Category:Legal-Affidavit
MONTHYEARML20366A1162020-11-30030 November 2020 Korea Hydro & Nuclear Power Co., Ltd, APR1400 Response to NRC Regulatory Issue Summary 2020-02, Review of New Licensing Applications for Light-Water Reactors and Non-Light Water Reactors ML19043A8182019-01-31031 January 2019 Affidavit KAW-17-0353 of Jeong-Kwan Suh ML19043A8152019-01-31031 January 2019 Affidavit KAW-17-0271 of Jeong-Kwan Suh ML19043A8172019-01-31031 January 2019 Affidavit KAW-17-0325 of Jeong-kwan Suh ML18243A4662018-08-30030 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Affidavit from Westinghouse Electric Co ML18235A1572018-08-14014 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Samdas Technical Reports ML18233A4322018-08-10010 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Accepted Versions of Topical Report APR1400-F-A-TR-12004-P-A/-NP-A, Realistic Evaluation Methodology for Large-Break LOCA of the APR1400 ML18232A1412018-08-10010 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of Accepted Versions of Topical Report APR1400-F-M-TR-13001-P-A/-NP-A, PLUS7 Fuel Design for the APR1400. ML18218A2092018-08-0606 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 271-8290 for Question 19-15 (Rev. 5) ML18218A2042018-08-0606 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 312-8343 for Question 19-16 (Rev. 3) ML18214A5642018-07-25025 July 2018 Korea Hydro - Transmittal of Revised Technical Reports for APR1400 Design Certification ML18199A5612018-07-18018 July 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of Revised Technical Reports for APR1400 Design Certification ML18194A8552018-07-13013 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 432-8377 for Question 19-64 (Rev.7) ML18145A0822018-05-25025 May 2018 Korea Hydro & Nuclear Power Co, Ltd. - Revised Response to RAI 301-8280 for the Question 07.01-45 (Rev.2) ML18137A4722018-05-17017 May 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 128-7980 for the Question 18-18 (Rev. 1) ML18131A1042018-05-11011 May 2018 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 7-8567 for Question APR1400-4 (Rev. 1) ML18124A1472018-05-0404 May 2018 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 555-9163 for the Question 07.02-19 (Rev. 2) ML18124A1112018-05-0404 May 2018 Korea Hydro & Nuclear Power Co, Ltd - Transmittal of Revised Response to RAI 45-7883 for the Question 07.09-2 (Rev.6) ML18120A2862018-04-30030 April 2018 Korea Hydro & Nuclear Power Co, Ltd, Submittal of Revised Technical Report, Onsite AC Power System Analysis, Revision 4 ML18115A3312018-04-25025 April 2018 Korea Hydro & Nuclear Power Co, Ltd. - Submittal of Revised Response to RAI 553-9084 for the Question 18-134 (Rev.2) ML18108A4682018-04-18018 April 2018 Korea Hydro & Nuclear Power Co, Ltd - Submittal of Technical Report for APR1400 Design Certification ML18102B2212018-04-12012 April 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Response to RAI 555-9163 ML18089A5872018-03-30030 March 2018 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 45-7883 for the Question 07.09-2 (Rev.5) ML18086B7482018-03-27027 March 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Technical Reports for APR1400 Design Certification ML18082A9272018-03-23023 March 2018 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 553-9084 for the Question 18-134 (Rev.1) ML18087A1272018-03-19019 March 2018 Korea Hydro & Nuclear Power Co., Ltd. - Submittal of Technical Reports for the APR1400 Design Certification ML18081A1032018-03-14014 March 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Technical Reports on Hfe and SSA for APR1400 ML18078A6822018-03-0909 March 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Technical Reports on Seismic and Ni Basemat Design ML18067A8522018-03-0808 March 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of Revised EQ Program and Onsite AC Power System Analysis Technical Reports ML18067A8482018-03-0808 March 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 426-8492 for