3C Accumulator hi-low level
circuit, in that,
the licensee failed to maintain documentation
of
the TSA.
The
inspector
reviewed
a revision,
dated
January
14,
1986,
to
O-ADM-503, Control
and
Use of Temporary
System Alterations (the
replacement
procedure
for AP-0103.3).
0-ADM-503 requires
that
a
TSA log
be
retained
as
a quality assurance
record.
Violation
example d. is closed.
The
licensee
failed to
implement
maintenance
procedure
9707.1,
Inverter Periodic Inspection.
The
licensee
informed
the
inspector
that the procedure
upgrade
program was currently revising maintenance
procedures
to make
them
easier
to
work with.
The
inspector
reviewed
numerous
new
procedures
to determine if they were easier
to follow.
These
new
procedures
require the journeyman to document actions,
and include
more
supervisory
hold
points
and
gC
inspection
points.
The
completion of the procedure
upgrade
program should result in more
usable
maintenance
procedures.
Violation example
e. is closed.
The licensee failed to implement Administrative Procedure
0190.26,
section 8.51,
and perform preventive
maintenance
procedure
Calorimetric Instrumentation
Periodic Calibration, at the frequency
designated
by the computerized
preventive maintenance file.
The licensee
planned
to reduce
the
frequency of this calibration
to
an
annual
PM, but after reviewing the past history of the
PM,
the
frequency
was
not
changed.
The
inspector
reviewed
the
computerized
preventive
maintenance file for
and it had
been
completed.
Violation example f. is closed.
LJ
(Closed)
UNR (250,251/85-22-04):
All post accident
sampling
system
(PASS)
PMs were delayed
due to system modifications.
The inspector
reviewed
the
PMs and all
had
been
completed with the exception
of calibrating the
nuclear data
computer
channels for each
PM.
The inspector
was informed that
the
computer
channels
could
not
be
calibrated
unti 1
the
computer
was
reprogrammed
to accept
the
PASS inputs.
This
UNR will be closed out, but
the
completion
ot
the
PMs will
be
an
inspector
followup
item
(250,251/86-.24-01).
(Closed)
(250,251/85-22-12):
Provide
documentation
justifying the
installation
of other
than,
the
approved
breaker
specified
in
plant
change/modification
PC/M
80-31.
'The
inspector
reviewed
a letter
from
Electric
Corporation
to
Turkey
Point
Plant,
Electrical
Department,
dated
June
28,
1985,
confirming
that
circuit
breaker
P/N 1250C29G04
is
the
same
as circuit breaker
P/N
1268C14G04.
This
UNR is closed.
Unresolved
Items"
One unresolved
item was identified during the inspection:
UNR (250, 251/86-24-03):
Utilization of operator
action statements
in
notes
(paragraph
6).
Reactive
Inspection
Background
Power
and
Light Juno
Plant Engineering
(JPE)
conducted
a Safety
Evaluation,
JPE-L-86-59,
Revision
1,
which indicated
special
restrictions
that
must
be
placed
on Unit 4 during
the
operation
of Unit 3.
These
restrictions
were necessary
to ensure that the diesel
generator
loads that
could
be
experienced
during
design
basis
events
do not exceed
technical
specification
or design
limitations.
JPE identified that
the
KW rating
assumed
in the
FSAR for the intake cooling water ( ICW) and component cooling
water
(CCW) pumps
was based
on
a design
point that could
be
exceeded
with
only one
ICW and
one
CCW pump in operation.
The evaluation indicated that
with ICW/CCW pump runout,
the
2?50
KW auto-connected
technical
specification
limit and the 2950
KW FSAR 168 hour0.00194 days <br />0.0467 hours <br />2.777778e-4 weeks <br />6.3924e-5 months <br />
EDG emergency rating could be exceeded.
An additional
evaluation
was
performed
to
provide
a Justification
for
Continued Operation
(JCO) for operation of a single unit with the other unit
in cold
shutdown.
The evaluation
concluded
that Unit 3 could
be operated
with Unit 4 in cold
shutdown provided that the loads which would be placed
on the diesel
generators
or
on
a single diesel
generator
in the event
one
diesel
is inoperable,
are
limited through
recommended
restrictions.
The
recommended
restrictions
included
general
areas
such
as
reduced
flows
through
and
ICW, locking out
unnecessary
electrical
loads
such
as
instrument air
compressors
and
Unit 4
normal
containment
coolers,
and
revising
the emergency
operating
procedures
(EOPs) to restrict the addition
of diesel
loads.
~ An Unresolved
Item is
a matter which more information is required to determine
whether it is acceptable
or may involve a violation or deviation.
~ I
,Ij
JPE-M-86-18,
which
was
submitted
with Revision
0 of JPE-L-86-59,
was
an
-evaluation of the Turkey Point
EOPs.
The
EOPs were rewritten to incorporate
the
recommendations
of
the
Emergency
Response
Guidelines
(ERGs).
JPE-M-86-18 contains
a
10
CFR 50: 59 review of the revised
by
and also
a
JPE
review of the
based
on emergency diesel
generator
(EDG)
loading
concerns
under
LOCA conditions.
The
JPE
review
determined
the
proposed
.EOPs
to
be adequate,
assuming
compliance with the
recommendations
in the
JCO and attachments.
Reactive
inspections
were conducted
by Region II personnel
on April 3-6 and
16-18,
1986,
to verify compliance with the recommendations
and limitations
detailed in JPE-L-86-59, "Justification for Continued Operation with One Unit
at Power and
One Unit in Cold Shutdown Relating to Emergency
Diesel Generator
Loads",
Revision
1, April 8,
1986.
The
combined
objectives
of the
two
inspections
included the following:
Review the incorporation of recommendations
of JPE into Turkey Point
EOPs.
The basis for this review was Revision
0 of JPE-M-86-18.
Review the adequacy
of licensed operator training on the
EOP revisions
resulting
from the Westinghouse
recommendations
and the recommendations
resulting
from the JPE
EDG loading evaluation.
Review resolution of the recommendations,
which are considered
commit-
ments
to
the
NRC,
as
contained
in JPE-L-86-59,
Revision
1,
dated
April 8,
1986, or in related
correspondence
including:
(1)
Unit 4 valve
and
breaker
alignments
necessary
to ensure
adequate
EDG capacity with an accident
on Unit 3 and
a loss of one of the
two
EDGs.
Review
of this
area
included
the
established
administrative controls over these
valve and breaker positions,
as
well as
a plant walkdown of the actual
alignments.
(2)
KW load limitations established
by procedures,
operator aids
and
training, or valve and breaker alignments.
