MONTHYEARML17335A5551999-10-12012 October 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Surveillance Requirement 4.6.2.2.d for Spray Additive Sys to Relocate Details Associated with Acceptance Criteria & Test Parameters to Associated TS Bases ML17335A5591999-10-11011 October 1999 Supplement to Application for Amends to Licenses DPR-58 & DPR-74,replacing Correct TS Pages Inadvertently Included in 990923 Submittal.Attached Pages Also Include Appropriate Administrative Changes ML17335A5411999-10-0101 October 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising Containment Recirculation Sump Water Inventory.Calculation & non-proprietary WCAP-15302 Rept Also Encl ML17326A1571999-09-23023 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,involving Movement of Loads in Excess of Design Basis Seismic Capability of Auxiliary Bldg Load Handling Equipment & Structures ML17326A1421999-09-17017 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,to Allow Credit of Rod Cluster Control Assemblies for Cold Leg Large Break LOCA Subcriticality.Ts Pages & non-proprietary Versions of WCAP-15246 Encl.Proprietary Version Withheld ML17326A1161999-09-10010 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Surveillance Requirement 4.4.7,TS Tables 4.4-3,3.4-1 & TS Surveillance Requirement 4.11.2.2 Re RCS & Gas Storage Tank Sampling ML17326A0921999-08-17017 August 1999 Application for Amend to License DPR-58,to Change TS 3/4.4.5 & Bases for TS 3/4.4.5,3/4.4.6.2 & 3/4.4.8 to Remove voltage-based Repair Criteria,F* Repair Criteria & Sleeving Methodologies from Unit 1 TS & Clarify Bases Sections ML17325B6041999-05-21021 May 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising Limitations of Positive Reactivity Additions in Several TS Action Statements ML17325B5511999-04-19019 April 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 3/4.8.1.2, Electrical Power Systems & Associated Bases to Provide one-time Extension of 18-month Surveillance Interval for Specific SRs ML17335A3661998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,adding TS for Distributed Ignition Sys ML17335A3631998-12-0303 December 1998 Application for Amend to License DPR-58,revising TS 3/4.7.7, Sealed Source Contamination & Associated Bases to Address Testing Requirements for Fission Detectors ML17335A3591998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,making Administrative Changes to Remove Obsolete Info,To Provide Consistency Between Units 1 & 2,to Provide Consistency with Std Tech Specs,To Provide Clarification & to Correct Typos ML17335A3561998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 4.6.5.1, Ice Condenser,Ice Bed & Associated Bases to Reflect Max Ice Condenser Flow Channel Blockage Assumed in Accident Analyses ML17335A2631998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Containment Sys Bases 3/4.6.1.4 Re Internal Pressure & 3/4.6.1.5 Re Air Temp ML17335A2761998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,placing Tighter Restrictions on Amount of Time RWST Water Level Instrumentation Can Be Out of Svc Before Compensatory Actions Are Required ML17335A2671998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 3.4.1.3, RCS - Shutdown & Associated Bases to Provide Separate Requirements for Modes 4 & 5 with Loops Filled & Mode 5 with Loops Not Filled ML17335A2311998-09-14014 September 1998 Application for Amends to Licenses DPR-58 & DPR-74,changing Runout Limits for Safety Injection Pump to 675 Gpm Unless Pump Is Specifically Tested to Higher Flow Rate Not Exceeding 700 Gpm ML17335A1901998-08-28028 August 1998 Application for Amend to License DPR-58,requesting Extension of SG Surveillance,Which TSs Require to Be Performed on or Before 990408,until End of Current Refuel Cycle Currently Scheduled for Mar 2000.W/assessment of SG Degradation & TSs ML17334A7471998-06-10010 June 1998 Application for Amends to Licenses DPR-54 & DPR-78,changing Implementation Date to Reduce Boric Acid Concentration in Boric Acid Storage Sys.Attachment 1 to Ltr Contains Description of Proposed Change & Justification for Change ML17334B7011998-03-0303 March 1998 Application for Amends to TS for Licenses DPR-58 & DPR-74, Removing Word Immediately from Unit 1 Hydrogen Recombiner Surveillance Requirement 4.6.4.2.b.4 & Revising Plants TS 3/4.6.4 Bases ML17334B6561997-10-0808 October 1997 Application for Amends to Licenses DPR-58 & DPR-78,changing TSs 3/4.6.5 & 3/4.5.5 to Increase Both Minimum Required Ice Mass Per Ice Basket & Total Minimum Required Ice Mass. Proprietary Summary of Sump Inventory Calculations,Encl ML17333B0431997-09-19019 September 1997 Application for Amends to Licenses DPR-58 & DPR-74,deleting Requirement for Automatic Valve Closure Feature on RHR Sys Suction from RCS ML17333A9831997-08-11011 August 1997 Application for Amends to