Question 19-53 (Rev.4) ML18057B5272018-02-26026 February 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Samdas and GSI-191 Technical Reports ML18044B0372018-02-13013 February 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Updated Technical Reports ML18029A8262018-01-29029 January 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Response to RAI 232-7864 for Question 19-7 (Rev. 2) ML18029A8602018-01-29029 January 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Supplemental Response to RAI 33-7880 ML18044B0402018-01-10010 January 2018 Westinghouse Electric Co. Application for Withholding Proprietary Information from Public Disclosure ML18044B0392018-01-10010 January 2018 Westinghouse Electric Co. Application for Withholding Proprietary Information from Public Disclosure ML17331B4682017-11-27027 November 2017 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 38-7878 for the Question 07.05-1 (Rev. 4) ML17331A3962017-11-27027 November 2017 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Response to RAI 555-9163 ML17331A3972017-11-20020 November 2017 Korea Hydro & Nuclear Power Co, Ltd - Westinghouse Electric Company Application for Withholding Proprietary Information from Public Disclosure ML18124A1482017-11-20020 November 2017 Apr_ WEC_000011, APR1400 Project- Response to RAI 555-9163 Question 07.02 19-Proprietary. ML18102B2232017-11-20020 November 2017 Application for Withholding Proprietary Information from Public Disclosure Re Apr_ WEC_000011, APR1400 Project - Response to RAI 555-9163 Question 07.02 19 - Proprietary (Proprietary) ML17290B2252017-10-17017 October 2017 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 38-7878 for the Question 07.05-1 (Rev.3) ML17261A4582017-09-15015 September 2017 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 301-8280 for Question 07.01-41 ML18044B0382017-07-26026 July 2017 Westinghouse Electric Co. Application for Withholding Proprietary Information from Public Disclosure ML15350A2151985-09-0505 September 1985 Overview Description of Core Operating Limit Supervisory System (Colss)(Rev 00-NP to CEN-312-NP) 2020-11-30
[Table view] Category:Letter
MONTHYEARML23353A1022023-12-19019 December 2023 Vendor Inspection of Korea Hydro & Nuclear Power Co. Safeguards Information Program Implementation ML20366A1162020-11-30030 November 2020 Korea Hydro & Nuclear Power Co., Ltd, APR1400 Response to NRC Regulatory Issue Summary 2020-02, Review of New Licensing Applications for Light-Water Reactors and Non-Light Water Reactors ML20143A0902020-05-13013 May 2020 Korea Hydro & Nuclear Power Co, Ltd., 10 CFR 50.46 Annual Report for the APR1400 Standard Plant Design ML21124A2362020-03-0404 March 2020 KHNP Request for Approval of New Reviewing Official ML19231A2092019-08-23023 August 2019 Nuclear Regulatory Commission Vendor Inspection Report of KHNP Washington, Dc. 05200046/2019201 ML19228A2142019-08-20020 August 2019 Signing Ceremony for the Advanced Power Reactor 1400 Design Certification ML19207A2742019-07-26026 July 2019 LLC Response to NRC Request for Additional Information No. 386 (Erai No. 9316) on the NuScale Design Certification Application ML19207A2572019-07-26026 July 2019 LLC Response to NRC Request for Additional Information No. 427 (Erai No. 9408) on the NuScale Design Certification Application ML19177A3522019-06-27027 June 2019 Vendor Inspection of KHNP Washington, DC Center Announcement Letter ML19116A2452019-04-26026 April 2019 Schedule to Complete Rulemaking and Certification of the Advanced Power Reactor 1400 Reactor Design ML19106A2642019-04-18018 April 2019 Response Letter to Charles J Poppe on APR1400 FSER ML19081A2042019-03-0808 March 2019 Letter from Charles Poppe to William Ward on APR1400 FSER ML18282A2182018-10-0909 October 2018 Korea Hydro & Nuclear Power Co., Ltd. - Review Result to Final Safety Evaluation Report for Chapter 18 ML18274A4032018-09-28028 September 2018 Korea Hydro & Nuclear Power Co., Ltd - Review Results to Final Safety Evaluation Report for Six Chapters