Requests Ref Matl Identified in Attachment 2 of ES-201 Be Furnished by 950301 to Prepare for Written & Operating Exams Scheduled for Wks of 950612 & 0619.W/o Encls
ML17332A525
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 01/11/1995
From: Ring M
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Fitzpatrick E
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
References
NUDOCS 9501190033
Download: ML17332A525 (4)


Text

PRlDRIT'Y Z REGULA'J6.%lÃfRMiKSRE5'MRI95ETIOFETEM (RIDE)

ACCESSION NBR:9501190033 DOC.DATE: 95/01/11 NOTARIZED: NO DOCKET FACIL:50-315 Donald C.

Cook Nuclear Power Plant, Unit 1, Indiana M '5000315 50-316 Donald C.

Cook Nuclear Power Plant, Unit 2, Indiana M

05000316 AUTH.NAME AUTHOR AFFILIATION RINGFM.A.

Region 3 (Post 820201)

RECZP.NAME RECIPIENT AFFILIATION FITZPATRICK,E.

Indiana Michigan Power Co. (formerly Indiana 6 Michigan Ele F

SUBJECT:

Requests ref matl identified in attachment 2 of ES-201 be furnished by 950301 to prepare for written

& operating exams R

scheduled for'weeks s of 950612 6 0619.W/o encls.

DISTRIBUTION CODE:

IE42D COPIES RECEIVED:LTR ENCL TITLE: Operator Licensing Examination Reports.

NOTES:

SIZE C'ECIPIENT ZD CODE/NAME PD3-1 PD INTERNAL~F1'LE CENTER 02 NRR/DRCH/HOLB EXTERNAL: NOAC COPIES LTTR ENCL RECIPIENT ID CODE/NAME HICKMAN,J NRR/DRCH/HHFB RGN3 FILE 01 NRC PDR COPIES LTTR ENCL R

D u

iPOTE TO ALL"RlDS" RECIPIENTS:

PLEASE HELP US TO REDUCE ~PASTE! COYTACTTHE DOCL'ilIENTCONTROL DESK, ROOi%1 PI -37 (EXT. 504-20S3

) TO ELIMlYATE YOUR NAME FROi!

DISTRIBL'TIOYLISTS FOR DOCI.'5!EYTS YOL'ON"INEED!

TOTAL NUMBER OF COPIES REQUIRED':

LTTR 8

ENCL

January ll, 1995 Indiana Michigan Power Company ATTN:

Mr. E.

E. Fitzpatrick Vice President 1 Riverside Plaza

Columbus, OH 43216

Dear Mr. Fitzpatrick:

In a telephone conversation between Mr. John Stubblefield, Training Supervisor, and Mr. Doug Shepard, Principal

Examiner, arrangements were made for the administration of licensing examinations at the D. C.

Cook Nuclear Power Plant.

The written and operating examinations are scheduled for the weeks of June 12 and June 19, 1995.

Your staff will be given an opportunity to review the licensing examinations in accordance with the guidelines in Revision 7 of NUREG-1021, "Operator Licensing Examiner Standards,"

(ES-201, )

during May 1995.

To prepare the examinations and meet the above schedule, it will be necessary foi your staff to furnish the reference materials identified in Attachment 2

of ES-201 by March 1, 1995.

Any delay in receiving approved and indexed reference material or the submittal of inadequate or incomplete reference material may result in the examinations being rescheduled.

The NRC will prepare and administer the written examinations in accordance with ES-401 and ES-402 of NUREG-1021.

In order to conduct the requested examinations, it will be necessary for your staff to provide adequate space and accommodations on the date noted above.

The NRC's guidelines for administering the written examinations are described in ES-402, Attachment 1.

The NRC will prepare and administer the operating tests in accordance with ES-301 and ES-302 of NUREG-1021.

In order to conduct the requested operating tests, it w'ill be necessary for, your staff to make the simulation facility available on the dates noted above.

Your staff should retain the original simulator performance data (e.g.,

system pressures, temperatures, and levels) generated during the dynamic operating tests until the examination results are final.

ES-402,,

and ES-302, Attachment 1, contain a number of NRC policies and guidelines that will be in effect while the written examination and operating tests are being administered.

OsggOsi5 PDR ADOCK OBLie -yg y~

E.

E. Fitzpatrick January ll, 1995 Your staff should submit preliminary reactor operator and senior reactor operator license applications and waiver requests at least 30 days before the first examination date so that the NRC will be able to review the applications and the medical certifications and evaluate any requested waivers.

If the applications are not received at least 30 days before the examination date, a

postponement may be necessary.

Final, signed applications certifying that all training has been completed should be submitted at least 14 days before the first examination date.

This request is covered by Office of Hanagement and Budget (OHB) Clearance Number 3150-0101, which expires October 31, 1995.

The estimated average burden =is 7.7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br /> per response, including gathering, copying and mailing the required material.

Send comments regarding this burden estimate or any other aspect of this collection of information, including suggestions for reducing this burden, to the Information and Records Hanagement Branch, Hail Stop T-6 F33, Office of Information Resources Hanagement, U.S. Nuclear Regulatory Commission, Washington, D.C.

20555; and to the Paperwork Reduction Project (3150-0101),

Office of Information and Regulatory Affairs, NEOB-10202, Office of Hanagement and Budget, Washington, D.C.

20503.

I Thank you for your cooperation in this matter.

Hr. Stubblefield has been advised of the policies and guidelines referenced in this letter.

If you have any questions regarding the NRC's examination procedures and guidelines, please contact J.

Hansen at (708) 829-9722.

Sincerely,

/s/ M. A. Ring Docket No. 50-315 Docket No. 50-316 Hark A. Ring, Chief Operations Branch See Attached List To eocatvo

~ co of thea doewent indtcato in tho box "C" ~ Co utthout attach ane1 E" ~ Co wtth attach anc1 N" ~ No copy OFFICE DRS:RIII DRS:RIII DRS:RIII A)

NAHE She ard:c Burdick Rin WK DATE 01/)

1 /95 01/0 /95 Ol/ 1'/95 OFFICIAL RECORD COPY

Distribution:

Letter to E.

E. Fitz atrick Dated:

CC:

A. A. Blind, Plant Hanager James R. Padgett, Hichigan Public Service Commission EIS Coordinator, USEPA Region 5 Office Hichigan Department of Public Health P.

F. Carteaux, Plant Training Hanager Distribution:

Docket File PUBLIC IE-01 OC/LFDCB DRP DRS RIII PRR

SRI, D. C. Cook
LPH, NRR IPAS S. A. Richards, Branch Chief, OLB W. J.

Kropp, Section Chief, DRP