Licenses DPR-58 & DPR-74,allowing Filling of ECCS Accumulators W/O Declaring ECCS Equipment Inoperable ML17335A2101997-08-0101 August 1997 Application for Amends to Licenses DPR-58 & DPR-74,deleting Wording When Secondary Steam Supply Pressure Is Greater than 310 Psig from TS ML17333A8281997-03-26026 March 1997 Application for Amends to Licenses DPR-58 & DPR-74, Modifying TS 4.7.5.1.e.2 Which Describes Control Room Ventilation Sys Autostart Functions ML17333A8311997-03-26026 March 1997 Application for Amends to Licenses DPR-58 & DPR-74,changing Grammatical Correction to Wording of Unit 2 TS 3.4.8,Action a for Modes 1,2 & 3 & Returning Frequency Requirement to TS 4.7.1.2.c & 4.7.1.2.d That Was Inadvertently Deleted ML17333A7121996-12-20020 December 1996 Application for Amends to Licenses DPR-58 & DPR-74, Requesting Rev of Reactor Coolant Pump Flywheel Insp Frequency ML17334B5941996-07-11011 July 1996 Application for Amends to Licenses DPR-58 & DPR-74,revising TS to Support Operation of Unit 2 at Increased Core Rated Thermal Power of 3,588 Mwt.Rev 1 to WCAP-14489, ...Unit 2 3,600 Mwt Uprating Program Licensing Rept Encl ML17334B5901996-06-19019 June 1996 Application for Amend to License DPR-58,addressing Applicable Requirements of NRC GL 95-05, Voltage-Based Repair Criteria for Repair of Westinghouse SG Tubes Affected by Outside Diameter Stress Corrosion Cracking. ML17334B5891996-06-11011 June 1996 Application for Amends to Licenses DPR-58 & DPR-74,removing TSs Certain Requirements for Administrative Controls,Related to QA Requirements,Per Administrative Ltr 96-05 ML17333A4201996-04-0808 April 1996 Application for Amends to Licenses DPR-58 & DPR-74,moving TS 4.0.4 Exemption Statement for MSSVs Into Section 4.7.1.1 ML17333A3551996-03-12012 March 1996 Application for Amend to License DPR-74,removing TSs Re Shutdown & Control Rod Position Indication While in Modes 3, 4 & 5 ML17334B5751996-02-29029 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,revising TS to Reduce Boric Acid Concentration in Boric Acid Storage Sys from Approx 12 Percent to Approx 4 Percent by Weight. Technical Rept Presenting Justificaion for Changes Encl ML17334B5741996-02-26026 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 5.6.2 to Increase Current Limit on Nominal Fuel Assembly Enrichment for New,Westinghouse - Fabricated Fuel Stored in New Fuel Storage Racks ML17333A3201996-02-22022 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,proposing to Remove Requirement That Operations Superintendent Must Hold or Have Held Sol at Plant or Similar Reactor ML17333A3151996-02-22022 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying Table 4.8-1,DG Test Schedule by Ref Rg 1.9,Rev 3 Rather than Rg 1.108,Rev 1 Criteria for Determination of Valid DG Test ML17333A2641996-01-12012 January 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS Section 4.4.11 to Eliminate SR Demonstrating Operability of Emergency Power Supply for Pressurizer PORVs & Block Valves ML17333A2391995-12-19019 December 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 3/4.6.1.2,3/4.6.1.3,3/4.6.1.6 & 3/4.6.1.6 to Require Types A,B & C Tests (Overall Integrated & Local Containment Leakage Rate) to Be Performed Per 10CFR50,App J Option B ML17332B0111995-11-10010 November 1995 Application for Amends to Licenses DPR-58 & DPR-74,revising Ts,By Modifying Surveillance Testing of EDG During Refueling & Normal Operations ML17332A9971995-10-20020 October 1995 Application for Amends to Licenses DPR-58 & DPR-74,proposing to Add Exemption to TS 4.0.4 in Surveillance Requirements for MSIV ML17332A9111995-08-0606 August 1995 Application for Amends to Licenses DPR-58 & DPR-74,informing That Licensee Has 45 Days from Date of Issuance to Implement Amend Unless Otherwise Specified ML17334B5561995-08-0404 August 1995 Application for Exigent Amend to License DPR-58,modifying TS 4.4.5.4 & 4.4.5.5 for Repair of Hybrid Expansion Joint Sleeved SG Tubes.Proprietary W Rept WCAP-14446, Repair...Of Hybrid Expansion Joint...Tubes Encl.W Rept Withheld ML17332A8271995-06-30030 June 1995 Application for Amends to Licenses DPR-58 & DPR-74,changing TS Section 5.3.1 to Allow Fuel Reconstitution,Per GL 90-02, Suppl 1 ML17334B5501995-06-20020 June 1995 License Amend Request to Licenses DPR-58 & DPR-74,to Remove Requirements for Fire Protection Systems from Licenses & Guidance in GL 86-10,GL 88-12 & GL 93-07 ML17332A7991995-06-15015 June 1995 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 4.8.1.1.2.e.7 to Reduce Duration of Surveillance Testing for EDGs During Refueling Operations from 24 H to 8 H ML17334B5481995-05-26026 May 1995 Application for Amends to Licenses DPR-58 & DPR-74.Amends Would Support Operation of Unit 1 at SG Tube Plugging Levels Up to 30%,make One Unit 1 TS More Nearly Like Corresponding Unit 2 TS & Maintain Consistency of Unit 2 Criteria ML17334B5461995-05-26026 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying Tech Specs 3/4.3.1 (Reactor Trip Sys Instrumentation) & 3/4.3.2 (ESFAS Instrumentation) & Bases to Relocate Tables of Response Time Limits to Ufsar,Per GL 93-08 ML17332A7661995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74.Amends Would Incorporate Cycle & Burnup Dependent Peaking Factor Penalty ML17332A7741995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 5.3.1 to Allow Fuel Reconstitution,Per GL 90-02,Suppl 1 ML17332A7771995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS Table 4.3-2 to Change Main Steam Line Isolation Valve Manual Actuation Sys Surveillance Frequency from Monthly to Quarterly 1999-09-23
[Table view] Category:TEXT-LICENSE APPLICATIONS & PERMITS
MONTHYEARML17335A5551999-10-12012 October 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Surveillance Requirement 4.6.2.2.d for Spray Additive Sys to Relocate Details Associated with Acceptance Criteria & Test Parameters to Associated TS Bases ML17335A5591999-10-11011 October 1999 Supplement to Application for Amends to Licenses DPR-58 & DPR-74,replacing Correct TS Pages Inadvertently Included in 990923 Submittal.Attached Pages Also Include Appropriate Administrative Changes ML17335A5411999-10-0101 October 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising Containment Recirculation Sump Water Inventory.Calculation & non-proprietary WCAP-15302 Rept Also Encl ML17326A1571999-09-23023 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,involving Movement of Loads in Excess of Design Basis Seismic Capability of Auxiliary Bldg Load Handling Equipment & Structures ML17326A1421999-09-17017 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,to Allow Credit of Rod Cluster Control Assemblies for Cold Leg Large Break LOCA Subcriticality.Ts Pages & non-proprietary Versions of WCAP-15246 Encl.Proprietary Version Withheld ML17326A1161999-09-10010 September 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Surveillance Requirement 4.4.7,TS Tables 4.4-3,3.4-1 & TS Surveillance Requirement 4.11.2.2 Re RCS & Gas Storage Tank Sampling ML17326A0921999-08-17017 August 1999 Application for Amend to License DPR-58,to Change TS 3/4.4.5 & Bases for TS 3/4.4.5,3/4.4.6.2 & 3/4.4.8 to Remove voltage-based Repair Criteria,F* Repair Criteria & Sleeving Methodologies from Unit 1 TS & Clarify Bases Sections ML17325B6041999-05-21021 May 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising Limitations of Positive Reactivity Additions in Several TS Action Statements ML17325B5511999-04-19019 April 1999 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 3/4.8.1.2, Electrical Power Systems & Associated Bases to Provide one-time Extension of 18-month Surveillance Interval for Specific SRs ML17335A3661998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,adding TS for Distributed Ignition Sys ML17335A3631998-12-0303 December 1998 Application for Amend to License DPR-58,revising TS 3/4.7.7, Sealed Source Contamination & Associated Bases to Address Testing Requirements for Fission Detectors ML17335A3591998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,making Administrative Changes to Remove Obsolete Info,To Provide Consistency Between Units 1 & 2,to Provide Consistency with Std Tech Specs,To Provide Clarification & to Correct Typos ML17335A3561998-12-0303 December 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 4.6.5.1, Ice Condenser,Ice Bed & Associated Bases to Reflect Max Ice Condenser Flow Channel Blockage Assumed in Accident Analyses ML17335A2631998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS Containment Sys Bases 3/4.6.1.4 Re Internal Pressure & 3/4.6.1.5 Re Air Temp ML17335A2761998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,placing Tighter Restrictions on Amount of Time RWST Water Level Instrumentation Can Be Out of Svc Before Compensatory Actions Are Required ML17335A2671998-10-0808 October 1998 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 3.4.1.3, RCS - Shutdown & Associated Bases to Provide Separate Requirements for Modes 4 & 5 with Loops Filled & Mode 5 with Loops Not Filled ML17335A2311998-09-14014 September 1998 Application for Amends to Licenses DPR-58 & DPR-74,changing Runout Limits for Safety Injection Pump to 675 Gpm Unless Pump Is Specifically Tested to Higher Flow Rate Not Exceeding 700 Gpm ML17335A1901998-08-28028 August 1998 Application for Amend to License DPR-58,requesting Extension of SG Surveillance,Which TSs Require to Be Performed on or Before 990408,until End of Current Refuel Cycle Currently Scheduled for Mar 2000.W/assessment of SG Degradation & TSs ML17334A7471998-06-10010 June 1998 Application for Amends to Licenses DPR-54 & DPR-78,changing Implementation Date to Reduce