(3)
Compliance
with
Confirmation
of Action Letter
(CAL) 50-250,
251/86-01 which confirmed actions to be completed prior to restart
of Units
3 and 4.
(4)
The
10 CFR 50.59 evaluation
submitted
on
EDG load limitations as
an
attachment
to JPE-L-86-59,
Revision
1
and
in
response
to
CAL 86-01.
Wal kdown
and
veri fy the throttled
val ve
positions
establ i shed
by
Special
Test 86-05
on the
CCW system.
Verify the adequacy of the revised Unit 3 startup shift staffing.
Review
Group
I
upgrade
requalification
training
effectiveness
and
progress.
II
v l.
Emergency Operating
Procedures
(EOPs)
In response
to the
EDG overload potential,
and the recommendations
contained
in
JPE-M-86-18,
the
licensee
made
significant
revisions
to
the
associated
with
LOCA or
loss
of offsite
power conditions.
The
general
philosophy utilized
by
the
Procedures
Upgrade
Plogram
(PUP)
staff
in
revising the
EOPs to meet
JPE recommendations
was to place
added actions
and
cautions
in .attachments
to the
whenever feasible.
Since the licensee
considers
the present operational restrictions
to be
a temporary condition,
this method of revision prevents
altering
the flow of the
permanent
EOPs.
This additional
reliance
on
attachments
to the
appears
to
be
less
effective
and more cumbersome
than placing the necessary
additional actions
and
cautions
directly into
the
appropriate
procedure
sections.
This
methodology
can
work provided that
each
EOP affected
by
an
attachment
contains
a reference
to the attachment,
or
a restatement
of the action or
caution
as contained
in the related attachment.
The inspection
in this area
was therefore
focused first on ensuring
that
each
recommendation
in
JPE-L-86-59,
Revision
1,
and JPE-M-86-18
was incorporated into the appropriate
EOPs,
or was adequately
resolved.
Secondly,
the attachments
and
EOPs were
compared to ensure that all
EOPs referenced
the appropriate
attachments,
and
that omissions
could not result in
a potential
over load of the
EDGs under
accident conditions.
An initial review of the
by the inspectors
noted that while many of the
JPE
recommendations
had
been
implemented
in
some
manner in the
EOPs,
there
appeared
to be
a number of omissions
and discrepancies.
An extended
meeting
was held
on Saturday,
Apri 1 5,
1986, with members of the
PUP to attempt to
resolve the identified concerns.
This was
a very constructive
meeting,
and
resulted in the resolution of several
of the concerns.
An example of an
concern
resolved
was the
requirement
in Section
2. 1. 1.2 of JPE-M-86-18 to
open breaker
MCCD-0825 prior, to resetting
a Safety Injection (SI) signal.
This step
was considered
necessary
to prevent automatic start of the
3S air
compressor
which could potentially exceed
the
EDG load limitations.
Since
all instrument air compressors
have
had the breakers
racked
out
and
danger
tagged to prevent starting, it was not necessary
to add this requirement to
the
EOPs.
During the
present
mode
of operations,
the
instrument air
compressors
have
been
replaced
by diesel air compressors
to prevent over-
loading the
EDGs.
In several
other
cases,
the
need to incorporate
a
JPE
recommendation
into
a specific
was resolved
because
the recommendation
was inserted into another
EOP which would be previously completed.
While the meeting
between
the inspectors
and
PUP personnel
resolved
a number
of EOP concerns,
other identified deficiencies
required additional revisions
of the
to in order
to
achieve
resolution.
These
deficiencies
are
considered
to
be significant in that they could have,
under
a given set of
circumstances,
resulted
in the
EDGs being overloaded.
Additionally, these
deficiencies
were
not detected
during the Plant Nuclear Safety
Committee
~'
(PNSC)
EOP reviews
and the procedures
were
approved for use
on
March 31,
1986.
Examples
of deficiencies
in the
approved
which could
have
permitted overloading
the
EDGs included the following:
JPE-M-86-18
required that for all
EDG scenarios,
the battery chargers
must
be aligned
and energized
no later than
30 minutes following a loss
of offsite power'.
This action
is essential
since
the
licensee
has
never
tested
the
capacity
of
the
safety-related
batteries
beyond
30 minutes.
The
JPE also requires
that the operating
pump
be
secured
within
20-30 minutes
of
the
event
and prior to
energizing
the
battery
chargers.
Allowing the
pump
to operate
beyond
30 minutes,
or
energizing
the battery
chargers
before
securing
the
pump,
could
overload the
EDGs.
3-EOP-E-O,
Reactor Trip or Safety Injection,
'approved
March 31,
1986,
Step
3.a
Response
Not
Obtained
(RNO)
directed
the
operator
to
3-EOP-ECA-0.0.,
Loss of'All AC Power.
ECA-0.0 was deficient in that it
did not ensure that
an
RHR pump would be secured
and
a battery charger
restored within 30 minutes.
ECA-O.O did not direct the operator
back
to
E-0
attachment
C which required energizing
the battery
charger s,
or attachment
D which required
securing
the
pump.
Attachment
E
of ECA-0.0 step 2.b contained di rection to energize
the battery charg-
ers,
but was inadequate
for several
reasons.
The entry condition for
step
2 was
an SI on Unit 4 and as
a result,
the direction to reenergize
a battery charger would not have
been
performed for an accident involv-
ing Unit 3.
Also, the directions
in step 2.b specified at 30 minutes
after reactor trip to verify adequate
diesel
capacity,
shed
loads
as
necessary,
then
place
a
battery
charger
in service
to
each
bus.
Starting at 30 minutes
and allowing
a reasonable
amount of time to shed
loads
per
attachment
D of E-0 would have placed the plant outside the
JCO
and
the
30 minutes of tested
battery capacity.
ECA-0.0 also did
not ensure
that
an
pump
was
secured
within 20 to
30 minutes
and
prior to reenergizing
a battery charger,
to prevent
overloading
the
EDGs.
Finally,
the
directions
for energizing
battery
chargers
in
ECA-0.0 Step 2.b did not specify utilizing the
"normal
bypass
switch"
for the
one
EDG available
case.
In this condition, utilizing the Reset
Switch, which is the normal
method of restoration,
could over load the
single
EDG by adding the boric acid tank heater
(15
KW) and boric acid
transfer
pumps
(27
KW).
In
response
to
these
identified deficiencies,
the
licensee
revised
ECA-O.O attachment
E on April 5,
1986.
Step
2 of attachment
E,
became
the directions for restoring battery chargers,
and
the directions for
manual
valving if an
SI occurs
on Unit 4 were
moved to step
3.
