Forwards Safety Insp Repts 50-315/92-23 & 50-316/92-23 on 921203-930119.No Violations Noted
ML17331A011
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 02/05/1993
From: Jorgensen B
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To: Fitzpatrick E
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
Shared Package
ML17331A012 List:
References
NUDOCS 9302160021
Download: ML17331A011 (4)


See also: IR 05000315/1992023

Text

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

DOCKET

05000315

05000316

SUBJECT:

Forwards safety insp repts

50-315/92-23

& 50-316/92-23

on

921203-930119.No violations noted.

DISTRIBUTION CODE:

IE01D

COPIES

RECEIVED:LTR

ENCL

SIZE:

TITLE: General

(50 Dkt)-Insp Rept/Notice of Violation Response

NOTES:

ACCESSION NBR:9302160021

DOC.DATE: 93/02/05

NOTARIZED: NO

~

~

ACIL:50-315 Donald C.

Cook Nuclear

Power Plant, Unit 1, Indiana

M

50-316 Donald C.

Cook Nuclear

Power Plant, Unit 2, Indiana

M

AUTH.NAME

AUTHOR AFFILIATION

JORGENSEN,B.L.

Region

3 (Post

820201)

RECIP.NAME

RECIPIENT AFFILIATION

FITZPATRICK,E.

Indiana Michigan Power

Co. (formerly Indiana

& Michigan

El'ECIPIENT

ID CODE/NAME

PD3-1

PD

INTERNAL: AEOD

AEOD/DSP/TPAB

DEDRO

NRR/DLPQ/LHFBPT

NRR/DOEA/OEAB

NRR/PMAS/ILPB 1

NRR/PMAS/ILRB12

~

~

OE DIR

~BEG F

E

02

EXTERNAL: EG&G/BRYCEiJ.H.

NSIC

COPIES

LTTR ENCL

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

RECIPIENT

ID CODE/NAME

DEAN,W

AEOD/DEIB

AEOD/TTC

NRR MORISSEAUiD

NRR/DLPQ/LPEB10

NRR/DREP/PEPB9H

NRR/PMAS/ILPB

2

NUDOCS-ABSTRACT

OGC/HDS2

RGN3

FILE

01

NRC PDR

COPIES

LTTR ENCL

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

1

,0

NOTE TO ALL RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK.

ROOM P 1-37 (EXT. 504-2065) TO ELIMINATEYOUR NAME FROM DISTRIBUTION

LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES

REQUIRED:

LTTR

23

ENCL

23

Docket No. 50-315

Docket No. 50-316

FEB

O $ "f93

Indiana Michigan Power

Company

ATTN:

Mr. E.

E. Fitzpatrick

Vice President

Nuclear Operations Division

1 Riverside

Plaza

Columbus,

OH

43216

Dear Mr. Fitzpatrick:

This refers to the routine safety inspection

conducted

by J.

A. Isom and

D. J. Hartland of this office on December

3,

1992, through January

19,

1993,

of activities at the Donald

C.

Cook Nuclear Plant, Units

1 and 2, authorized

by

NRC Operating

Licenses

No.

DPR-58

and DPR-74,

and to the discussion

of our

findings with A. A. Bl'ind and others of your staff at the conclusion of the

inspection.

Areas

examined during the inspection

are identified in the report.

Within

these

areas,

the inspection consisted

of selective

examinations of procedures

and representative

records,

interviews with personnel,

and observation of

activities in progress.

No violations of NRC requirements

were identified during the course of this

inspections

In accordance

with 10 CFR 2.790 of the Commission's

regulations,

a copy of

this letter

and the enclosed

Inspection

Report will be placed in the

NRC

Public Document

Room.

We will gladly discuss

any questions

you have concerning this inspection.

Enclosure:

Inspection

Reports

No. 50-315/92023(DRP);

No. 50-316/92023(DRP)

See Attached Distribution

B. L. Jorgensen,

Chief

Reactor Projects

Section

2A

RI II.

~g~.c2

W<4K

Sc

eibinz

RI

Sc umacher

Para.

4

02/Z /93

02/6 /93

P

x20QOQ

9302160021

930205

PDR

ADOCK 05000315

8

PDR

J

ensen

02/5 /93

UNITED STATES

NUCLEAR REGULATORY COMMISSION

REGION III

399 ROOSEVELT ROAO

GLEK ELLVK.ILLINOIS 60137

F" ..=

Docket

No. 50-315

Docket

No. 50-316

Indiana Hichigan

Power

Company

ATTN:

Nr.

E.

E. Fitzpatrick

Vice President

Nuclear Operations

Division

1 Riverside

Plaza

Columbus,

OH

43216

Dear Hr. Fitzpatrick:

This refers to the routine safety inspection

conducted

by J.

A.

Isom and

D. J. Hartland of this office on December 3,

1992,

through January

19,

1993,

of activities at the Donald

C.

Cook Nuclear Plant, Units

1

and 2, authorized

by

NRC Operating

Licenses

No.

DPR-58

and DPR-74,

and to the discussion

of our

findings with A. A. Blind and others

of your staff at the conclusion of the

inspection.

Areas

examined during the inspection

are identified in the report.

Within

these

areas,

the inspection consisted

of selective

examinations of procedures

and representative

records,

interviews with personnel,

and observation of

activities in progress.

No violations of NRC requirements

were identified during the course of this

inspection.

In accordance

with 10 CFR 2.790 of the Commission's

regulations,

a copy of

this letter

and the enclosed

Inspection

Report will be placed

in the

NRC

Public Document

Room.

We will gladly discuss

any questions

you have concerning this inspection.

Sincerely,

Enclosure:

Inspection

Reports

No. 50-315/92023(DRP);

No. 50-316/92023(DRP)

B. L. Jorgensen,

Chief

Reactor Projects

Section

2A

See Attached Distribution

Indi an a Michi g an

Power

Company

Distributi on:

cc w/enclosure:

A. A. Blind, Plant Manager

DCD/DCB (RIDS)

OC/LFDCB

Resident

Inspector,

RIII

James

R. Padgett,

Michigan Public

Service

Commission

EIS Coordinator,

USEPA

Region

5 Office

Michigan Department of

Public Health

D.

C. Cook,

LPM,

NRR