ML17333A899
| ML17333A899 | |
| Person / Time | |
|---|---|
| Site: | Cook |
| Issue date: | 05/21/1997 |
| From: | Marcus G NRC (Affiliation Not Assigned) |
| To: | Fitzpatrick E INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG |
| References | |
| NUDOCS 9705230329 | |
| Download: ML17333A899 (4) | |
Text
Hay 21, 1997 k
E.
E. Fitzpatrick, Vice President Indiana Michigan Power Co.
Nuclear Generation Group 500 Circle Drive
- Buchanan, HI 49107
SUBJECT:
D.C.
COOK NUCLEAR PLANT DESIGN INSPECTION
Dear Mr. Fitzpatrick:
This letter is to inform you of our plans to conduct a design inspection of
, the D.C.
Cook nuclear facility.
We have scheduled the onsite portion of the inspection for the periods of August 4 through 8,
- 1997, August 18 through 29,
- 1997, and September 8 through 12, 1997.
Your staff has indicated that there are no major conflicts with on-site activities during this period.
The team leader and two team members will visit the site and corporate office in early July to collect documents necessary for the on-site portion of the inspection and to complete the badging process.
Recent NRC inspections at nuclear power reactor facilities have identified numerous findings where the plant configuration or operations were inconsistent with the design basis, licensing basis, or the UFSAR.
Therefore, the NRC has decided to perform design inspections at nuclear power reactor facilities utilizing Inspection Procedure (IP) 93801, "Safety System Functional Inspection."
Two systems will be selected for review during the inspection.
Hr. Thomas Foley, Team Leader, NRR', will interface with you and your statf regarding all matters related to this inspection.
The inspection will be performed using a team of five engineers from Stone 8 Webster Engineering Corporation (SWEC) who have been contracted by the NRC for this purpose.
Hr. Robert NaJuch of SWEC who is part of the five person team will be the lead contractor engineer We will be in contact with your staff regarding additional details for the inspection.
Should you have any questions, please contact Hr. Foley at (301) 415-1036 or me at (301) 415-1111.
Sincerely, Original signed by:
Gail H. Marcus, Director Project Directorate III-3 Division of Reactor Projects Office of Nuclear Reactor Regulation cc:
See next page Distribution:
Docket File. (50-315/316)
" PSIB R/F FPGi llespie.
NRR DOCUMENT NAME: G:NFOLEYNFOLEY.LTR PUBLIC RPZimmerman, NRR Mark Ring, RIII OFFICE DISP/NRR DISP/NRR DISP/NRR DRPE/NRR DRP/NRR NAME TFoley~
DPNorkin RMGallo JHickman ~
GHarcus DATE 5/
/97 5/
/97 5/
/97 5/
/97 5/Z i/97 P Wig ( J, p. r" 9705230329 97052i P'OQ "j '"'DR
- Doer osooosas PDR
May 21, 1997 Mr. E.
E. Fitzpatrick, dice President
ndiana Michigan Power Co.
Nuclear Generation Group 500 Circle Drive
- Buchanan, MI 49107
SUBJECT:
D.C.
COOK NUCLEAR PLANT DESIGN INSPECTION
Dear Hr. Fitzpatrick:
This letter is to inform you of our plans to conduct a design inspection of the D.". Cook nuclear facility.
We have scheduled the onsite portion of the inspection for the periods of August 4 through 8, 1997.
August 18 through 29,
- 1997, and September 8 through 12, 1997.
Your staff has indicated that there are no major conflicts with on-site activities during this period.
The team leader and two team members will visit the site and corporate office in early July to collect documents necessary for the on-site portion of the inspection and to complete the badging process.
Recent NRC inspections at nuclear power reactor facilities have identified numerous findings where the plant configuration or operations were inconsistent with the design basis, licensing basis, or the UFSAR.
Therefore.
the NRC has decided to perform design inspections at nuclear power reactor facilities utilizing Inspection Procedure (IP) 93801, "Safety System Functional Inspection."
Two systems will be selected for review during the inspection.
Hr. Thomas Foley, Team Leader, NRR, will interface with you and your staff regarding all matters related to this inspection.
The inspection will be performed using a team of five engineers from Stone 8 Webster Engineering Corporation (SWEC) who have been contracted by the NRC for this purpose.
Hr. Robert NaJuch of SWEC who is part of the five person team will be the lead contractor engineer.
We will be in contact with your staff regarding additional details for the inspection.
Should you have any questions, please contact Mr. Foley at (301) 415-1036 or me at (301) 416-1lll.
Sincerely, Original signed by:
Gail H. Marcus, Director Project Directorate III-3 Division of Reactor Projects Office of Nuclear Reactor Regulation cc:
See next page Distribution:
Docket Fi le (50-315/316)
PSIB R/F FPGillespie, NRR DOCUMENT NAME: G:KFOLEYKFOLEY.LTR OFFICE DISP/NRR DISP/NRR PUBLIC RPZimmerman, NRR Hark Ring, RIII DISP/NRR DRPE/NRR DRP/NRR 5/
/97 DATE 5/
/97 5/
/97 NAME TFol ey~
DPNorkin
'MGal 1 o JHickman ~
5/
/97 GMarcus 5/2 I/97
r
Hr.
E.
E. Fitzpatrick Indiana Michigan Power Company CC:
Regional Administrator. Region III U.S. Nuclear Regulatory Commission 801 Warrenyille Road Lisle, Illinois 60532-4351 Attorney General Department of Attorney General 525 West Ottawa Street
- Lansing, Michigan 48913 Township Supervisor Lake Township Hall P.O.
Box 818, Bridgman, Michigan 49106 Al Blind. Site Vice President Donald C.
Cook Nuclear Plant 1 Cook Place Bridgman, Michigan 49106 U.S.
Nuclear Regulatory Commission Resident Inspector's Office 7700 Red Arrow Highway Stevensville, Michigan 49127 Gerald Charnoff, Esquire
- Shaw, Pittman, Potts and Trowbridge 2300 N Street, N.
W.
Washington, DC 20037 Mayor. City of Bridgman Post Office Box 366 Bridgman, Michigan 49106 Special Assistant to the Governor Room 1 - State Capitol Lansing.
Michigan 48909 Drinking Water and Radiological Protection Division Michigan Department of Environmental Quality 3423 N. Martin Luther King Jr Blvd P.
O.
Box 30630 CPH Hai lroom
- Lansing, Michigan 48909-8130 Donald C.
Cook Nuclear Plant Hr. Steve J.
Brewer Indiana Michigan Power Nuclear Generation Group 500 Circle Drive Buchanan.
Michigan 49107