Informs That NRC Will Perform Sys Based Instrumentation & Control Insp at Plant During Wks of 930830-0913.Requests Assistance in Providing Encl Info for Review During 930816-18 pre-insp Visit
ML17331A289
Person / Time
Site: Cook  
Issue date: 04/21/1993
From: Martin T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Fitzpatrick E
INDIANA MICHIGAN POWER CO.
References
NUDOCS 9304270102
Download: ML17331A289 (5)


Text

FORD I REGULA'I INFORMATION DISTRZBUTZYSTEM (RIDE)

ACCESSION NBR:9304270102 DOC.DATE: 93/04/21 NOTARIZED:

NO DOCKET ¹

. FACIL:50-315 Donald C.

Cook Nuclear Power Plant, Unit 1, Indiana M

05000315 50-316 Donald C.

Cook Nuclear Power Plant, Unit 2, Indiana M

05000316 AUTH.NAME AUTHOR AFFILIATION MARTIN,T.O.

Region 3 (Post 820201)

RECIP.NAME RECIPIENT AFFILIATION FITZPATRICK,E.

Indiana Michigan Power Co.

SUBJECT:

Informs that NRC will perform sys based instrumehtation control insp at plant during wks of 930830-0913.Requests assistance in providing encl info for review during

'930816-18 pre-insp visit.

DISTRIBUTION CODE:

IE51D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: File Dist for Region Document (50 DKT):Region, P R, LPDR, NSIC NOTES:

RECIPIENT ID CODE/NAME DEANFW COPIES LTTR ENCL

-1 1

RECIPIENT ID CODE/NAME COPIES LTTR ENCL INTERNA EG FILE EXTERNAL: NRC PDR 02 1

1 1

1 RGN3 FILE 01 1

1 NOTE TO ALL RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK.

ROOM P 1-37 (EXT. 504-2065) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED:

LTTR 4

ENCL 4

%.~8 RECII c<

+~

nO Vl O~

4p w+

4p

+R*W+

II UNITED STATES NUCLEAR REGULATORY COMMISSIO REGION III 799 ROOSEVELT ROAD GLEN ELLYN, ILLINOIS 60I37 ADR."..: 1993 Docket No. 50-315 Docket No. 50-316 Indiana Michigan Power Company ATTN:

Hr.

E.

E. Fitzpatrick Vice President Nuclear Operations Division 1 Riverside Plaza

Columbus, OH 43216

Dear Mr. Fitzpatrick:

SUBJECT:

DOCUMENTATION RE(VEST TO SUPPORT THE D.

C.

COOK SYSTEMS BASED INSTRUMENTATION AND CONTROL INSPECTION (SBICI)

I would like to inform you that the NRC will perform a system based

,instrumentation and control inspection (SBICI) at the D.

C.

Cook Nuclear Powers Plant.

The onsite inspection activities are scheduled for the weeks of August 30 and September 13, 1993.

Part of the inspection will be conducted at your engineering offices.

The inspection will assess

design, operation, maintenance, surveillance, quality assurance, and corrective actions associated with instrumentation and

'ontrol systems.

To accomplish its objectives, the SBICI team will review a

broad range of information and activitie's for the IIlC system loops selected.

The attachment to this letter lists the initial items which the team expects to review.

The list is being provided to allow you to anticipate the team's informational needs.

I request your assistance in making this information available for review during the August 16-18, 1993, pre-inspection visit.

If you have any questions regarding the attachment or the inspection itself, please contact Mr. Ronald Gardner (708/790-5524) or Hr. Zelig Falevits (708/790-5772) of my staff.

Sincerely,'

upI~

T. 0. Hartin, Acting Director Division of Reactor Safety

Attachment:

As stated See Attached Distribution 9304270i02 93042i PDR ADQCK 050003i5 8

PDR

Indiana Hichigan Power Company Distribution cc w/attachment:

A. A. Blind, Plant Hanager OC/LFDCB Resident Inspector, RIII James R. Padgett, Hichigan Public Service Commission EIS Coordinator,

USEPA, Region V Office Hichigan Department of Public Health D.

C.

Cook LPH, NRR

ATTACHMENT SBICI Information Re uest l.

Index of instrument loop design calculations.

2.

Index of setpoint calculations and setpoint tolerance analyses.

3.

Instrument setpoint control program.

4.

Instrument setpoint methodology used.

5.

List of safety related instrument loops.

6.

List of 80P instrument loops that can impact safety related systems and cause reactor trips.

7.

Copy of loop schematics and P8 I diagrams for items 5 and 6, above:

8.

Copy of FSAR and Technical Specifications.

9.

Summary of PRA study.

10.

MME program for instrumentation.

11.

Organizational chart of I&C engineering groups (corporate and site).

12.

Index of instrument surveillance procedures.

13.

Index of preventive and corrective maintenance procedures for safety related instruments.