Boric Acid Concentration in Boric Acid Storage Sys.Attachment 1 to Ltr Contains Description of Proposed Change & Justification for Change ML17334B7011998-03-0303 March 1998 Application for Amends to TS for Licenses DPR-58 & DPR-74, Removing Word Immediately from Unit 1 Hydrogen Recombiner Surveillance Requirement 4.6.4.2.b.4 & Revising Plants TS 3/4.6.4 Bases ML17334B6561997-10-0808 October 1997 Application for Amends to Licenses DPR-58 & DPR-78,changing TSs 3/4.6.5 & 3/4.5.5 to Increase Both Minimum Required Ice Mass Per Ice Basket & Total Minimum Required Ice Mass. Proprietary Summary of Sump Inventory Calculations,Encl ML17333B0431997-09-19019 September 1997 Application for Amends to Licenses DPR-58 & DPR-74,deleting Requirement for Automatic Valve Closure Feature on RHR Sys Suction from RCS ML17333A9831997-08-11011 August 1997 Application for Amends to Licenses DPR-58 & DPR-74,allowing Filling of ECCS Accumulators W/O Declaring ECCS Equipment Inoperable ML17335A2101997-08-0101 August 1997 Application for Amends to Licenses DPR-58 & DPR-74,deleting Wording When Secondary Steam Supply Pressure Is Greater than 310 Psig from TS ML17333A8281997-03-26026 March 1997 Application for Amends to Licenses DPR-58 & DPR-74, Modifying TS 4.7.5.1.e.2 Which Describes Control Room Ventilation Sys Autostart Functions ML17333A8311997-03-26026 March 1997 Application for Amends to Licenses DPR-58 & DPR-74,changing Grammatical Correction to Wording of Unit 2 TS 3.4.8,Action a for Modes 1,2 & 3 & Returning Frequency Requirement to TS 4.7.1.2.c & 4.7.1.2.d That Was Inadvertently Deleted ML17333A7121996-12-20020 December 1996 Application for Amends to Licenses DPR-58 & DPR-74, Requesting Rev of Reactor Coolant Pump Flywheel Insp Frequency ML17334B5941996-07-11011 July 1996 Application for Amends to Licenses DPR-58 & DPR-74,revising TS to Support Operation of Unit 2 at Increased Core Rated Thermal Power of 3,588 Mwt.Rev 1 to WCAP-14489, ...Unit 2 3,600 Mwt Uprating Program Licensing Rept Encl ML17334B5901996-06-19019 June 1996 Application for Amend to License DPR-58,addressing Applicable Requirements of NRC GL 95-05, Voltage-Based Repair Criteria for Repair of Westinghouse SG Tubes Affected by Outside Diameter Stress Corrosion Cracking. ML17334B5891996-06-11011 June 1996 Application for Amends to Licenses DPR-58 & DPR-74,removing TSs Certain Requirements for Administrative Controls,Related to QA Requirements,Per Administrative Ltr 96-05 ML17333A4201996-04-0808 April 1996 Application for Amends to Licenses DPR-58 & DPR-74,moving TS 4.0.4 Exemption Statement for MSSVs Into Section 4.7.1.1 ML17333A3551996-03-12012 March 1996 Application for Amend to License DPR-74,removing TSs Re Shutdown & Control Rod Position Indication While in Modes 3, 4 & 5 ML17334B5751996-02-29029 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,revising TS to Reduce Boric Acid Concentration in Boric Acid Storage Sys from Approx 12 Percent to Approx 4 Percent by Weight. Technical Rept Presenting Justificaion for Changes Encl ML17334B5741996-02-26026 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 5.6.2 to Increase Current Limit on Nominal Fuel Assembly Enrichment for New,Westinghouse - Fabricated Fuel Stored in New Fuel Storage Racks ML17333A3201996-02-22022 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,proposing to Remove Requirement That Operations Superintendent Must Hold or Have Held Sol at Plant or Similar Reactor ML17333A3151996-02-22022 February 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying Table 4.8-1,DG Test Schedule by Ref Rg 1.9,Rev 3 Rather than Rg 1.108,Rev 1 Criteria for Determination of Valid DG Test ML17333A2641996-01-12012 January 1996 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS Section 4.4.11 to Eliminate SR Demonstrating Operability of Emergency Power Supply for Pressurizer PORVs & Block Valves ML17333A2391995-12-19019 December 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 3/4.6.1.2,3/4.6.1.3,3/4.6.1.6 & 3/4.6.1.6 to Require Types A,B & C Tests (Overall Integrated & Local Containment Leakage Rate) to Be Performed Per 10CFR50,App J Option B ML17332B0111995-11-10010 November 1995 Application for Amends to Licenses DPR-58 & DPR-74,revising Ts,By Modifying Surveillance Testing of EDG During Refueling & Normal Operations ML17332A9971995-10-20020 October 1995 Application for Amends to Licenses DPR-58 & DPR-74,proposing to Add Exemption to TS 4.0.4 in Surveillance Requirements for MSIV ML17332A9111995-08-0606 August 1995 Application for Amends to Licenses DPR-58 & DPR-74,informing That Licensee Has 45 Days from Date of Issuance to Implement Amend Unless Otherwise Specified ML17334B5561995-08-0404 August 1995 Application for Exigent Amend to License DPR-58,modifying TS 4.4.5.4 & 4.4.5.5 for Repair of Hybrid Expansion Joint