ACCELERATED ISTRIBUTION DEMON RATION SYSTEM
"~
REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
DOCKET g
FACIL:50-316 Donald C.
Cook Nuclear Power Plant, Unit 2, Indiana M
05000316 AUTH.NAME AUTHOR AFFILIATION TURNER,D.G.
(formerly Indiana 6 Michigan Ele REYNNELLS,R.D.
(formerly Indiana 6 Michigan Ele BLIND,A.A.
(formerly Indiana
& Michigan Ele +
RECIP.NAME RECIPIENT AFFILIATION I
SUBJECT:
Monthly operatin e t for Nov 1993 for DC Cook Nuclear Plant, Unit 2.W/93120 ltr.
DISTRIBUTION CODE:
IE24D COPIES RECEIVED:LTR ENCL SIZE TITLE: Monthly Operating Report (per Tech Specs)
NOTES:
D RECIPIENT ID CODE/NAME PD3-1 LA HICKMAN,J INTERNAL: AEOD/DOA
~NEBR OEAB
~z 01 EXTERNAL EGS(G BRYCE iJ
~ H NSIC COPIES LTTR ENCL 3
3 1
1 1
1 1
1 1
1 1
1 1
1 RECIPIENT ID CODE/NAME PD3-1 PD AEOD/DSP/TPAB NRR/DRIL/RPEB RGN3 NRC PDR COPIES LTTR ENCL 1
1 1
1 1
1 1
1 1
1 D
D R
D NOTE TO ALL"RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOM P 1-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!
TOTAL NUMBER OF COPIES REQUIRED:
LTTR 14 ENCL 14 A
D D
indiana Mich Power Comp Cook Nuclear ant One Cook Place Bridgrnan, MI 49106 616 465 5901 December 3,
1993 U.S. Nuclear Regulatory Commission ATTN:
Document Control Desk Washington, D.C.
20555 Gentlemen:
Pursuant to the requirements of Donald C.
Cook Nuclear plant Unit 2 Technical Specification 6.9.1.10, the attached Monthly Operating Report for the month of November 1993 is submitted.
Respectfully, A.A. Blind Plant Manager Attachment c!
NRC Region III D.R. Hahn R.C. Callen S.
Hamming J.G. Keppler INPO Records Center ANI Nuclear Engineering Department E.E. Fitzpatrick R.L.
Simms W.G. Smith, Jr.
S.J.
Brewer D.W. Paul S.H. Steinhart J.L. Leichner J.A.
Isom D.G. Turner E.A. Smarrella J.C. Krieger B.A. Svensson D.F. Krause M.E. Russo 9312210043/931130 PDR, ADOCK'05000316 PDR l/g
1 N
N'R.C.
OPERATING DATA REPORT DOCKET NO.
50-316 DATE'02/Dec/93 COMPLETED BY DG TURNER TELEPHONE 616-465-5901 OPERATING STATUS
- 1. Unit Name D.
C.
Cook Unit
- 2. Reporting Period, NOV
- 3. Licensed Thermal Power (MWt) 4.
Name Plate Rating (Gross MWe)
.5. Design Electrical Rating (Net MWe) 6.
Maximum Dependable Capacity (GROSS MWe) 7.
Maximum Dependable Capacity (Net MWe) 2 93 3411 1133 1090 1100 1060 notes
- 8. If Changes Occur in Capacity Ratings (Items no.
3 through
- 7) Since Last Report Give Reasons 9.
Power Level To Which Restricted..If Any (Net MWe) 10.
Reasons For Restrictions. If Any:
11.
Hours in Reporting Period 12.
No. of Hrs. Reactor Was Critical
- 13. Reactor Reserve Shutdown Hours
- 14. Hours Generator on Line
- 15. Unit Reserve Shutdown Hours
- 16. Gross Therm.
Energy Gen.
(MWH) 17.
Gross Elect.
Energy Gen.
(MWH)
- 18. Net Elect.
Energy Gen.
(MWH)
- 19. Unit Service Factor
- 20. Unit Availability Factor
- 21. Unit Capacity Factor (MDC Net)
- 22. Unit Capacity Factor (DER Net)
- 23. Unit Forced Outage Rate 24.