ML18261A1872018-09-28028 September 2018 Letter from F. Brown to Kepco/Khnp Issuing the Standard Design Approval for the Advanced Power Reactor 1400 ML18263A2652018-09-28028 September 2018 Letter from R. Taylor to Korea Electric Power Corporation / Korea Hydro & Nuclear Power Co., Ltd, Issuing the Final Safety Evaluation Report for the Advanced Power Reactor 1400 Design ML18262A0632018-09-25025 September 2018 Advanced Power Reactor 1400 Design Certification Application - Final Safety Evaluation for Six Chapters - Letter ML18264A1272018-09-21021 September 2018 Korea Hydro & Nuclear Power Co., Ltd - Review Results to Final Safety Evaluation Report for Thirteen Chapters ML18262A0642018-09-19019 September 2018 Advanced Power Reactor 1400 Design Certification Application - Final Safety Evaluation for Thirteen Chapters ML18243A4652018-08-31031 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of LTR-RAM-17-81, Revision 4, Work Order 89: Response to Digital I&C Questions. ML18240A0422018-08-28028 August 2018 Korea Hydro & Nuclear Power Co., Ltd., Submittal of Confirmation of Final Safety Evaluation for the APR1400 Generic Report, Ptlm for RCS Heatup and Cooldown ML18199A3332018-08-23023 August 2018 APR1400, Generic Pressure-Temperature Limits Report, Final Safety Evaluation Report - Letter to KHNP ML18234A4292018-08-22022 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of Updated Technical Report ML18235A1572018-08-14014 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Samdas Technical Reports ML18225A1372018-08-13013 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 520-8693 for Question 06.02.02-43 (Rev.1) ML18225A3342018-08-13013 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of APR1400 Applicant'S Environmental Report (Rev.2) ML18222A2582018-08-10010 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Technical Report on CCF Coping Analysis ML18222A3492018-08-10010 August 2018 Korea Hydro & Nuclear Power Co., Ltd. - Transmittal of Response to RAI Er 1-8428 for Question EIS ACC/SA-15 (Rev.4) ML18232A1412018-08-10010 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of Accepted Versions of Topical Report APR1400-F-M-TR-13001-P-A/-NP-A, PLUS7 Fuel Design for the APR1400. ML18233A4322018-08-10010 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Accepted Versions of Topical Report APR1400-F-A-TR-12004-P-A/-NP-A, Realistic Evaluation Methodology for Large-Break LOCA of the APR1400 ML18221A5152018-08-0909 August 2018 Korea Hydro & Nuclear Power Co., Ltd. - Submittal of Response to RAI 452-8545 for the Question 10.03.06-21 (Rev.1) ML18218A2042018-08-0606 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 312-8343 for Question 19-16 (Rev. 3) ML18218A2092018-08-0606 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 271-8290 for Question 19-15 (Rev. 5) ML18218A1962018-08-0606 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 434-8352 for Question 19-92 (Rev.5) ML18180A3272018-07-31031 July 2018 APR1400 Topical Report Safety Evaluation, Realistic Evaluation Methodology for Large Break Loss of Coolant Accident of the APR1400 - KHNP Letter ML18212A3462018-07-31031 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Technical Reports for APR1400 Design Certification ML18207A2252018-07-30030 July 2018 LTR-18-0307-1 - Letter from M. Doane to M. Corradini Report on the Safety Aspects of the APR1400 Pressurized-Water Reactor ML18225A1182018-07-27027 July 2018 Ametek Solidstate Controls - Notification of Potential Defect-10CFR Part 21 ML18206B0862018-07-26026 July 2018 Report on the Safety Aspects of the APR1400 Pressurized-Water Reactor ML18269A2412018-07-26026 July 2018 APR1400 Final Safety Evaluation Report, Appendix F - ACRS Report on APR1400 Design ML18214A5642018-07-25025 July 2018 Korea Hydro - Transmittal of Revised Technical Reports for APR1400 Design Certification ML18205A6382018-07-24024 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 356-7881 for the Question 07-18 (Rev.3) ML18205A7322018-07-24024 