Monthly Operating Rept for Nov 1993 for DC Cook Nuclear Plant Unit 1.W/931203 Ltr
ML17331B122
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 11/30/1993
From: Blind A, Reynnells R, Doreen Turner
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9312210047
Download: ML17331B122 (9)


Text

ACCELERATEDDISTRIBUTION DEMOlTPATION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS) ssgBgso DOCKET FACIL:50-315 Donald C. Cook Nuclear Power Plant, Unit 1, Indiana M 05000315 AUTH. NAME AUTHOR AFFILIATION TURNER,D.G. Indiana Michigan Power Co. (formerly Indiana 6 Michigan Ele REYNNELLS,R.D. Indiana Michigan Power Co. (formerly Indiana & Michigan Ele BLIND,A.A. Indiana Michigan Power Co. (formerly Indiana 6 Michigan Ele RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operatin Plant Unit 1.W/ 3120 t ltr.

for Nov 1993 for DC Cook Nuclear D

DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL D

PD3-1 LA 3 3 PD3-1 PD 1 1 HICKMAN,J 1 1 D

INTERNAL: AEOD/DOA 1 1 AEOD/DSP/TPAB 1 1 NR /JUROR OEAB 1 1 NRR/DRIL/RPEB 1 1 EG~FI LE 01 1 1 RGN3 1 1 EXTERNAL EGGG BRYCE g J H 1 1 NRC PDR 1 1 NSIC 1 1 D

D D

NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 14 ENCL 14

t ~

f r '

Indiana Mic Power Com Cook Nuclear ant One Cook Place Bridgman, Ml 49106 616 465 5901 IN!NEli8$l NSCNIGQN PQSFM December 3, 1993 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555 Gentlemen:

Pursuant to the requirements of Donald C. Cook Nuclear Plant 1 Technical Specification 6.9.1.10, the attached Monthly'nit Operating Report for the month of, November 1993 is submitted.

A.A. Blind Plant Manager Attachment c! NRC Region D.R. Hahn III R.C. Callen S. Hamming J.G. Keppler INPO Records Center ANI Nuclear Engineering Department E.E. Fitzpatrick R.L. Simms W.G. Smith, Jr.

S.J. Brewer D.W. Paul S.H. Steinhart J.L. Leichner J.A. Isom D.G. Turner E.A. Smarrella J.C. Krieger B.A. Svensson D.F. Krause M.E. Russo 93122100474"',931130

'~

PDR' R......., '.PAR.

'ADOCK '05000315 I(I

, ~

li A'

N.R.C. OPERATING DATA REPORT DOCKET NO. 50-315 DATE 02/Dec/93 COMPLETED BY DG TURNER TELEPHONE 616-465-5901 OPERATING STATUS

l. Unit Name D. C. Cook Unit 1 notes
2. Reporting Period NOV 93
3. Licensed Thermal Power (MWt) 3250
4. Name Plate Rating (Gross MWe) 1152
5. Design Electrical Rating (Net MWe) 1020
6. Maximum Dependable Capacity (GROSS MWe) 1056
7. Maximum Dependable Capacity (Net MWe) 1000
8. If Changes Occur in Capacity Ratings (Items no. 3 through 7) Since Last Report Give Reasons
9. Power Level To Which Restricted.
10. Reasons For Restrictions. If Any:

If Any (Net MWe)

This Mo. Yr. to Date Cumm.

11. Hours in Reporting Period 720.0 8016.0 165816 '
12. No. of Hrs. Reactor Was Critical 720.0 8016. 0 124910 4~
13. Reactor Reserve Shutdown Hours 0.0 0.0 463 ~ 0
14. Hours Generator on Line 720.0 8016. 0 122864 ~ 6
15. Unit Reserve Shutdown Hours 0' 0.0 321 0
16. Gross Therm. Energy Gen. (MWH) 2329064 25686645 361128968
17. Gross Elect. Energy Gen. (MWH) 755360 8299570 117242930
18. Net Elect. Energy Gen. (MWH) 729175 ~