The
directions in step
2 were revised
to require that action
be
taken to
restore
the chargers
in
20 to 30 minutes,
and contain specific direc-
tions for reenergizing
the chargers
including the
use of the
bypass
~v
fl,
et
switch.
Although this revision significantly improved the procedure
and
reduced
the
chances
of overloading
an
EDG,
the fact that
the
battery chargers
must
be
energized
within
30 minutes,
and that
the
RHR pump must
be secured first, sti 1.1
needs to be emphasized.
JPE-M-86-18
Section
2. 1. 1. 10 requires that the
computer
room chiller
shall not be loaded onto
an
EDG until approximately
one hour following
'a loss of offsite power and after
a containment
spray
pump is secured
(55 minutes).
The delay in starting the computer
room chiller prevents
overloading
the
EDGs.
Licensee
test
data
indicates
a computer
room
rate of temperature
rise of 13'F/hr with no chiller on,
and controls
are
in place to maintain the normal
ambient temperature
at 67'F.
This
should
prevent
exceeding
80
F in the
computer
room
which is
the
temperature
above
which computer
card failures
have
been experienced.
3-EOP-E-0 dated April 31,
1986, did not ensure
that the
computer
room
chiller was
not started
for an
hour or unti 1 containment
spray
was
secured.
Attachment
E
step
2 directed
the
operator
to start
the
computer
room chiller within one hour of the reactor trip and loss of
offsite power.
Under these directions,
the operator could have started
the
computer
room chiller
(59
KW)
anytime
during
the . 60 minutes
following an accident,
potentially overloading
the diesel.
Attachment
D directions
were better.
They
required
the operator
to start
the
chiller in approximately
one hour,
and
noted that it should
be
done
after securing
the containment
spray
pump.
Due to the words "approxi-
mately" or "should",
however,
the potential for overloading the diesel
still exi sted.
In
response
to
the
identified deficiencies,
the
licensee
revised
3-EOP-E-0
attachment
D on April 5,
1986,
to prevent
the potential
of
overloading
the
EDGs.
Note
5 of attachment
D was revised
to require
placing the
B computer
room chiller in operation
in
55 minutes to
one
hour after
a reactor trip.
Attachment
E was not revised
and continued
to direct the operator
to start
computer
room chiller
B within
one
hour.
Since
step 3.c of E-0 directs
the operator to complete attach-
ment
E, the chiller could
be started
much earlier
than
one
hour
and
before
securing
the
containment
spray
pump.
Failure
to adequately
correct
this
deficiency
in all
will
remain
an
inspector
followup item (250,251/86-24-02)
pending resolution.
attachment
D is referenced
in several
EOPs for direction in
removing non-essential
loads
from the
EDGs during accident
conditions.
attachment
D of the version of E-0 approved
on March- 31,
1986, listed
46 separate
KW loads,
but did not differentiate
between
essential
and non-essential
loads.
An operator directed
to this attachment
t'o
remove non-essential
loads during accident
conditions
would probably
have
encountered
difficulty in determining
quickly which of the
46
listed loads were non-essential.
In addition,
several
essential
action
statements
such
as
securing
an
pump within 20-30 minutes
and
starting
a
computer
room chiller in
one
hour
were
contained
in
an
insert labeled "notes".
Placing actions
under "notes"
does
not appear
to
be consistent
with
Owners
Group guide-
lines for writing
EOPs.
Actions contained
under
"notes"
have
the
potential
to be overlooked during the stress
of emergency conditions.
In
response
to
the
identified deficiencies,
the
licensee
revised
attachment
D of E-0
on April 5,
1986.
The essential
and non-essential
loads
were
separated
which
should better
facilitate
the
removal
of
non-essential
loads during
an
emergency.
The action
statements
were
left in the insert
marked
"n'otes".
This item will remain
unresolved
(250,251/86-24-03)
pending determination
of the licensee's
commitment
to
and the Mestinghouse
PWR Owners
Group
EOP guidelines.
The inspectors
noted that the
EOPs contained
no directions to limit the
Unit 4 loads
added
to the
EDGs during
a
loss
of offsite
power
and
accident
on Unit 3.
The concern is that loads might be added to Unit 4
which could overload the'vailable
EDG, or reduce
the available
capacity
to support Unit 3 accident mitigation.
The licensee
revised
attachment
C
on April 5,
1986,
to
add
a caution:
"the unaffected
unit should
be aware or cautioned
on the effects of
EDG loading."
A Confirmation of Action letter
was issued to Florida Power and Light
confirming
EDG loading
commitments
ma'de during
a telephone
conferen'ce
on April 2,
1985.
Among the commitments
stated
were the following:
"Total loads
on emergency diesel
generators will be reduced to no
more than
2845 kilowatts per diesel
generator
and procedures will
be
changed,
and
operators
trained
on
these
changes
prior to
assuming duties, to assure
operation within this limitation."
A review of the
approved
on March 31,
1986,
indicated
inconsis-
tencies
in the
maximum
EDG load ratings stated.
3-EOP-ECA-0.2,
Loss of
All Power Recovery with SI Required,
contained
a caution that the loads
placed
on the energized
4
KV bus should not exceed
the capacity of the
power
source
EDG load rating of 2900
KW or 480 amps.
3-EOP-ECA-0. 1,
Loss of All AC Power Recovery Mithout SI Required,
contained
a similar
caution with an
EDG load rating of 2890
KW or 480 amps.
Both of these
EDG load ratings were in excess
of the 2845
KM listed in
the
Confirmation of Action letter
as
maximum
EDG loading.
Also,
a
maximum
EDG load test
conducted
in
May 1984,
only tested
the
EDGs to
2750
KW (reference
JPE-L-85-47).
The licensee
indicated to the inspectors
that the
2845
KW was
a maximum expected
EDG loading during an accident,
but that the 2950
KM for 168 hours0.00194 days <br />0.0467 hours <br />2.777778e-4 weeks <br />6.3924e-5 months <br />
was the
FSAR emergency rating and was
addressed
in the
10 CFR 50.59 review.
The licensee
committed at
the exit following the first week of inspection to place
a maximum of
10"
2845
KW
EDG loading caution
in all applicable
EOPs.
This commitment
included
those
which
had
previously just
required
that
the
capacity of the power source
not be exceeded
with no value stated.
The
revisions
made to the applicable
on April 5,
1986,
did contain
cautions
to limit the
EDG loading to 2845
KW.
In addition,
however,
the caution
statements
also
allowed additional
loads to
be placed
on
the energized
4
KV buses until the red mark, or 168 hour0.00194 days <br />0.0467 hours <br />2.777778e-4 weeks <br />6.3924e-5 months <br /> engine rating
(2950
KW) was reached
on the
KW meter for short periods.