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 558-9456 for Question 14.03.01-1 (Rev.1) ML18204A4082018-07-23023 July 2018 Korea Hydro & Nuclear Power Co, Ltd., Transmittalof Revised Response to RAI 374-8481 for the Question 18-101 (Rev.1) ML18204A4332018-07-23023 July 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 63-7983 for Question 06.02.02-13 (Rev.2) ML18207A4572018-07-20020 July 2018 Korea Hydro - Transmittal of Revised Response to RAI 112-8015 for Question 13.05.02.01-5, Revision 3 ML18201A4002018-07-20020 July 2018 LLC Response to NRC Request for Additional Information No. 491 (Erai No. 9557) on the NuScale Design Certification Application ML18207A4512018-07-20020 July 2018 Korea Hydro - Transmittal of Revised Response to Section 19.1 Issue #PRA-135, Revision 1 ML18199A5612018-07-18018 July 2018 Korea Hydro & Nuclear Power Co, Ltd., Submittal of Revised Technical Reports for APR1400 Design Certification ML18194A4152018-07-13013 July 2018 OEDO-18-00316 - Letter from M. Doane to M. Corradini Safety Evaluation of Topical Report, APR1400-F-A-TR-12004-P, Revision 1, Realistic Evaluation Methodology for Large-Break Loss of Coolant Accident of the APR1400 2023-12-19
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARML19207A2572019-07-26026 July 2019 LLC Response to NRC Request for Additional Information No. 427 (Erai No. 9408) on the NuScale Design Certification Application ML19207A2742019-07-26026 July 2019 LLC Response to NRC Request for Additional Information No. 386 (Erai No. 9316) on the NuScale Design Certification Application ML18243A4682018-08-31031 August 2018 Korea Hydro & Nuclear Power Co., Ltd - WO 89 Response to Digital I&C Questions ML18243A4652018-08-31031 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of LTR-RAM-17-81, Revision 4, Work Order 89: Response to Digital I&C Questions. ML18225A1382018-08-13013 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 520-8693 for Question 06.02.02-43, (Rev.1) ML18222A3502018-08-10010 August 2018 Korea Hydro & Nuclear Power Co., Ltd. - Response to RAI Er 1-8428 for Question EIS ACC/SA-15 (Rev.4) ML18221A5162018-08-0909 August 2018 Korea Hydro & Nuclear Power Co., Ltd. - Response to RAI 452-8545 for the Question 10.03.06-21 (Rev.1) ML18218A2092018-08-0606 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 271-8290 for Question 19-15 (Rev. 5) ML18218A2072018-08-0606 August 2018 Korea Hydro & Nuclear Power Co., Ltd - Revised Response to RAI 271-8290 for Question 19-15 (Rev. 5) ML18218A2032018-08-0606 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 312-8343 for Question 19-16 (Rev. 3) ML18218A1952018-08-0606 August 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 434-8352 for Question 19-92 (Rev.5) ML18205A7322018-07-24024 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 558-9456 for Question 14.03.01-1 (Rev.1) ML18205A7312018-07-24024 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Revised Response to RAI 558-9456 for Question 14.03.01-1 (Rev.1) ML18205A6372018-07-24024 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Revised Response to RAI 356-7881 for the Question 07-18 (Rev.3) ML18207A4562018-07-20020 July 2018 Korea Hydro - Revised Response to Request for Additional Information, APR1400 Design Certification, RAI No. 112-8015 ML18201A4002018-07-20020 July 2018 LLC Response to NRC Request for Additional Information No. 491 (Erai No. 9557) on the NuScale Design Certification Application ML18197A2972018-07-13013 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Revised Response to RAI 88-8046 for Question 03.05.02-4 (Rev.1) ML18197A2962018-07-13013 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 88-8046 for Question 03.05.02-4 (Rev.1) ML18194A8572018-07-13013 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Revised Response to RAI 432-8377 for Question 19-64 (Rev.7) ML18194A8552018-07-13013 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 432-8377 for Question 19-64 (Rev.7) ML18194A8232018-07-13013 July 2018 Korea Hydro & Nuclear