Requests 1-yr Exemption from 10CFR50,App E,Section F.3 for 1991 Re Emergency Plan Exercise Schedule
ML17329A032
Person / Time
Site: Cook  
Issue date: 05/24/1991
From: Fitzpatrick E
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To: Boger B
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9105310122
Download: ML17329A032 (8)


Text

FORD 1

REGULA I INFORMATION DISTRIBUTIO YSTEM (RIDS)

ACCESSION NBR:9105310122 DOC.DATE: 91/05/24 NOTARIZED:

NO DOCKET FACIL:50-315 Donald C.

Cook Nuclear Power Plant, Unit 1, Indiana 6

05000315 50-316 Donald C.

Cook Nuclear Power Plant, Unit 2, Indiana a

05000316 AUTH.NAME AUTHOR AFFILIATXON FITZPATRICK,E.

Indiana Michigan Power Co. (formerly Indiana 6 Michigan Ele RECIP.NAME RECIPIENT AFFILIATION BOGER,B.

Document Control Branch (Document Control Desk)

SUBJECT:

Requests 1-yr exemption from 10CFR50,App E,Section F.3 for 1991 re emergency plan exercise schedule.

DISTRIBUTION CODE:

A045D COPIES RECEIVED:LTR

/

ENCL j

SIZE:

TITLE: OR Submittal:

Emergency Preparedness

Plans, Implement'g Procedures, C ~

NOTES:

RECIPIENT ID CODE/NAME PD3-1 PD INTERNAL: AEOD/DOA/IRB NUDOCS-ABSTRACT EXTERNAL: NRC PDR COPIES LTTR ENCL 1

1 1

1 1,

1 1

1 RECIPIENT XD CODE/NAME COLBURN,T.

NRR/j)R~E- -

RQ9D R 6 F1L~

NSIC COPIES LTTR ENCL 1

1 1

1 1

1 1

1 TOTAL NUMBER OF COPIES REQUIRED:

LTTR 8

ENCL 8

Indiana Michigih Power Company P.O. Box 16631 Cotumbus, OH 43216 AEP:NRC:0965Y 10 CFR 50 App.

E Donald CD Cook Nuclear Plant Units 1 and 2

Docket Nos.

50-315 and 50-3166 License Nos.

DPR-58 and DPR-74 EMERGENCY PLAN EXERCISE SCHEDULE CHANGE U.S. Nuclear Regulatory Commission ATTN:

Document Control Desk Washington, D.C.

20555 ATTN:

Mr. Bruce Boger Director Division of Reactor Projects 3/4/5 May 24, 1991

Dear Mr. Boger:

The purpose of this letter is to request a one year exemption from 10 CFR 50, Appendix E, Section F.3 for 1992.

FEMA has requested that the State of Michigan and Indiana Michigan Power Company reschedule the off-site participation portion of the radiological emergency preparedness (REP) exercise for the Donald C.

Cook Nuclear Plant by one year (see the attachment to this letter.)

The current exercise schedule requires Michigan to participate in one off-site exercise one year and in three off-site exercises during the next year.

The current schedule places an uneven workload on the FEMA Region V Office in their evaluation of REP exercises.

The affected local jurisdiction, Berrien County, participates in both the Palisades and Donald C.

Cook Nuclear Plant REP exercises.

The schedule change would not reduce the number of exercises in which Berrien County participates.

This proposed schedule change would move State of Michigan and Berrien County participation from the November, 1992 exercise to the May, 1993 exercise.

The November, 1992 exercise would then be a

utility only exercise.

Therefore, in 1992, we will not meet the requirement that "each licensee at each site shall exercise with offsite authorities However, given that the State of Michigan and Berrien County exercise with Palisades and that the exemption is only for one year, we believe that the schedule change is acceptable.

Following 1992, the exercise schedule will continue to meet 10 CFR 50 Appendix E requirements.

9105310122 910524

'DR ADOCK 05000315 F

PDR

Mr. Bruce Boger AEP:NRC:0965Y In order to prepare for our annual scheduling conference, we request your approval of the exemption by September 30, 1991.

This document has been prepared following Corporate procedures that incorporate a reasonable set of controls to ensure its accuracy and completeness prior to signature by the undersigned.

Since'rely, ee-E.

E. Fitzpa rick Vice President edg CC:

D. H. Williams, Jr.

A. A. Blind - Bridgman NFEM Section Chief J.

R. Padgett G. Charnoff T.

E. Murley - Washington, D.C.

R. Erickson

- Washington, D.C.

9H15 NRC Resident Inspector

- Bridgman A. B. Davis

- Region III F/Lt. J.

M. Tyler, State of Michigan F. L. Jewell

- Berrien County Sheriff's Department D. Bement FEMA Region V

APR 18 1991 STATE OF hllCIIIGAN JOHN ENGLER, GOVERNOR DEPARTMENT OF STATE POLICE COI MICIIAELD. ROBINSON, DIRECTOR April 15, 1991 EhIERGENGY MANAGEhIENTDIVISION KNAPPS CENTRP, SUITS 300 300 SOUTII WASIIINGTONSQUARE LANSING,MICIIIGAN48913 PIIONE: 5I7 373-6371 Mr. E.

E. Fitzpatrick, Vice President Nuclear Operations American Electric Power Company 1 Riverside Plaza, 20th Floor

Columbus, OH 43215

Dear Nr. Fitzpatrick:

During 1990, in several meetings with the Federal Emergency Management

Agency, Region V Office, PENA requested that the State of Michigan and the American Electric Power Company reschedule the off-site participation in the Radiological Emergency Preparedness exercise for the Donald C.

Cook Nuclear Power Plant by one year.

The current schedule requires Michigan to participate in one off-site exercise one year, and in three off-site exercises during the next year.

This one/three schedule places an uneven workload on the FENA.Region V Office in their evaluation of the REP exercises.

In discussions with Ms. Leah Bounds, AEP Radiological Emergency Preparedness, and this office, Mr. Bement, Chairman of the FENA Region V RAC; indicated that FEMA Region V's request for such a change in exercise participation would be supported by the National FEMA office.

The State of Michigan and American Electric Power Company discussed the issue and had no objections to the schedule change.

The affected local jurisdiction, Berrien County, participates in both the Donald C.

Cook and Palisades Nuclear Power Plant REP exercises.

The schedule change would not reduce the number of exercises that they participate in, but would only change the schedule.

Ms. Bounds discussed the issue with the NRC Region III Office, which indicated

.support for the change.

This office then provided correspondence to the FEMA Region V Office requesting the change in schedule.

FEMA Region V has now been in contact with us and has stated that FEMA Headquarters supports the change in exercise

schedule, but that any change in off-site participation also needs to be initiated by the American Electric Power Company through the NRC Region III Office.

Once NRC Region III has approved the change and forwarded it to NRC Headquarters, FEMA Headquarters can then approve the rescheduling of the off-site participation in the Donald C.

Cook REP exercise.

A PROUD tradition ofSERVICE through EXCI.'LLENCE,INTEGRITY,and COURTI"'SY. ~~~

gA

~

ll II'

Mr. E.

E. Fitzpatrick Page Two of Two April 15, 1991 This change will move the State and,Berrien County participation from the

November, 1992 exercise to the May, 1993 exercise.

The November, 1992 exercise would then become a utility only exercise.

We would appreciate it if you could initiate the contact with NRC Region III to make the change in the exercise participation.

If you have any questions, please feel free to contact this office.

Sincerely, F/