This caution,
as inserted
in the
EOPs,
does not meet the load limitations in the
or the
verbal
commitment
made
to the
inspectors;
however, it does
fully meet
the
loading
limitations
specified
in JPE-L-86-59,
Revision
1.
This
apparent
failure
to
meet
a
commitment
to
the
Commission
was
due to the licensee'
failure to promptly notify the
Commission of a difference in understanding
of the commitment.
The
licensee
responded
quickly to resolve
most of the
EOP deficiencies
identified
during
the first week of inspection,
initiating
changes
on
Sunday,
April 6,
1986,
the
day of the exit.
These deficiencies,
however,
could have allowed operation outside of the
JCO and overloaded
the
EDGs with
a loss of all
AC power event.
This potential
should
have
been
detected
during tlie
PNSC
review
and
approval
process.
Indications
are
that
the
review, conducted
on the Saturday
evening just prior to the inspection,
was
directed
primarily towards
ensuring
each
of the
JPE
recommendations
was
incorporated
or resolved,
as
opposed
to ensuring
the
and attachments
could all interface
adequately
. to prevent
EDG overload.
The failure to
adequately
revise
EOPs to assure
that
EDG loading
was within limitations
pursuant to the Confirmation of Action letter issued
on April 2,
1986, is
a
deviation (250, 251/86-24-04).
7.
Training
The
inspectors
conducted
interviews
and
walkthrough
evaluations
of
licensed
operators
to
access
the
level
of training
on
the
EDG loading
restrictions
imposed
by JPE-L-86-59
and the revised
and attachments.
These evaluations
indicated that while the operators
were familiar with the
basic
contents
of the
attachments,
some
amount
of difficulty was
encountered
when they were walked through scenarios
requiring integrated
use
of the
and related attachments.
Part of thi s difficulty in utilizing
the
and attachments
was probably attributable to the deficiencies with
EOP and attachment
interface
as described
in Section
5.
Additionally, the
training
on these
revised
and
added
attachments
had
been primarily a
static
type of training.
Transparencies
were utilized to explain to the
operators
the
content
of each
attachment
such
as
re-energizing
battery
chargers
within
30 minutes
and
removing
non-essential
loads.
The'raining
on these
EOP revisions
and attachments
necessary
to support plant
operation
under JPE-L-86-59,
Revision
1
and JPE-N-86-18
was apparently
not
done
on
an integrated
basis
using
scenarios
on
a simulator
or plant walk-
throughs.
The
operators
expressed
the
opinion that earlier training
on
these
on the Standardized
Nuclear Utility Power Plant
(SNUPP)
simu-
lator had
been valuable,
but the
absence
of
a site specific simulator did
not allow this
type of training
on
the latest
revi sions.
Examples
of
specific deficiencies
in training included:
When placed
in certain
scenarios
such
as
a loss of all
AC power, the
operators
questioned
may not have performed
steps
necessary
to prevent
diesel
overload
such
as restoring battery
chargers
within 30 minutes,
or
removing
a
pump within
20-30 minutes.
This
was primarily
attributed to
a lack of references
between
the procedure
the operator
was
in,
and
the
attachments
to other
procedures
containing
these
actions.
The
absence
of integrated
training
on the
and attach-
ments also
appeared
to contribute to this problem.
The operators
were not adequately
familiar with the entry points into
EOP attachments.
Since
verbatim procedure
compliance
is required
and
the
lacked
appropriate
references
to attachments,
this lack of
familiarity had the potential
to place
the plant outside
the
analyzed
conditions in the JCO.
Some
steps
and sections
of the
EOP attachments
appeared
particularly
confusing
to the
operators.
An
example
was
the
action
statements
contained
within
an
insert
labeled
"notes"
in
attachment
D to
3-EOP-E-O,
Reactor Trip or Safety Injection.
The six "notes" contained
in this insert are designed
to be independent
and unrelated
actions to
be taken to prevent overloading
an
EDG in the
one
EDG available
case.
Due to the lack of integrated training
on the
use of these
attachments,
several
operators
thought these actions
were interrelated
and required
to be performed in the listed sequence.
Several
operators
demonstrated
a lack of familiarity with the locations
of controls necessary
to start the
computer
room chi llers
as directed
in note
4 of attachment
D to 3-EOP-E-O.
In isolated cases,
operators
indicated
a reluctance
to perform certain
actions
required
by
the
revised
and
attachments
which
were
contrary to the normal
mode of operation.
An example
was the require-
ment in step
3 of attachment
C to
3-EOP-E-0
to energize
a battery
charger utilizing the
"normal
bypass
switch".
Utilizing the
"normal
reset
switch",
which would
be
the
normal
method,
could result
in
overloading
the available
EDG due to auto
connected
loads.
At least
one operator indicated that
he
had been trained never to use the bypass
switch
and
hence
would
not.
This
reluctance
to
perform
actions
contained
in the
approved
and attachments
indicated
a
need for
operator
training
on
the
basis
for
unusual
actions
required
by the
EOPs.
w'Iky
l
12
The
licensee
promptly initiated
additional
training
on
the
upon
identification of the deficiencies
by the inspectors.
On-shift integrated
training in the
use of the revised
and attachments
was initiated
on
April 6,
1986.
A review the
second
week of the inspection
indicated that
the training
was
comprehensive,
and that it should resolve
the identified
concerns
in the area of EOP training.
The training included the use of the
attachments
and their'ntry points,
the
30 minute test limitations
on the
batteries,
the
basis
for
unusual
action
statements,
and
in-plant
walkthroughs of
E-0
and
ECA-0.0
under
simulated
with
an
and loss of one
EDG or loss of all
AC conditions.
The large
number of questions
generated,
and the extended
length of several
of these
training sessions,
appear to indicate the additional training in use of the
revised
and
attachments
was
both
warranted
and
effective.
The
inspectors
verified that all on-shift licensed
personnel
had received this
additional
EOP training, but noted that the
licensed
personnel
attending
accelerated
requalification training
had
not received
the training.
The
licensee
committed
to train
these
licensed
individuals prior to their
assuming
licensed
duties.
This will be carried
as inspector followup item
(250, 251/86-24-05).
Training Brief
No.
122
was
written
on April 27,
1986,
to familiarize
licensed
operators
with
new
generation
and
the
incorporation
of
Westinghouse/JPE
recommendations
concerning
EDG loading.
Training
on
the
JPE
EDG loading
recommendations
was
based
on
Revision
0 of JPE-L-86-59
dated
March 29,
1986.
