ML17328A200

From kanterella
Jump to navigation Jump to search
Forwards Approved Plant Ref Matls for Requalification Program Evaluation,Per NRC 890803 Request.W/O Encls
ML17328A200
Person / Time
Site: Cook  
Issue date: 10/11/1989
From: Nichols W
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To: Murley T
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
AEP:NRC:, NUDOCS 8910180345
Download: ML17328A200 (5)


Text

,ACi."'ELERATED D1S1BVT1ON DEMONSTRION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:8910180345 DOC.DATE: 89/10/11 NOTARIZED: NO DOCKET FACIL:50-315 Donald C.

Cook Nuclear Power Plant, Unit 1, Indiana 6

05000315 50-316 Donald C.

Cook Nuclear Power Plant, Unit 2, Indiana 6

05000316 AUTH.NAME AUTHOR AFFILIATION NICHOLS,W.A.

Indiana Michigan Power Co.

(formerly Indiana 6 Michigan Ele RECIP.NAME RECIPIENT AFFILIATION MURLEY,T.E.

Document Control Branch (Document Control Desk)

SUBJECT:

Forwards approved plant ref matls for requalification program evaluation,per NRC 890803 request.W/o encls.

DISTRIBUTION CODE:

M003D COPIES RECEIVED:LTR I(

ENCL 0 SIZE: 2.

TITLE: Operator Requalification Program NOTES RECIPIENT ID CODE/NAME PD3-1 LA GIITTER,J.

INTERNAL: AEOD/DOA NRR/DLPQ/HFB 10 NUDOCS-ABSTRACT RGN3 EXTERNAL: LPDR NSIC COPIES LTTR ENCL RECIPIENT ID CODE/NAME PD3-1 PD AEOD/DSP/TPAB

~J3+gg OLB 10 REG FILE 01 NRC PDR COPIES LTTR ENCL R

S h

NOXK 'ZO ALL RIDS" MCZP'IEN'IS:

PURSE HELP US 'XO REDUCE KL8TE!

CGHZACZ %HE DOCUNEVZ CDFZROL DESK, RDCN P1-37 (EXT. 20079) K) XKJMZKQR %SR NAME PHD DISTRIBUTION TOTAL NUMBER %RRRPk&%2$58t89. %Fit~

ENCL

Cook Nnciear Plant Training Center PO. Box 458 Bridgman, Ml 49106 616 465 5901 AEP:NRC:

Donald C.

Cook Nuclear Plant Units 1 and 2

Docket Nos.

50-315 and 50-316 License Nos.

DPR-58 and DPR-74

SUBJECT:

REQUALIFICATION PROGRAM EVALUATION U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C. 20555 Attn:

T. E. Murley October 11, 1989 Reference; (a)

USNRC Letter Dated 8/3/89 from G.

C. Wright to Mr.

M. P. Alexich (90-day Notification Letter)

Dear Dr. Murley:

As required in reference (a), this letter transmits one complete set of approved (where appropriate)

D. C. Cook Plant reference materials to Region III NRC Headquarters.

These reference materials are being provided for use in developing and administering our upcoming NRC Requalification Examination.

Accompanying this letter to Region III are:

1.

Proposed RO and SRO requalification examination test items (366 Part A and 400 Part B items).

2.

All reference material and objectives for the proposed test items in addition to 15 simulator scenarios and 75 job performance measures.

3.

A requalification training cycle sampling plan.

+910~~0~~&9101 1

I I

PDR ADOCK 05000315 V

PDC OP89114 OPP008

'0 C~

fl

Dr. T. E.

Mu y

AEP:NRC:

Mr. Doug Burris, an active SRO from the D. C.

Cook Operations Department, will be provided to the NRC to complete the examination team.

If you have any questions regarding this submittal, or require additional materials, please contact Mr. Roger Anderson at (616) 465-5901, extension 3108.

Sincerely, g.Q.

W. A. Nichols, Operations Training Supervisor WAN/gc cc:

D. H. Williams, Jr.

A. A. Blind Bridgman R. C. Callen G. Charnoff A. B. Davis NRC Resident Inspector - Bridgman NFEM Section Chief OP89114 OPP008

t l'

ll