ML17331A785

From kanterella
Jump to navigation Jump to search
Summarizes Discussions W/Nrc Staff Re Inaccuracies in 810616 SER Concering Auxiliary Feedwater Sys.Inaccuracies Have No Impact on Conclusions Reached in SER & Revised SER Will Not Be Issued
ML17331A785
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 08/21/1981
From: Hunter R
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To: Harold Denton
Office of Nuclear Reactor Regulation
References
AEP:NRC:00300G, AEP:NRC:300G, NUDOCS 8108260028
Download: ML17331A785 (3)


Text

GULATJRY fNFOR~ATION DISTRIBUTION SYSTEM (RIDS)

ACCESSIOV VBR: 81092600 FACIL:SO-315 Dona 1 o 50 316 Dona 1 d AUT9, N 4,'1E AUT HUNTERgR.Se Indi R EC I P ~ V A'41E REC DENTONg H.R ~

Gffi 28 0 JC, DATE: 81/08/21 NOTARIZED:

Coom Nuclear Po<<er Plant< Unit 1<

Cook ivuclear Power Plant<

Unit 2i HOR AF F ILI ATION ana 8 Micnigan Electric Co, IP I EN l' F F ILI 4 T I0 V ce of Nuclear Reactor Regulationi Di NO Indiana Indiana rector:

DOCKET ¹ 05 0

SUBJ:-CT: SJ~varizes discussions

<</NRC staff r e inaccuacies in

'910616 SER concering auxil>ary feedwater sys

~ Inaccuracies nave no inoact on conclusions reached in SER 4

r evised SER will not oe issued.

DISTRIS JTIDN C3OE:

AOOLS COPIES RECEIVED:LTH I

ENCL SIZE:

TITLE: general Distribution for after Issuance of Oper ting License VOTES: IKE:3 cooi es al 1

~aters al Send 3 conies of all material to IEE.

0S00031S 05000316

<ECIP IENT 13 COOE/VA~E ACTION:

QRi Pl BC 04 INTERN

l8,=

06 OH

""S S 9R FI~

01 COPIES LT i'R ENCL 13 1

1 1'1 RECIPIENT 10 CODE/NAHE 0 IRI DI V OF LIC OELD 11 PAD ASST QR COPIES LTTR =VCL EXTERNAL:

ACRS VR" P')9 VTLS na n~

16 1

1l LPDR VSIC 03 05 TOTAL,VU'WHEAL OF COPIES REgUiRED:

LTTR ~

ENCL

INDIANA 5 MICHIGAN ELECTRIC COMPANY P. 0, BOX I8 BOWLING GREEN STATION NEW YORK, N. Y. 10004 August 21, 1981 AEP:NRC:00300G Donald C.

Cook Nuclear Plant Units 1 and 2

Docket Nos 50-315 and 50-316 License Nos.

DPR-58 and DPR-74 Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D.

C.

20555

Dear Mr. Denton:

II,@

/-; ~ILL 'IL9 ~

/7

., i'i I/I

'i 25 1S8j ~:

LhJe tUQLAR RfQ4gQQ COAWtSSQg This letter summarizes our discussions with members of your staff concerning inaccuracies in the June 16, 1981 Safety Evaluation Report (SER) of the Donald C.

Cook Plant Auxiliary Feedwater System (AFS).

The explanations we were given are provided below:

1)

Two typographical errors in the cover letter:

a)

June 1,

1980 letter referenced should be June 1,

1981 b)

NUREG-0736 should be NUREG-0737 2)

Page 2 of the SER states that the steam generator level in-strumentation at D.

C.

Cook "must be" in conformance with Regulatory Guide 1.97 and implemented on the Regulatory Guide schedule.

The NRC intended this statement to be an indication that this "wi11 be" required in the future,not at the present time.

3)

Page 5 of Franklin Institute's report incorrectly states that the FMO valves for the motor driven pump are normally closed.

These valves are normally open receiving a signal to open when the pump is challenged.

4)

On Pages 6,

7 and 8, Franklin quotes IEEE-279-1971 and IEEE-323-1974 standards from our submittals.

We never listed the applic-able year of the standards in the. submittals.

Actually, the Cook Plant AFS actuation and control system is designed to the IEEE-279-1969 - Draft and IEEE-323-1971 standards.

8108260028 8i082i PDR ADOCK 05000315 P

PDR

Mr. Harold R. Denton AEP:NRC:00300G 5)

Page 9 of Franklin's report states that operability of the BOP inverter is required by the Technical Specifications.

We spe-cifically clarified and corrected this in our letter of January 23, 1981, No. AEP:NRC:00307F.

6)

The deadline for installation of AFS flow transmitter was re-vised from January 1,

1981 to be "... compatible with the NUREG-0737 implementation schedule" in our response of January 8, 1981, letter No. AEP:NRC:0398.

We have been told by members of your staff that these inaccuracies have no impact on the conclusions reached in the SER and that, as such, a revised SER will not be issued.

This letter, then, documents our discus-sions and corrects the record.

Very truly yours,

'k.'.""Hunter Vice President cc:

John E. Dolan - Columbus R.

C. Callen G. Charnoff R.

W. Jurgensen D. V. Shaller - Bridgman Joe Williams, Jr.