Sleeved SG Tubes.Proprietary W Rept WCAP-14446, Repair...Of Hybrid Expansion Joint...Tubes Encl.W Rept Withheld ML17332A8271995-06-30030 June 1995 Application for Amends to Licenses DPR-58 & DPR-74,changing TS Section 5.3.1 to Allow Fuel Reconstitution,Per GL 90-02, Suppl 1 ML17334B5501995-06-20020 June 1995 License Amend Request to Licenses DPR-58 & DPR-74,to Remove Requirements for Fire Protection Systems from Licenses & Guidance in GL 86-10,GL 88-12 & GL 93-07 ML17332A7991995-06-15015 June 1995 Application for Amends to Licenses DPR-58 & DPR-74,revising TS 4.8.1.1.2.e.7 to Reduce Duration of Surveillance Testing for EDGs During Refueling Operations from 24 H to 8 H ML17334B5481995-05-26026 May 1995 Application for Amends to Licenses DPR-58 & DPR-74.Amends Would Support Operation of Unit 1 at SG Tube Plugging Levels Up to 30%,make One Unit 1 TS More Nearly Like Corresponding Unit 2 TS & Maintain Consistency of Unit 2 Criteria ML17334B5461995-05-26026 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying Tech Specs 3/4.3.1 (Reactor Trip Sys Instrumentation) & 3/4.3.2 (ESFAS Instrumentation) & Bases to Relocate Tables of Response Time Limits to Ufsar,Per GL 93-08 ML17332A7661995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74.Amends Would Incorporate Cycle & Burnup Dependent Peaking Factor Penalty ML17332A7741995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS 5.3.1 to Allow Fuel Reconstitution,Per GL 90-02,Suppl 1 ML17332A7771995-05-25025 May 1995 Application for Amends to Licenses DPR-58 & DPR-74,modifying TS Table 4.3-2 to Change Main Steam Line Isolation Valve Manual Actuation Sys Surveillance Frequency from Monthly to Quarterly 1999-09-23
[Table view] |
Text
P.,CCELERATED D RIBUTION DEMONS TION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
ACCESSION NBR:9102220136 DOC.DATE: 91/02/15 NOTARIZED: NO DOCKET FACIL:50-315 Donald C. Cook Nuclear Power Plant, Unit 1, Indiana 6 05000315 50-316 Donald C. Cook Nuclear Power Plant, Unit 2, Indiana 6 05000316 AUTH. NAME AUTHOR AFFILIATION ALEXICH,M.P. Indiana Michigan Power Co. (formerly Indiana & Michigan Ele RECIP.NAME RECIPIENT AFFILIATION R MURLEY,T.E. Document Control Branch (Document Control Desk)
SUBJECT:
Application for amends to Licenses DPR-58 6 DPR-74, consisting of miscellaneous administrative changes to Tech Specs.
DISTRIBUTION CODE: AOOID TITLE: OR Submittal: General COPIES RECEIVED:LTR D'ribution t ENCL i SIZE: l NOTES RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD3-1 LA 1 1 PD3-1 PD 1 1 COLBURN,T. 2 2 D INTERNAL: NRR/DET/ECMB 9H 1 1 NRR/DET/ESGB 1 1 S NRR/DOEA/OTSBll 1 1 NRR/DST 8E2 1 1 NRR/DST/SELB 8D 1 1 NRR/DST/SICB 7E 1 1 NRR/DST/SRXB 8E 1 1 NUDOCS-ABSTRACT 1 1 0 1 0 OGC/HDS2 1 0 EG FI 01 1 1 RES/DSIR/EIB 1 1 EXTERNAL: NRC PDR 1 1 NSIC 1 1 D
D NOTE TO ALL "RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED! /'7 TOTAL NUMBER OF COPIES REQUIRED: LTTR ~/y ENCL
Indiana Michigan Power Company P.O. Box 16631 Columbus, OH 43216 AEP:NRC:1137 Donald C. Cook Nuclear Plant Units 1 and 2 Docket Nos. 50-315 and 50-316 License Nos. DPR-58 and DPR-74 MISCELLANEOUS ADMINISTRATIVE TECHNICAL SPECIFICATION CHANGE REQUESTS U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, D.C. 20555 Attn: T. E. Murley February l5, 1991
Dear Dr. Murley:
This letter constitutes an application for amendment to the Technical Specifications (T/Ss) for the Donald C. Cook Nuclear Plant:
Units 1 and 2. Specifically, we are proposing to make miscellaneous administrative changes to the T/Ss of both units. A description of the proposed changes, our reasons for the changes, and our analysis concerning significant hazards considerations are included in
'ttachment 1. The proposed revised T/Ss pages are contained in Attachment 2. Attachment 3 consists of the existing T/Ss pages marked to reflect how they will be impacted by this proposed amendment.
We believe that the proposed changes will not result in (1) a significant change in the types of effluents or a significant increase in the amounts of any effluent: that may be released offsite, or (2) a significant increase in individual or cumulative occupational radiation exposure.
These proposed changes have been reviewed by the Plant Nuclear Safety Review Committee and by the Nuclear Safety and Design Review Commi.ttee.
In compliance with the requirements of 10 CFR 50.91(b)(1), copies of this letter and its attachments have been transmitted to Mr. J. R. Padgett of the Michigan Public Service Commi,ssion and the Michigan Department of Public Health.
ga: Q~eA~~/r ei<
4'o~
9102220136 910215 ADOOK 05000315 PDR
-P PDR li
t Dr. T. E. Murley AEP:NRC:1137 This document has been prepared folloving Corporate procedures that incorporate a reasonable set of controls to ensure its accuracy and completeness prior to signature by the undersigned.