The inspectors
noted that Revision
1 of JPE-L-86-59,
dated
April 3,
1986,
contained
two significant
changes
from Revision
0
including:
Revision
0 of JPE-L-86-59
Section
3. 1.a required that
no
more
than
two
CCW or
ICW heat
exchangers
shall
be
in service.
Revision
1
allowed two or three
CCW or
ICW heater
exchangers
to be in service.
Revision
0 of JPE-L-86-59
Section
3. 1.d required that the
CCW flow to
components
in service. for the unit in cold shutdown shall-be throttled
until
pump
KW load is
less
than
291
KW or
a total
system
flow of
4600
gpm.
Section
3.2 required that
ICW flow shall
be throttled until
the
pump load is less
than
209
KW or a total
system
flow of 6000
gpm.
Revision
1 allowed changes
in the configuration of CCW and
ICW provided
that the total load for the operating
pumps
on the cold
shutdown unit
does not exceed
500
KW.
Gamma-Metrics Training
On July
15,
1985,
the
Commission
issued
an
"Order Modifying Licenses
to
Confirm Additional Licensee
Commitments
on
Emergency
Response
Capability"
confirming
the
licensee'
implementation
of -Regulatory
Guide
(RG)
1.97
modifications
in accordance
with the
schedule
commitments
finalized in- a
May 10,
1985 submittal.
The July 15,
1985,
Order confirmed that the
modifications would be completed prior to the Unit 3 startup
following the
cycle
10 refueling
outage.
On
June
27,
1985,
the
licensee
submitted
a
letter to
NRR stating
that
the
Unit 3 installation
of the
neutron
flux
13
instrumentation
channels
(Gamma-Metrics)
was
complete
and the
system
was
operational
including
startup
testing,
plant
procedures,
and
operator
training.
A review of the
1985/1986 requalification curriculum and the
Gamma Metrics
neutron
flux -monitor requalification
lesson
plan during this
inspection
indicated that the licensee
completed this training for operators
licensed
prior to
February
1986,
as
part
of licensed
operator
requalification;
however,
a
review of the
replacement
Hot
License
Class
10
curriculum
revealed
that operators
receiving
licenses
after February
1986,
were
not
provided equivalent training
on the Gamma-Metrics
neutron monitor.
The
Gamma-Metrics
neutron
flux monitor
provides
reliable
neutron
flux
measurement
from reactor
shutdown to reactor full power level or from 10-'nv
to 10" nv in
a harsh
environment,
It is designed
to measure
neutron flux
with the detector
in
a high
gamma radiation
and electrical
noise
environ-
ment.
The
system
is
designed
to
operator
for
40 years
under
normal
conditions
and to survive
a design
basis
event
(DBE), providing reliable
measurement
before, during,
and after the
DBE.
On February
3-12,
1986,
the
NRC administered
reactor
operator
and 'senior
reactor operator
examinations
and requalifications
examinations
(Examination
Report
50-250/OL-86-01
and
Requalification
Examination
Report
50-250/
OL-86-01)
which contained
a
question
on
the
Gamma
Metrics
neutron
flux
monitor (RO 3.03,
SRO 6.05,
RO Requal
3.02,
and
SRO Requal 6.04).
Licensed
operators
admini stered
the requalification
examinations
were significantly
more
successful
on this question
than
the
Hot License
Class
10 candidates
reflecting the
Gamma Metrics instruction provided in 1985/1986 requalifica-
tion
training.
Subsequent
to
the written
examinations,
the
licensee
provided
the
following
comments
to
the
NRC
regarding
the
examination
question
on the
Gamma Metrics neutron flux monitor:
,"We request this question
be deleted for the following reason:
The
Gamma-Metrics
Monitor is
a
component
of the larger
safe
shutdown
system.
The Safe
Shutdown
system
has
not yet
been
turned
over for
plant
use.
A partial
turnover
of
the
Gamma-Metrics
Monitor
was
performed
in 1985.
The
Gamma-Metrics
Monitor was
functional
at
the
time but was to
be
used for indication only.
Procedure
changes
and
training were determined
to not
be necessary.
Full training will be
implemented
at
time, of safe
shutdown
system
turnover.
A training
overview was presented
to licensed operators
as "look ahead"
to inform
them
of the
new
instrument
in their control
room.
However,
the
instruction
given
was
not detailed
because
of the limited purpose
of
the Gamma-Metrics Monitor at that time."
Based
on the licensee's
response
to,the
Gamma-Metrics
neutron flux monitor
examination
question,
the
NRC
deleted
this
question
from the
reactor
operator
and
senior
reactor
operator
examination
and
requalification
examination.
The deletion of this question affected grading statistics
and
impacted the
NRC's granting of licenses
and renewal
licenses.
,I
r ly
S
b
The licensee
indicated that Hot License
Class
10 candidates
were not trained
on the
Gamma-Metrics
system
because
of the training staff's
misconception
that
the
Gamma-Metrics
system
was
not fully operational
and therefore
training
was
not
required
to
be
completed.
This
misconception
was
apparently
due to the training staff's
conclusion
that the portion of the
Gamma-Metrics modifications installing
a neutron flux channel
to the alternate
shutdown
panel
was
incomplete.
The
Gamma-Metrics
neutron
flux channels
installed in the control
room pursuant to the July 15,
1985 "Order Modifying
Licenses
to Confirm Additional Licensee
Commitments
on
Emergency
Response
Capability" were operational.
During a previous inspection
conducted
by the resident
inspection staff, the
inspectors identified that prior to August 14,
1985,
no operator training on
the
use of the
new nuclear
instrument
channels
had
been
performed.
Only
after
NRC inspectors
informed the licensee
that their June
27,
1985 letter
stated
that training
had
already
been
completed,
was
a requalification
training lesson
plan developed
and implemented.
In that
the
Gamma-Metrics
neutron
flux monitor
was
operational
in the
control
room,
required
in the
emergency
procedures
(4-EOP-FR-S.2,
Response
to Loss of Core
Shutdown,
Step 2),
and provided the only reliable
neutron
flux measurement
in
a harsh
environment pursuant to Regulatory
Guide 1.97,
the inspectors
consider that training was mandatory for Hot License Class
10
candidates.
Appendix B, Criterion XVI requires
that in the case of signifi-
cant conditions
adverse
to quality, that
measures
shall
assure
that
the
cause of the condition is determined
and corrective action taken to preclude
repetition.
Contrary to the
above,
the licensee's
comments
on tlie Gamma-
Metrics neutron flux monitor examination
question
and the licensee's
failure
to provide
Gamma-Metrics training to Hot License
Class
10 candidates
were
indicative of
a
general
failure to take
adequate
corrective
actions
to
preclude repetition of deficiencies identified during
a previous
NRC inspec-
tion.