Power Co., Ltd, Revised Response to RAI 316-8305 for the Question 17.04-1 (Rev. 4) ML18190A1622018-07-0909 July 2018 Korea Hydro & Nuclear Power Co, Ltd., Revised Response to RAI 420-8482 for Question 19.03-36 (Rev.2) ML18184A3682018-07-0303 July 2018 Korea Hydro & Nuclear Power Co., Ltd - Response to RAI 301-8280 for the Question 07.01-45 ML18178A5772018-06-27027 June 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI Er 1-8428 for Question EIS ACC/SA-15 (Rev.3) ML18172A3142018-06-21021 June 2018 Korea Hydro & Nuclear Power Co., Ltd - Response to Action Item 5-6 Section 5.4.2.1 Mcb Issue List Regarding APR-1400, FSAR Section 5.4.2.1 ML18172A3132018-06-21021 June 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to Action Item 5-6.11 Regarding Mcb Issue for DCD Section 5.4 ML18170A0592018-06-19019 June 2018 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 329-8424 for Question 14.03.08-13 (Rev.1) ML18162A3432018-06-11011 June 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 557-9199 for the Question 03.08.05-20 (Rev. 2) ML18155A4082018-06-0404 June 2018 Korea Hydro & Nuclear Power Co, Ltd. - Revised Response to RAI 61-7984 for Question 08.03.01-5 (Rev. 1) ML18155A4012018-06-0404 June 2018 Korea Hydro & Nuclear Power Co, Ltd. - Revised Response to RAI 297-8309 for Question 19.03-1 (Rev.2) ML18155A3932018-06-0404 June 2018 Korea Hydro & Nuclear Power Co., Ltd - Revised Response to RAI 297-8309 for Question 19.03-2 (Rev. 1) ML18155A3922018-06-0404 June 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 297-8309 for Question 19.03-2 (Rev. 1) ML18155A3822018-06-0404 June 2018 Korea Hydro & Nuclear Power Co., Ltd'S Revised Response to RAI 420-8482 for Question 19.03-36 (Rev. 1) ML18150A5832018-05-30030 May 2018 Korea Hydro & Nuclear Power Co., Ltd - Revised Response to RAI 557-9199 for the Question 03.08.05-20 ML18150A5802018-05-30030 May 2018 Korea Hydro & Nuclear Power Co., Ltd - Submittal of Revised Response to RAI 557-9199 for the Question 03.08.05-20 ML18145A0842018-05-25025 May 2018 Korea Hydro & Nuclear Power Co, Ltd. - Revised Response to RAI 301-8280 for the Question 07.01-45 (Rev.2) ML18142A2992018-05-18018 May 2018 Korea Hydro & Nuclear Power Co, Ltd. - Revised Response to RAI 255-8285 for the Question 03.08.05-7 (Rev. 5) ML18142A3062018-05-17017 May 2018 Korea Hydro & Nuclear Power Co., Ltd. - Response to RAI 554-9146 for Question 07.02-18 (Rev. 1) ML18137A4822018-05-17017 May 2018 Korea Hydro & Nuclear Power Co, Ltd. - Response to RAI 558-9456 for Question 14.03.01-1 ML18137A4742018-05-17017 May 2018 Korea Hydro & Nuclear Power Co., Ltd - Revised Response to RAI 128-7980 for the Question 18-18 (Rev. 1) ML18137A4722018-05-17017 May 2018 Korea Hydro & Nuclear Power Co., Ltd - Transmittal of Revised Response to RAI 128-7980 for the Question 18-18 (Rev. 1) ML18131A1042018-05-11011 May 2018 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 7-8567 for Question APR1400-4 (Rev. 1) ML18131A1062018-05-11011 May 2018 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 7-8567 for Question APR1400-4 (Rev. 1) ML18131A1132018-05-11011 May 2018 Revised Response to RAI 412-8525 for Question 08.04-15 (Rev. 1) ML18129A3882018-05-0909 May 2018 Korea Hydro & Nuclear Power Co., Ltd - Revised Response to Request for Additional Information for Question No. 08.01-21 ML18124A1132018-05-0404 May 2018 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 45-7883 for the Question 07.09-2 (Rev.6) ML18124A1512018-05-0404 May 2018 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 555-9163 for the Question 07.02-19 (Rev. 2) ML18121A4162018-05-0101 May 2018 Korea Hydro & Nuclear Power Co, Ltd - Revised Response to RAI 433-8363 for Question 19-83 (Rev.2) ML18120A3042018-04-30030 April 2018 Korea Hydro & Nuclear Power Co., Ltd - Response to RAI 342-8291 for Question 07.08-10 (Rev.2) ML18115A3332018-04-25025 April 2018 Korea Hydro & Nuclear Power Co, Ltd. - Revised Response to RAI 553-9084 for the Question 18-134 (Rev.2) 2019-07-26
[Table view] |