Sincerely, M. . Ale ich Vice President eh Attachments cc: D. H. Williams, Jr.
A. A. Blind - Bridgman J. R. Padgett G, Charnoff NFEM Section Chief NRC Resident Inspector - Bridgman A. B. Davis - NRC Region III
/~
~0
~ ~
ATTACHMENT 1 TO AEP:NRC:1137 REASONS AND 10 CFR 50.92 ANALYSES FOR CHANGES TO THE DONALD C. COOK NUCLEAR PLANT UNIT NOS. 1 AND 2 TECHNICAL SPECIFICATIONS 9 )P2220136
0
~ ~
f' W
to AEP:NRC:1137 Page 1 The proposed changes in this Technical Specifications (T/Ss) change request are purely administrative' description of each proposed change is given below.
- 1. Add "121" to Section 2.CD 2. of Unit 2 License This section of the Unit 2 license was deleted by License Amendment 121. However, the new page states only the following:
(p) Deleted by Amendment Consequently, we request to revise this phrase to read as follows:
(p) Deleted by Amendment 121 2, Correct two s ellin mistakes on Unit 2 a e 1-7 "particulates' In T/S 1.29 the word "resine" should be "resin." In T/S 1.32 the word "particulate" should be "
3 ~ Add "avera e" to T S 2.1.1 Units 1 and 2 To make the T/S clearer and more accurate we are proposing to add the word "average" to the Limiting Condition for Operation (LCO). Currently the T/S reads:
The combination of THERMAL POWER, pressurizer pressure, and the highest operating loop coolant temperature (Tavg) shall not exceed the limits shown in Figure 2.1-1 for 4 loop operation.
We are proposing to change it to read as follows:
The combination of THERMAL POWER, pressurizer pressure, and the highest operating loop coolant average temperature (Tavg) shall not exceed the limits shown in Figure 2.1-1 for 4 loop operation.
- 4. Delete the hrase "RATED THERMAL POWER 3413 MWT " from Unit 1
~ae 2-2 As part of the analysis Westinghouse performed to support increased steam generator tube plugging, they provided Figure 2.1-1, which was later issued as part of Amendment 152. To be conservative, Westinghouse assumed a rated thermal power of 3413 MWT, as is stated on T/S page 2-2, Figure 2.1-1. However, since Unit 1 is actually rated for 3250 MWT, this statement appearing in the T/Ss is very confusing. The similar table in the Unit 2 T/Ss does not contain this statement. Consequently, we are proposing to delete this statement from the Unit 1 T/Ss.
V<p
, V I
li g A
"Ql lg
,Jg E
' b 1(
to AEP:NRC:1137 Page 2
- 5. Reflect ro er terminolo in Table 2.2-1 Units 1 and 2 We are proposing to change the wording for functional unit 17 '
in Table 2.2-1 from "Low Trip System Pressure" to "Low Fluid Oil Pressure." This change is proposed to make the T/S clearer by reflecting proper terminology. In addition, we are changing the orientation of this table from horizontal to vertical.
- 6. Correct t o ra hical error in Unit 2 T S 3.2.1 LCO The Unit 2 T/S 3.2.1 LCO currently refers to the "target ban."
This should be changed to "target band."
- 7. Correct inconsistenc in Unit 1 T S Table 3.3-5 Item 7 d T/S 4.6.5.6(a) requires the containment air recirculation fans to automatically start in 9 + 1 minutes after receiving a high-high containment pressure signal. Table 3.3.5 gives a maximum response time of less than or equal to 660 sec. This should be changed to less than or equal to 600 sec. Unit 2 is already correct. In addition, we are writing out "less than or equal to" throughout this page of the table.
- 8. Correct discre anc in Unit 2 T S Table 3.3-1 In the Unit 2 T/Ss, for item 22 of Table 3.3-1, Actions 1 and 14 are listed such that they refer to'Modes 1, 2, 3, '4, and
- 5. We are revising item 22 such that Action 1 refers to Modes 1 and 2 and Action 14 refers to Modes 3, 4, and 5.
This is consistent with Unit 1.
In addition, we are changing the orientation from horizontal to vertical for all three pages of this table.
- 9. Correct editorial error on Unit 1 a e 3 4 3-33 Functional unit 4.d currently reads:
- d. Steam Flow in Two Steam Lines--
High Coincident with Tavg--Low-Low Pressure--Low
~ I lu to AEP:NRC:1137 Page 3 This should be broken into two functional units, as is the case for Unit 2. We propose the following:
- d. Steam Flow in Two Steam Lines--
High Coincident with Tavg--Low-Low e ~ Steam Line Pressure--
Low
- 10. Delete reference to reviousl deleted T S in Table 3.3-6 Units 1 and 2 Currently Action 22A-3 and Action 22B-4 in Table 3.3-6 state:
Technical Specification Sections 3.0.3, 3.0.4 and 6.9.1 13 Not Applicable.
~
However T/S 6.9.1.13 has been deleted by a previous amendment.
Consequently, we are requesting to change Action 22A-3 and Action 22B-4 to state:
Technical Specification Sections 3.0.3 and 3.0,4 Not Applicable.