This is
a violation (250, 251/86-24-06).
In response
to this inspection
finding, the licensee
committed to provide
training
on
Gamma Metrics to those
Hot License Class
10 candidates
who were
successful
on their
NRC license
examinations
and who currently hold reactor
operator
and senior reactor operator licenses.
Implementation of
EDG Loading Compensatory
Controls
To comply with the Justification
for Continued
Operation with One Unit at
Power
and
One Unit in Cold Shutdown Relating to Emergency
Diesel Generator
Loads (JPE-L-86-59,
Revision 1),
and (JPE-M-86-18,
Revision 0), the licensee
established
clearance
number 86-3-166.
This clearance
allowed the placement
of danger
tags to ensure
the proper position for components
necessary
to
prevent
overloading
the
EDGs.
The
inspectors
verified
through
plant
walk-downs that all components listed in the
JCO were correctly positioned
with the required administrative
controls
(tags)
in place.
The inspectors
also verified the following JCO recommendations:
i '
15
Section 3.0 required that the total
pumping loads
on Unit 4 CCW/ICW be
limited to
500
KW to provide additional
EDG margin.
Section
3. 1
and
3.2
provided
a list of
and
ICW valves
supplying
non-essential
Unit 4
loads
that
should
be
closed
to
ensure
that
the
500
KW pump
loading
is
not
exceeded.
The
inspector
verified
closed
and
administratively controlled all Unit 4 valves listed in Section
3. 1 and
3.2.
A danger
tag,associated
with clearance
86-3-166
was
found with
the
wrong clearance
number
and
was promptly resolved
by the licensee.
Additionally, the inspectors
were concerned that the level of approval
to remove the
EDG loading clearance
was not sufficiently high enough in
the
licensee's
management
organization.
Subsequently,
the
licensee
added
the Operations
Supervisor
and the Operations
Superintendent
to
the clearance
for approval.
This resolved
the inspector's
concerns.
Sections
3. l.d and 3.2.d required that the
CCW/ICW flows to the Unit 4
components
in service
be throttled unti 1
the
combined
pump
loads
do
not
exceed
500
KW.
The
inspector
verified that
the
ICW/CCW heat
exchanger
valves
were throttled
to
ensure
that
the
500
KW was
not
exceeded
and were administratively cont'rolled.
The inspector indicated
to the licensee
that locks might provide
more positive control
than
danger
tags over these throttled valves
and
the licensee
committed to
install locks.
JPE-M-86-18,
Revision
0,
Section
2. 1. 1. 1, required that
each control
room
KW meter
and
ammeter
be
marked to help ensure
that the
load limits were
not exceeded.
The inspector
verified that the con-
trol room meters
were
marked
in accordance
with the table
in Section
2. 1
~ 1. 1.
The
maximum
KW and
ampere
ratings were marked with red tape
and the normal
maximum loading of 2845
KW was marked with orange
tape.
It should
be noted,
however, that the red marker
KW values
ranging from
2910
KW to 2960
KW were in excess
of the
maximum value of 2845
con-
tained in the
CAL.
JPE-M-86-18,
Revision 0,
Item 2,
requires
that
the
instrument
air
compressors
be
deenergized
to prevent
overloading
the
and
be
replaced
by portable
diesel
compressors.
The inspector verified that
the electrical
breakers
for all instrument air compressors
were
racked
out and tagged
under
a clearance.
JPE-M-86-18 Revision,
0 Item 2. 1.3. 1, requires that the Unit 4 high head
safety injection
(HHSI) and containment
spray
pumps
be prevented
from
starting to prevent overloading the
EDGs.
The inspector verified that
these
pumps were in the pull-to-lock position
and caution tagged.
JPE-L-86-59,
Revision
1, Item 2.2, requires that the computer
room tem-
peratures
be limited to 67
F during
normal
operations.
At a
13 /hour
rate of temperature
rise, this limitation will allow a one. hour delay
in restarting
.the
computer
room chiller on
a
loss
of offsite
power
reducing
the initial EDG loading requirements.
The inspector verified
the
computer
room temperature
to
be
less
than
67'F
and
that
the
ql '
16
temperatures
are
logged
twice
per
shi ft to
ensure
thi s limit i s
maintained.
JPE-M-86-18,
Revision
0,
Item
2. 1. 1. 1
recommends
that
the
KW and
ammeters
for the
be calibrated
on
a monthly basis to ensure
the
are
not
overloaded.
The
inspector
reviewed
the
initial
calibration
pack'ages
for the
A and
B
(Work Orders
058980
and
047797 .respectively)
that were
completed
on
March 24,
1986
and
they
appeared
acceptable.
In addition,
the monthly calibration tests
were
under development
and scheduled
to be
implemented within one
month of
" the initial calibrations.
A review of the monthly calibrations will be
an inspector
followup item (250, 251/86-24-07).
The licensee
determined
that
on
a loss of the
"B" EDG, that
a single
failure of battery
3B could prevent
the automatic transfer of motor
control center
(MCC) "D" to the
"A" EDG.
MCC "D" supplies
essential
loads
including
two battery
charger s
and
an
emergency
containment
cooler.
A modification (PC/M-86-047)
was completed to allow a transfer
of
"D"
on
a loss'f
the
"B"
even without battery
"3B"
available.
The inspector
reviewed this modification package
and the
corresponding
safety evaluation
and they
appeared
adequate
to resolve
the identified deficiency.
On April 14,
1986 at
1:05 a.m.,
the licensee
deenergized
the
4B 4160 volt
bus to perform Appendix
R upgrade modifications
on Unit 4.
The deenergized
4B 480 volt load center,
which is normally powered
by the
4B 4160 volt bus
was reenergized
from the
4A 4160 volt bus via crosstie
breakers
with the
4A
480 volt load center.
At 5:20 p.m.,
approximately
16 hour1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> s after entering
this
abnormal
alignment,
the
licensee
restored
the
normal
power
supply
alignment to the 480 volt load centers.
Supplying
power
to
the
4B
480 volt
loads
via
the
4A
4160 volt bus
represented
an
emergency
diesel
generator
(EDG)
loading
case
that
was
unanalyzed
in the licensee'
Justification for Continued Operation with One
Unit at
Power
and
One Unit in Cold Shutdown
Relating to Emergency
Diesel
Generator
Loads (JPE-L-86-59,
Revision
1) transmitted
to the
NRC by letter
dated April 8,
1986.
In that safety evaluation,
the licensee
assumed that
the
4160 volt busses,
480 volt load
centers
and
480 volt motor control
centers
remained
in their normal configuration
as described
in
FSAR Section
8.2.
