Notice of Violation from Insp on 890522-25 & 0707.Violation Noted:Approval for Testing Cd Emergency Diesel Generator Not Signed Prior to Starting Work & Work Performed Per Job Order Not within Scope of Order Form
ML17325B280
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 08/09/1989
From: Cooper R
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
To:
Shared Package
ML17325B279 List:
References
50-315-89-20, NUDOCS 8908170620
Download: ML17325B280 (1)


Text

NOTICE OF VIOLATION American E1ectri c Power Service Corporati on Indiana Hichigan Power Company Docket No. 50-315 License No. DPR-58 As a result of the inspection conducted on Hay 22-25 and July 7,

1989, and in accordance with 10 CFR Part 2, Appendix C - General Statement of Policy and Procedure for NRC Enforcement Actions

( 1988), the following violation was identified:

10 CFR 50 Appendix B, Criterion V, as implemented by the D. C.

Cook Operational-guality Assurance

Program, requires that activities affecting quality be prescribed by documented instructions or procedures and that work be accomplished in accordance with these instructions or procedures.

Contrary to the above:

Paragraph 4.4.3 of procedure PHI-2290 required that "all work performed via a job order must be within the scope of the job order form."

Due to an overspeed problem, extensive additional inspection and rework was performed on job order 761729 even though the scope of the job order was to perform the normal 18 month inspection of the Unit 1

CD emergency diesel (315/89020-01A).

Paragraph 4.4.2 of procedure PHI-2290 required that, when specified, individuals performing work will obtain the approval of the Unit Supervisor, the Assistant Shift Supervisor or the Shift Supervisor prior to starting work.

Although this approval requirement was specified on job order A010547 for testing of Unit 1

CD Emergency Diesel Generator, this block was not signed and there was no objective evidence that the required approval was obtained prior to starting work (315/89020-01B).

This is a Severity Level IV violation (Supplement 1).

Pursuant to the provisions of 10 CFR 2.201, you are required to submit to this office within thirty days of the date of this Notice a written statement or explanation in reply, including for'ach violation:

( 1) the corrective actions that have been taken and the results achieved; (2) the corrective actions that will be taken to avoid further violations; and (3) the date when full compliance;will be'chieved.

Consideration may be'given to extending your response time for good cause show'n.

Dated z.

v'.

W.

ooper, I, Chief Engineering Branch 8908170620 890809 PDR ADOCK 05000325 G