Provides Detailed Info on How to Operate,Maintain & Provide Qualified Replacement Parts for Existing RPS in Short Term, & Long Term Plans Re RPS Upgrade
ML17329A547
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 06/29/1992
From: Fitzpatrick E
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
AEP:NRC:1159D, NUDOCS 9207020292
Download: ML17329A547 (4)


Text

ACCELERATED DISTPJBUTION DEMONST$&TION SYSTEM REGULARY INFORMATION DISTRIBUTISYSTEM (RIDE)

~f ACCESSION NBR:9207020292 DOC.DATE: 92/06/29 NOTARIZED: NO DOCKET FACIL:50-315 Donald C.

Cook Nuclear Power Plant, Unit 1, Indiana M

05000315 50-316 Donald C.

Cook Nuclear Power Plant, Unit 2, Indiana M

05000316 AUTH.NAME AUTHOR AFFILIATION FITZPATRICK,E.

Indiana Michigan Power Co. (formerly Indiana

& Michigan Ele RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)

SUBJECT:

Provides detailed info on how to operate, maintain

& provide qualified replacement parts for existing RPS in short term, a long term plans re RPS upgrade.

DISTRIBUTION CODE:

A001D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: OR Submittal: General Distribution R

D NOTES:

RECIPIENT ID CODE/NAME PD3-1 LA STANGFJ COPIES LTTR ENCL RECIPIENT ID CODE/NAME PD3-1 PD COPIES LTTR ENCL D,

INTERNAL: NRR/DET/ECMB 7D NRR/DOEA/OTSB11 NRR/DST/SELB 7E NRR/DST/SRXB SE OC LPM REG FILE 01 EXTERNAL: NRC PDR NRR/DET/ESGB NRR/DST SE2 NRR/DST/SICBSH7 NUDOCS-ABSTRACT OGC/HDS2 RES/DSIR/EIB NSIC D

R D

NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTEI CONTACT THE DOCUMENT CONTROL DESK.

ROOM PI-37 (EXT. 20079) TO ELIMINATEYOUR NAMEFROM DISTRIBUTION LIPID FOR DOCUMENTS YOU DON'T NEEDl D

D TOTAL NUMBER OF COPIES REQUIRED:

LTTR 18 ENCL

indiana Michigan Power Company P.O. Box 16631 Columbus, OH 43216 AEP'NRC:1159D Donald C.

Cook Nuclear Plant Units 1 and 2

Docket Nos.

50-315 and 50-316 License Nos.

DPR-58 and DPR-74 REACTOR PROTECTION SYSTEM INSTRUMENTATION REPLACEMENT U.

S. Nuclear Regulatory Commission Document Control Desk Washington, D.C.

20555 Attn:

T.

E. Murley June 29, 1992

Dear Dr. Murley:

Reference:

Letter, J.

F. Stang (NRR) to E. E. Fitzpatrick (AEPSC),

"Donald C.

Cook Nuclear Plant, Units 1 and 2, Reactor Protection System Instrumentation Replacement,"

May 6, 1992.

In the referenced letter, the NRC requested that we provide detailed information, on 1),,

how we. will,operate, r maintain, and provide qualified'eplacements,parts, for, the existing reactor protection system instrumentation (RPS) in the short term and 2), our long-term plans regarding an RPS upgrade.

The following information is provided in response to that request.

With respect to short-term considerations, specific details on how we will operate and maintain our present Foxboro analog instrumentation were presented to and discussed with your staff during a meeting held in Washington, DE C.

on April 21, 1992.

The life extension and maintenance program that is being implemented is made up of a number of elements.,

These include actions to evaluate historical data and monitor current failure data by frequency and RPS module type, project future repair and replacement needs, repair and return failed modules, and support inventory and replacement needs with substitute modules manufactured by another vendor.

Each of the above activities was, addressed in detail during the April 21, 1992, meeting...

Based on follow-up discussions and concurrence of, the Project Manager, it isunderstood.that, there, are no remaining o'pen~items,that need to,be addressed.-

...*r J )

~

~. << p

(

f ~ \\

J 0

II

'I

~

I o

~

~

r 9207020292'920629 PDR'- ADOCK '05000315 p

PDR y0 l g

Il<<

~ I I <<<<)

I g

~

I I

f

'f

<< ~

\\

Dr. T.

E. Murley 2

AEP:NRC:1159D During the April 21,

1992, meeting we also presented our long-term plans for replacing the present analog instrumentation with a

digital Foxboro microprocessor line of instrumentation.

As a

follow-up to an April 21 meeting commitment, letter AEP:NRC:1159B, dated May 1,

1992, was submitted to formally request NRC review and approval of this upgrade project.

We also agreed to transmit by November 30,

1992, a majority of the engineering documentation needed for your staff's review and approval of this project.

A discussion was held with the Project Manager in late May. It was concluded that our May 1,

1992, letter closed out previously remaining issues regarding our long-range RPS upgrade plans.

Pursuant to the agreements reached in that conversation, no further information is necessary on that subject.

Sincerely, E.

E. Fitz trick Vice President tjw CC:

D. H. Williams, Jr.

A. A. Blind - Bridgman J.

R. Padgett G. Charnoff NFEM Section Chief A. B. Davis