ML17331A659
| ML17331A659 | |
| Person / Time | |
|---|---|
| Site: | Cook |
| Issue date: | 02/20/1981 |
| From: | Hunter R INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG |
| To: | Harold Denton Office of Nuclear Reactor Regulation |
| References | |
| AEP:NRC:00518, AEP:NRC:518, NUDOCS 8103020626 | |
| Download: ML17331A659 (3) | |
Text
REGULATOR )
'NFORMATION DISTRIBUTION S EIM (RIDS)
ACCESSION NOR:8],03020626 DOC ~ DATE: 81/02/20 NOTARIZED:
NO DOCKET FACy Donald CD Cook Nuclear power Plant, Unit li Indiana 8
05000315 50 316 Donald CD Cook Nuclear Power Plantr Unit 2P Indiana 8
05000316 A T, AUTHUR AFFILIATION HUNTERER ~ ST Indiana 8 ~ichigan Electric Co, REC I P ~ NAI!K REC IP I EN I'FF Il I ATION DENTON, H.R.
Office of Nuclear Reactor Regulationr Director
SUBJECT:
Updates 810112 info r e utils'80 proor am r e hydr ogen control measures for ice condenser containments. Interim distributed igrIition sys will be manually actuated from auxiliary bldg, Agrees to 810312 techr ical meeting.-
DISTRIBUTION CODE:
ASSIS COPIES RECEIVED:LTR g ENCL g SIZE:
TITLE: General Distribution for af ter Issuance of Operating License NOTES: I8E:3 copies all material.
Send 3 copies of all material to I8,K ~
05000315 05000316 REC,I P I EN 7 IO COOK/NAME ACTION Ir A<GAP S ~
04 INTERNAL: D/D IR HU!U; F ACORN I8,E 06 0
L 11 FILE 01 COPIES LTTR ENCL 13 1
RECIPIENT I'3 COOK/NAi4IE DIR P D I V OF L I C NRC PDR 02 OH ASSESS BR 10 COPIES LTTR ENCL EXTERNAL: ACRS BASIC ne 05 16 1
1 LPOR 03 AIR p3 )~
fp 0
TOTAL NUMBER OF COPIES REQUIRED:
LTTR ENCL
INDIANA L MICHIGAN ELECTRIC COMPANY P. O. BOX 18 BOWLIN G GR E EN STATION NEW YORK, N. Y. 10004 February 20, 1981 AEP:NRC:00518 Donald,C.
Cook Nuclear Plant Unit Nos.
1 and 2
Docket Nos. 50-315 and 50-316 License Nos.
DPR-58 and OPR-74 Post-Accident Hydrogen Control Mr. Harold R. Denton, Director Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Washington, O.
C.
20555
Dear Mr. Oenton:
As you know, we have joined the Tennessee Valley Authority and Duke Power Company in a research and development program to investigate hydrogen control measures for ice condenser containments.
By letter dated January 12, 1981, AEP:NRC:00500, Indiana 8 Michigan Electric Company (I8MECo) submitted to the Commission the first in a series of quarterly reports describing our efforts regarding hydrogen control during hypothetical degraded core cooling events.
Various potential hydrogen control methods are being studied, including the use of an Interim Distributed Ignition System (IDIS).
In our AEP:NRC:00500 submittal we stated that we would install the in-containment portion, of the IDIS during the 1981 refueling outages for the Cook Units, if required by the NRC.
Having reviewed the NRC SER for Sequoyah on the IOIS as well as other information available concerning the IDIS mitigation
- concept, we are proceeding to install the in-containment portion of an IDIS during the 1981 refueling outages.
Materials are being ordered with scheduled delivery dates in accordance with our expected refueling outages.
The Cook Plant IDIS will be designed in accordance
'with the criteria set forth in Section 6.1 of the enclosure to our AEP:NRC:00500 submittal.
In essence, the IDIS wi 11 be a two-train, seismically supported system consisting of thirty-four igniter assemblies per train.
The IDIS will be a manually actuated system controllable from the Auxiliary Building.
IOIS operating procedures and actuation criteria are presently under development.
Pool 5
820302
Mr., H. R. Denton, Director AEP:NRC:00518 Members of your staff have requested that a technical meeting be held in Bethesda, Maryland to discuss hydrogen control measures for the Cook Plant.
We would be ready to meet with your staff on March 12, 1981.
Very truly yours,
~ -
~
R.
S. Hunter Vice President cc:
John E. Dolan G. Charnoff R. C. Callen R.
W. Jurgensen D. V. Shaller - Bridgman Region III Resident Site Inspector