Shutdowns Scheduled over Next Six None This Mo.
Yr. to Date 720.0 8016.0 720.0 7747.5 0.0 0;0 720-0 7715 '
0 '
0.0 1850397 22587578 585510 7234490 559610 6960623 100.0 96.3 100.0 96.3 73 '
81.9 71.3 79.7 0.0 3.8 Months (Type, Date,and Cumm.
139512 '
94105.0 0.0 91031. 9 0.0 280175350 90988520 87632795
'66. 4 66.4 60 '
58 '
15.4 Duration):
- 25. If Shut Down At End of Report Period, Estimahed Date of Startup:
- 26. Units in Test Status (Prior to Commercial Operation):
Forcast INITIALCRITICALITY INITIALELECTRICITY COMMERCIAL OPERATION Achieved
AVERAGE DAILY POWER LEVEL (MWe-Net)
DOCKET NO.
50-316 UNIT TWO 02/Dec/93 02/Dec/93 DG TURNER DG TURNER TELEPHONE 616-465-5901 DAY NOV 93 AVERAGE DAILY POWER LEVEL NOV 93 DAY AVERAGE DAILY POWER LEVEL 11/0 1/93 11/02/93 11/03/9 3 11/04/93 11/05/93 11/06/93 11/07/93 11/08/93 11/09/93 11/10/93 11/11/93 11/12/93 11/13/93 11/14/93 11/15/93 11/16/93 780 779 783 782 781 778 777 776 771 781 779 777 779 779 777 776 11/17/93 11/18/93 11/19/93 11/20/93 11/21/93 11/22/93 11/23/93 11/24/93 11/25/93
.11/26/93 11/27/93 11/28/93 11/29/93 11/30/93 777 775 778 778 779
- 779, 778
- 778, 777 782 771 772 768 771 0
UNIT SHUTDOWNS AND POWER REDUCTIONS REPORT MONTH: NOVEMBER 1993 UNIT NAME:
DATE:
COMPLETED BY:
TELEPHONE:
PAGE 1 OF 1 D. C.
COOK UNIT 2 Dec 1, 1993 R. D. Reynnells (616) 465-5901 DURATION NO.
DATE TYPE HOURS METHOD OF SHUTTING DOWN REASON~
REACTOR~
LICENSEE EVENT
'YSTEM COMPONENT CAUSE AND CORRECTIVE ACTION REPORT NO.
CODE~
CODE TO PREVENT RECURRENCE None There were no unit shutdown or significant power reductions from 75%
RTP this month.
1 F:
Forced S:
Scheduled 2
Reason:
A:
Equipment Failure (Explain)
B:
Maintenance or Test C:
Refueling D:
Regulatory Restriction E:
Operator Training and License Examination F:
Administrative G:
Operational Error (Explain)
H:
Other (Explain) 3 Method:
1:
Manual 2:
Manual Scram 3:
Other (Explain) 4Exhibit G Instructions for preparation of data entry sheets for Licensee Event Report (LER) File (NUREG 1061) 5Exhibit I:
Same Source
DO T NO.:
UNIT NAME:
COMPLETED BY:
TELEPHONE:
DATE:
PAGE 50-316 D.C.
Cook Unit 2 R.
D. Reynnells (616) 465-5901 Dec 1, 1993 Page 1 of 1 MONTHLY.OPERATING ACTIVITIES NOVEMBER 1993 HIGHLIGHTS The unit entered the reporting period in Mode 1 at 75~o RTP.
The unit exited this reporting period in Mode 1 at 754 RTP.
There were no challenges to the pressurizer safety valves or power operated relief valves.
Gross Electrical generation for the month of November was 585510,MWH.
DETAILS None
DOCKET NO:
UNIT NAME:
COMPLETED BY:
TELEPHONE:
DATE:
PAGE 50-316 D.C.
Cook Unit 2 M. E. Russo (616) 465-5901 December 3,
1993 1 of 1 MAJOR SAFETY-RELATED MAINTENANCE November 1993 No major safety-related maintenance items are included for the month of November.