Energizing
the
4B loads
via
the
4A 4160 volt bus violated
these
assumptions
and
placed
unanalyzed
loads
on the
4A bus which potentially
could have
exceeded
loading limitations placed
on the
"A"
EDG specified
in
JPE-L-86-59,
Revision
1.
A subsequent
safety evaluation
(JPE-L-86-63) of the April 14,
1986 alignment
of the
4B
loads
and their effect
on
the total
EDG loading
assumed
in
JPE-L-86-59,
Revision
1 concluded that the post-accident
loading of the "A"
EDG would not have
exceeded
the loading
assumed
in JPE-L-86-59,
Revision
1.
JPE-L-86-63
identified the
"C" boric acid
tank
heater
and
the
analyzer
heat tracing
as the only loads which would have
auto
connected
to
the
"A" EDG.
This represents
an additional
21
KW to the
"A" EDG loading;
17
however,
during the time that the crosstie
was in effect,
the
4D normal
containment
cooler,
also
powered
from the
4B load center
and representing
64
KW, was maintained deenergized
with breaker clearances
in place.
There-
fore,
the net result of this specific
EDG loading
case of April 14,
1986,
represented
an
actual
43
KW reduction
below
the
loading
assumed
in
JPE-L-86-59,
Revision
1.
The safety evaluation
conducted
by the licensee
pursuant
to
provided justification for continued operation of Unit 3 with Unit 4 in cold
shutdown relating to
EDG loads
and concluded that by following the actions
and recommendations
specified in JPE-L-86-59,
Revision
1, that post-accident
loading
would
be
limited to
2845 kilowatts
per diesel
generator.
Contrary to
10 CFR 50.59, for approximately
16
hours
on April 14,
1986,
the
licensee
added
additional
auto
connected
loads
to the
4A
EOG beyond
those
analyzed
in JPE-L-86-59,
Revision
1, without first evaluating their
impact
on
EDG loading.
This is
a violation (250, 251/86-24-08).
The crosstie
of the
4B 480 volt load center to the
4A 480 volt load center
was
accomplished
under
clearance
number
86-4-063
and
in
accordance
with
approved operating
procedure
4-0P-006,
480 Volt Switchgear
System to support
PCM 83-155 (Appendix
R Modifications).
Operating
procedure
4-OP-006 did not
incorporate
necessary
procedural
instructions,
nor
did
the
licensee
established
administrative
controls (i.e.,
tagging
the tie breakers)
to
preclude
invalidating the safety evaluation
in JPE-L-86-59,
Revision
1 by
cross-tieing
480 volt load centers.
In addition,
the
licensee
had
not
sufficiently sensitized
shift supervisors
to the
requirement
for
a formal
evaluation
prior to
adding
loads
to the
beyond
those
assumed
in
JPE-L-86-59,
Revision
1
Subsequent
to
the
480 volt
load
center
crosstie,
the
licensee
placed
clearance
tags
on the
480 volt tie breakers
to preclude
future problems.
Additionally, the licensee
issued
correspondence
to all plant supervisors
on
April 17,
1986,
emphasizing that
no electrical
system cross
connects
between
trains
can
be
made
without first discussing
the
new alignment with the
corporate
engineering staff.
Discussions
with the
licensee
indicated that their procedural
reviews to
assure
that
the
2845 kilowatt diesel
generator
load limitation is
not
exceed
included only the
emergency
operating
procedures.
The
Confirma-
tion of Action letter transmitted
to Florida
Power
and Light on April 2,
1986,
confirmed that total
loads
on
emergency
diesel
generators
will be
reduced
to
no
more
than
2845
kilowatts
per diesel
generator
and that
procedures
will be
changed
to
assure
operation
within this limitation.
Contrary to this commitment,
the
licensee
did not revise
operating
proce-
dure
4-0P-006,
480 Volt Switchgear
System to assure
that diesel
generator
loading
remained
no
more
than
2845 kilowatts.
This is another
example of
deviation (250, 251/86-24-04).
18
10.
Special
Test 86-05,
Component
Cooling Water Flow Balancing
The
CCW discharge 'valves
on the residual
heat
removal
(RHR) heat
exchangers
had been throttled to approximately
30 percent valve throttling positions to
prevent the
RHR tube vibration problems that
had been
experienced
at Indian
Point.
Although the
RHR heat
exchanger
tubes
were modified at Turkey Point
in 1974 to eliminate this concern,
the throttling valves were never returned
to their initial positions.
An evaluation
by the
FP8 L Safety
Engineering
Group indicated that at 30 percent,
the valves
were probably throttled too
much to assure
adequate
post accident
flow with only one
CCW pump and one
RHR'heat exchanger in. service.
Only one
CCW pump would be available if one
was
Special
Test
86-01
demonstrated
that
the
CCW flow
through
the
heat
exchanger
in
the
post-LOCA
recirculation
phase
alignment
was
less
than
the
minimum required.
In addition,
with these
throttling valves
opened to'he
100 percent position,
the
CCW flows to the
emergency
containment coolers,
containment
spray
pump seal
coolers,
and
pump -seal
coolers
was
less
than
the
required
flows.
On
March 18,
1986,
Special
Test
86-05
was
performed
on Unit 3 to balance
system flows and to
ensure that the minimum and
maximum flow rates to safety related
components
were
within
the
design
requirements.
This test
established
throttling
positions for the
CCW discharge
valves
from the
RHR heat
exchangers
(748
A
and B) of 35 and
38 percent.
These valves were verified by the inspector to
be under administrative controls,
and that
a flow test must be conducted
to
reset
the valve positions
whenever
the valves
are adjusted
or closed for
maintenance.
It was
noted
that this
flow balance
test
has
not
been
conducted for Unit 4 and should
be completed prior to restart of this unit.
This will be
an inspector
followup item (250, 251/86-24-09).
11.
Revised Shift Staffing
Due
to
the
adverse
results
of
an
NRC
administered
requalification
examination
and
the
resultant
accelerated
requalification
training,
a
shortage
of experienced
licensed
personnel
were available
to
support
the
restart
of Unit 3.
A temporary shift staffing plan consi sting primarily of
newly licensed
personnel
supplemented
by experienced
licensed
advisors
was
developed
by the
licensee
and
approved
by the
Region.
Subsequent
to
NRC
approval,
promotions,
and transfers
between
shifts
necessitated
several
changes
to this shift staffing.
The inspectors
reviewed the qualifications
of the replacement
personnel
and they appeared
to be equivalent.
Although a
Special
Instruction Letter
had
been
issued
on March 22,
1986,
to provide
guidelines for this interim staffing, the inspectors
expressed
concern
that
there
was
no
procedure
or directive indicating
whether
the
and
advisors could leave the control
room during operation
and for how long.