- 11. Correct elevation in Unit 1 Table 3.3-10 and Unit 2 Table Item a under the heading "Auxiliary Building" in Unit 1 Table 3.3-10 incorrectly lists elevation 587. The correct listing for item a is elevation 573. Item d under the heading "Auxiliary Building" in Unit 2 Table 3,3-11 lists elevation 587, when elevation 573 should be listed first (it is the lowest elevation). Therefore, item d has become item a and items a through f are relettered accordingly, 12, Correct terminolo in Unit 1 T S Table 3.3-11 and Unit 2 T S Table 3.3-10 Item 11 in these tables refers to a footnote that says,
"~PRODAC250 subcooling margin readout can be used as a substitute for the subcooling monitor instrumentation."
Reference to the "PRODAC 250" is interpreted to be the plant process computer (PPC). The PRODAC 250 computer was replaced by the new PPC ~ Consequently, we are proposing to revise the subject phrase to read as follows: "PPC subcooling margin readout can be used as a substitute for the subcooling monitor instrument."
Qi to AEP:NRC:1137 Page 4 In addition, we are deleting the following note from the bottom of the Unit 1 page, since it is no longer applies:
Amendment No, 112 (Effective before startup following the refueling outage currently scheduled in August 1989),
Likewise, this note. should be deleted from the Unit 2 page:
Amendment No. 95 (Effective before startup following refueling outage currently scheduled in early 1988).
- 13. Correct cross reference in T S 3 4.4.11.3 Units 1 and 2 Amendment 125 to Unit 1 and 112 to Unit 2 added new surveillance requirements and rearranged the order of the surveillances listed in T/S 4,8.11.2. This has resulted in improper cross references being given in T/S 3/4.4.11. For Unit 1, reference to 4.8.1.1.2b is incorrect and should be revised to 4.8.1.1.2e. For Unit 2, reference to 4.8.1,1.2c is incorrect and should be revised to 4.8.1.1.2e.
- 14. Make 2 5 4.5.2 consistent between units and provide clarification revise Unit 2 At present, Unit 2 T/S 4.5.2(a) says:
At least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by verifying that the following valves are in the indicated positions with power to the valve operator removed:
This wording implies that the valve motor breaker is to be open. In reality the breaker is closed but control power is removed. The same specification in Unit 1 is worded correctly. Consequently, we are proposing to make Unit 2 read like Unit 1, as follows:
At least once per 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> by verifying that the following valves are in the indicated positions with the control power locked out.
15 'elete Unit 1 a e 3 4 5-6a This page should have 'been deleted by Amendment No. 126. The information on Unit 1 T/S page 3/4 5-6a has been superseded by that on page 3/4 5-6. Consequently, we are requesting that page 3/4 5-6a be deleted.
,P l
to AEP:NRC:1137 Page 5
- 16. Make T S 3 4 6.1.3 consistent between units Units 1 and 2 To clarify T/S 4.6.1.3.b for both units, we wish to change the partial sentence "After each opening, except when the air lock is being used for multiple entries, when it shall be done at least once per 3 days, by performing . . ." to "Within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> following each closing, perform We also propose the following editorial changes:
o T/S 3.6.1.3(b), both units, write out "less than or equal to" o T/S 3 '.1.3(b), Unit 2, change "12.0" to "12" o T/S 4.6.1.3(c), Unit 1, replace the word "gap" with "volume" o T/S 4,6.1.3(c), Unit 2, delete the commas and insert parentheses around "12 psig."
- 17. Delete re eated lines on Unit 1 a e 3 4 6-15 We are proposing to delete the following lines from the top of page 3/4 6-15 since they appear on the bottom of page 3/4 6-14:
valve or its associated actuator, control or power circuit by performance of the cycling test, above, and verification of isolation time. h
- 18. Chan e the described function of items in Table 3.6-1 to reflect ro er terminolo Units 1 and 2 For valves listed as items D.3 through D.6 in Table 3.6-1 the term "inlet" is used to describe the function of the valve.
The terms "inlet" and "outlet" are relative, depending on your frame of reference, At Cook Nuclear Plant we typically use the term "inlet" to refer to the reactor coolant pump inlet. The proper terminology for these valves should be "outlet," since they are at the outlet of the boron injection tank.
R I
FW to AEP:NRC:1137 Page 6 Consequently, we are requesting to change the table from:
- 3. ICM - 250 Boron Injection Inlet
- 4. ICM - 251 Boron Injection Inlet
- 5. ICM - 260 Safety Injection Inlet
- 6. ICM - 265 Safety Injection Inlet tol 3 ~ ICM - 250 Boron Injection Outlet
- 4. ICM - 251 Boron Injection Outlet
- 5. ICM - 260 Safety Injection Outlet
- 6. ICM - 265 Safety Injection Outlet In addition, Items D.7 and D.8,contain an incomplete description of the valve's function. In both cases the description currently reads "RHR Suction From Sump." It should read "RHR/CTS Suction From Sump."
- 19. Provide clarification to 3.7.1.2 Units 1 and 2 Currently T/S 3,7,1.2(a) 1 and 2 read as follows:
- 1. Two feedwater pumps, each capable of being powered from separate emergency busses,
- 2. One feedwater pump capable of being powered from an OPERABLE steam supply system.