8006521 112768886

19. Unit Service Factor 100.0 100.0 75 '
20. Unit. Availability Factor 100.0 100.0 75.1
21. Unit Capacity Factor (MDC Net) 101.3 99 ' 67.8
22. Unit Capacity Factor (DER Net) 99.3 97 ' 66 '
23. Unit Forced Outage Rate 0.0 0 ~ 0 6 1

~

24. Shutdowns Scheduled over Next Six Months (Type, Date,and Duration):

to be in Februar 5 1994 for an estimated

25. If Shut Down At End of Report Period, Estimated Date of Startup:
26. Units in Test Status (Prior to Commercial Operation):

Forcast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY COMMERCIAL OPERATION

AVERAGE DAILY POWER LEVEL (MWe-Net)

DOCKET NO. ~ 50-315 UNIT ONE 02/Dec/93 02/Dec/93 DG TURNER DG TURNER TELEPHONE 616-465-5901 NOV 93 NOV 93 AVERAGE DAILY AVERAGE DAILY DAY POWER LEVEL DAY POWER LEVEL 11/Ol/93 1012 11/17/93 1021 11/02/93 1016 11/18/93 1011 11/03/93 1010 11/19/93 1019 11/04/93 1011 11/2O/93 1020 11/05/93 1014 11/21/93 1007 11/06/93 1019 11/22/93 946 11/07/93 1017 11/23/93 951 11/08/93 1020 11/24/93 1019 11/09/93 1018 11/25/93 '020 11/10/93 1023 11/26/93 1020 11/11/93 1020 11/27/93 1019 11/12/93 1019 11/28/93 1020 11/13/93 1020 11/29/93 1018 11/14/93 1020 11/30/93 1020 11/15/93 1019 0 11/16/93 1014

UNIT SHUTDOWNS AND POWER REDUCTIONS UNIT NAME: D. C. COOK UNIT 1 DATE: Dec 1, 1993 REPORT MONTH: NOVEMBER 1993 COMPLETED BY: R. D. Reynnells TELEPHONE: (616) 465-5901 Page 1 of 1 METHOD OF SHUTTING LICENSEE DURATION DOWN EVENT SYSTEM COMPONENT CAUSE AND CORRECTIVE ACTION NO. DATE TYPE HOURS REASON2 REACTOR~ REPORT NO. CODE4 CODE TO PREVENT RECURRENCE None There wer no unit shutdown or significant power reductions from 100% RTP this month.

1 2 3 4 5 F Forced Reason:

A: Equipment Failure (Explain)

Method: Exhibit G Instructions Exhibit I: Same S: Scheduled 1: Manual for preparation of data Source B: Maintenance or Test 2: Manual Scram entry sheets for Licensee C: Refueling 3: Automatic Scram Event Report (LER) File "

D: Regulatory Restriction 4: Other (Explain) (NUREG 1061)

E: Operator Training and License Examination F: Administrative G: Operational Error (Explain)

H: Other (Explain)

DO(. T NO.: 50-'3 15 UNIT NAME: D.C. Cook Unit 1 COMPLETED BY: R. D. Reynnells TELEPHONE: (616) 465-5901 DATE Dec 1, 1993 PAGE: Page 1 of 1 MONTHLY OPERATING ACTIVITIES NOVEMBER 1993 The unit entered the reporting period in Mode 1 at 1004 RTP.

The unit exited this reporting period in Mode 1 at 100% RTP.

There were no challenges to the pressurizer safety valves or power operated relief valves.

Gross Electrical generation for the month of November was 755360 MWH.

DETAILS 11-21-93 1945 Commenced reactor power decrease to 904 RTP to remove. MSR's from service.

2145 Reactor power is at 904.

11-22-93 0015 Commenced reactor power increase to 954 RTP.

02'4 0 Reactor power is at 95%.

11-24-93 0230 Commenced reactor power increase to 1004 RTP.

0355 Reactor power is at 1004 RTP.

DOCKET NO: 50-315 UNIT NAME D.C. Cook Unit 1 COMPLETED BY: M. E. Russo TELEPHONE: (616) 465-5901 DATE December 3, 1993 PAGE 1 of 1 MAJOR SAFETY-RELATED MAINTENANCE November 1993 No major safety-related maintenance items are included for the month of November.