In
response
to the inspector's
concern,
the licensee
issued
an
addendum to the
guidelines
on April 3,
1986 .
This
addendum
required that the
SRO advi sors
remain
in the control
room in Modes
1,
2,
3, or 4.
The
SRO advisor could
leave the control
room in these
modes for up to
15 minutes
to check vital
equipment,
provided
he remains
in radio communication.
The
RO advisor is to
remain in the control
room in Modes
1, 2, 3, or 4 and
may leave the control
room
only
when
relieved
by
another
advisor.
This directive
appeared
adequate
to meet the inspector's
concern.
19
12.
Accelerated
Requali fication Training
An evaluation
of the results
of requalification
examinations
administered
on
February 3-11,
1986,
as
documented
in
Turkey
Point Requalification
Examination-
Report
50-250/OL-86-01,
determined
that
the
Turkey
Point
Requalification
Program
was unsatisfactory.
As a result of this determina-
tion, the licensee
en'tered
an accelerated
requalification
program for all
licensed
operators
who
were
- not
successful
on
the
NRC
administered
requalification
examinations,
or
who
had
not
been
administered
the
examination.
The Accelerated Requalification
Program consists
of five weeks of classroom
instruction
in the
areas
of Reactor
Theory,
Thermodynamics,
Systems
and
Procedures
supplemented
by directed self-study
and plant walkthroughs.
The
licensee
plans
on three
accelerated
requalification
classes.
The first
class will complete accelerated
requalification
on April 26,
1986.
The
inspectors
reviewed
the administration
of selected
portions
of the
Accelerated
Requalification
Program.
Curriculum
development
included
a
content
analysis
of
NRC examinations,
an operator
performance
analysis
of
the
NRC examination,
and
a
survey
of operators
to determine
what
they
perceived
as
necessary
training needs.
Contact
hours
were determined
for
each topic selected
in the development
of the curriculum,
and instructor s
were
scheduled
to teach
the topics
through the five weeks of accelerated
requalification.
Learning objectives
were well developed
and
formal
lesson
plans
were
available
for
each
instructional
topic.
Walkthroughs
were
scheduled
with formal evaluation objectives
developed for each task.
Student
evaluations
consisted
of numerous
quizzes,
two examinations
and
a
final
examination.
The
average
scores
on
the
two
examinations
for
accelerated
Requalification Class I were 85.5% and 89.9%, respectively.
Within this area,
no violations or deviations
were identified.
13.
Licensee Action on Previous Inspection
Items
(Open) IFI (250,251/85-22-01),
Resolution of abnormally large
PWO backlog
and
their assigned priority.
The inspector
was informed by the licensee that the
backlog
was being addressed
in the following manner:
the
IKC backlog will
be placed
in
a separate
category
and
a separate
group of I&C technicians
will be assigned
to work on reducing this backlog.
Prior to being placed in
the
new category,
all
PWOs will be walked
down to verify their validity.
All new
PWOs will be classified
as "real
time work" and will be
worked
as
they
are
generated.
Additionally, 'the inspector
was
informed that
a
new
computer
system will be placed into operation
by the
end of April to monitor
all maintenance
indicators
which includes
the El'ectrical,
Mechanical,
and
IKC
PWO backlogs.
The licensee
has instituted
a morning meeting with the
off-going shift supervisor
and the maintenance
department
heads
to determine
the "hot items list" major work items.
This will aid in ensuring
that all
high priority work receives
the
appropriate
attention.
Since
the
PWO
Cg
20
backlog
was essentially at the
same
high level
as previously noted,
the
PWO
backlog IFI will remain open.
(Closed)
IFI (250,251/85-22-06),
Administrative Procedure
0103. 15 requires
that each department retain records of personnel
trained
on feedback
items
for
a minimum of only six months.
The Turkey Point Technical Specification
6. 10.2.g.
requires that traini'ng records
be maintained for the duration of
the operating license,
or duration of employment.
The procedure
needs
to be
consistent
with
Technical
Specifications.
The
inspector
reviewed
AP 0103. 15, Operating
Experience
Feedback,
revision dated
November 27,
1985,
and the retention requirements
for feedback training have
been
removed
from
the
procedure.
With
the
require'ment
removed
from
the
procedure,
the
licensee
must retain
feedback
training
records
in
accordance
with
the
Technical Specifications.
This item is closed.
(Closed)
IFI (250,251/85-22-07),
The licensee
committed
of 120 volt vital instrument
panel
procedures
to include
actions to be taken to stabilize the unit following loss
bus.
The inspector
reviewed'rocedures
3/4-0NOP-003.6,
~ Instrument
Panel,
revision
dated
March 25,
1986.
These
immediate operator actions to
be
taken following a loss
instrument panel.
This item is closed.
to revise the loss
immediate operator
of a
120 volt vital
Loss of 120V Vital
procedures
include
of 120 volt vital
(Closed)
IFI
(250,251/85-22-08)
The
licensee
committed
to
provide
appropriate
identification for relay
and
fuses
and
to provide
adequate
lighting for the
cabinet
containing
the
pressurizer
heater
relays.
The
inspector
visually
inspected
the
cabinets
for
adequate
lighting
and
relay/fuse
identification
tags.
The
licensee
had
added
identification
tags to the cabinets
and the lighting appeared
adequate.
This item is closed.
(Closed) IFI (250,251/85-22-09)
The licensee
committed to remove the allowance for
15C department
personnel
to remove fuses to prevent, depressurization
of the
pressurizer
following a loss of inverter and the
120 volt vital instrument
panel.
The inspector
reviewed the subject procedures
and the allowance
has
been
removed.
This item is closed.
(Open)
IFI (250,251/85-22-10)
Complete
120 volt vital bus training for all
licensed
personnel
at Turkey Point.
The
inspector
was
unable
to verify
that all licensed
personnel
received
immediate on-shift training on the
new
off-normal procedures
for loss of 120 volt vital AC buses.
This will remain
an
open item.
(Closed) IFI (250,251/85-22-11)
Complete engineering
evaluation
and coordination
study
to determine
the
DC feed
breaker
and
inverter
input breaker trip
setpoint settings.
The inspector
reviewed Inter-Office correspondence,
from
Turkey Point Plant
to
Power
Plant
Engineering
dated
September
19,
1985,
Subject:
Exide Inverter
DC Input Breaker
Coordination.
The
Request
for
Technical
Assistance
(85.649-003),
Inverters Input
DC Breakers
Coordination
and the completed evaluation of the technical
assistance
request
established
the breaker trip setpoints.
This item is closed.
rW