We wish to revise T/S 3.7,1.2(a) as follows to provide clarification:
- 1. Two motor-driven auxiliary feedwater pumps, each capable of being powered from separate emergency r
busses, and
- 2. One steam turbine-driven auxiliary feedwater pump capable of being powered from an OPERABLE steam supply system.
- 20. Correct t o ra hical error in T S 3 4.8.3 Unit 2 Currently the footnote says "Unit 2". This should be changed to say "Unit 1".
- 21. Delete non a licable T S surveillance re uirement from T S 4.9 '.1 Units 1 and 2 Currently T/S 4.9.7 ' reads as follows:
Crane interlocks and physical stops which prevent crane travel with loads in excess of 2,500 pounds over fuel
l 0
1, to AEP:NRC:1137 Page 7 assemblies shall be demonstrated OPERABLE within 7 days prior to crane use and at least once per 7 days thereafter during crane operation.
The requirement to verify both interlocks and physical stops on the auxiliary building crane within seven days prior to crane use whenever fuel is stored in the pit was taken directly from NUREG-0452, "Standard Technical Specifications for Westinghouse Pressurized Water Reactors," and is not totally applicable to Cook Nuclear Plant, The auxiliary building crane is not equipped with physical stops. As such, this T/S has been interpreted such that verification of the electrical interlocks alone constitutes compliance. Thus, we are proposing to delete this requirement, so that T/S 4.9 '.1 will state; Crane interlocks which prevent crane travel with loads in excess of 2,500 pounds over fuel assemblies shall be demonstrated OPERABLE within 7 days prior to crane use and at least once per 7 days thereafter during crane operation.
In addition, in the footnote we are changing "D.CD COOK - UNIT" to "Cook Nuclear Plant - Unit" ~
- 22. Delete asterisk from T S 3.9.9 Unit 2 The first line of the action statement of Unit 2 T/S 3.9.9 reads:
With the Containment Purge and Exhaust isolation system+
inoperable, The asterisk after the word "system" was not deleted as part of Amendment No. 63 when the footnote was removed.
Consequently, we are proposing to delete the asterisk in this submittal.
- 23. Ca italize defined term in T S 5.1.3 'nits 1 and 2 Technical Specification 5.1.3 currently reads as follows:
The site boundary for gaseous and liquid effluents shall be shown in Figure 5.1-3 However, the term "site boundary" is defined in T/S 1.3.6.
'Per T/S 1.1, defined terms should appear in capitalized type and we are therefore proposing to revise T/S 5.1.3 as follows:
The SITE BOUNDARY for gaseous and liquid effluents shall be shown in Figure 5.1-3.
ij tj,
"= 1 <<,II.
SI i,
id 4 to AEP:NRC:1137 Page 8
- 24. Correct t o ra hical error in Unit 1 T S 6.5.1.6 a Ve propose to correct the spelling of "proceudres" to "procedures."
- 25. Correct terminolo in T S 6.4 T/S 6.4 should be revised to reference Subpart "A" of 10 CFR Part 55, not Appendix "A" of 10 CFR Part 55.
Im act on Pendin Submittals Several of the technical specifications that we are proposing to change in this submittal are the subject of submittals pending NRC review and approval. These technical specifications and the submittals that impact them are as follows:
Unit 1 Table 3.3-5 AEP:NRC:1030 03/14/89 Table 4.3-2 T/S 3/4.7.1.2 AEP:NRC:0433N 08/07/90 T/S 6.5.1.6 AEP:NRC:0659M 08/25/89 T/S 6 '.1 Unit 2 T/S 3/4.7.1.2 AEP:NRC:0433N 08/07/90 T/S 6.4.1 AEP:NRC:0659M 08/25/89 Anal sis of Si nificant Hazards Per 10 CFR 50 '2, a proposed amendment will involve no significant hazards considerations if the proposed amendment does not:
(1) involve a significant increase in the probability or consequences of an accident previously evaluated, (2) create the possibility of a new or different kind of accident from any accident previously analyzed or evaluated, or (3) involve a significant reduction in a margin of safety,
t~ to AEP:NRC:1137 Page 9 Criterion 1 The proposed changes are purely administrative and are intended to correct errors or problems in the T/Ss. Therefore, we believe these changes do not involve a significant increase in the probability or consequences of a previously analyzed accident.
Criterion 2 Since the proposed changes are purely administrative and introduce no new operating conditions, we believe that these changes will not create the possibility of a new or different kind of accident, from any previously analyzed or evaluated.
Criterion 3 For the reasons cited in Criterion 1 above, we believe that the proposed changes will not result in a significant reduction in the margin of safety, Lastly, we note that the Commission has provided guidance concerning the determination of significant hazards by providing certain examples of amendments not likely to involve significant hazards considerations. The first example is that of a purely administrative change to the T/Ss; for example, a change to achieve consistency throughout the T/Ss, correction of an error, or change in nomenclature. We believe that the changes requested in this letter are of the type specified in this example, since they are intended to correct errors and problems in the T/Ss. Therefore, we believe this change involves no significant hazards considerations as defined in 10 CFR 50.92
1f fr I