ML17321A973

From kanterella
Jump to navigation Jump to search
Responds to NRC Re Violations Noted in Insp Repts 50-315/85-25 & 50-316/85-25.Corrective Actions:Performance of Supplemental Test Using Imposed Leak Method Placed on Hold Pending Resolution of Inspector Concern
ML17321A973
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 11/18/1985
From: Alexich M
INDIANA MICHIGAN POWER CO. (FORMERLY INDIANA & MICHIG
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
AEP:NRC:0961, AEP:NRC:961, NUDOCS 8512020296
Download: ML17321A973 (14)


Text

INDIANA8 NICHIGAN ELECTRIC COlMPANY P.O. BOX 16631 COLUMBUS, OHIO 43216 November 18, 1985 AEP:NRC:0961 Donald C. Cook Nuclear Plant Nos.

1 and 2

Docket Nos. 50-315 and 50-316 License Nos.

DPR-58 and DPR-74 NRC Report Nos.

50-315/85025(DRS) and 50-316/85025(DRS)

Mr. James G. Keppler U.S. Nuclear Regulatory Commission Region III 799 Roosevelt Road Glen Ellyn, IL 60137

Dear Mr. Keppler:

This letter is in response to Mr. C. J. Paperiello's letter dated October 18, 1985, which forwarded the subject inspection reports of the routine safety inspection conducted by your staff at the Donald C. Cook Nuclear Plant during the period August 14 through September 5,

1985.

The Notice of Violation attached to Mr. Paperiello's letter identified one violation.

In addition, we were requested to respond to the unresolved items identified in paragraph 4.d and 7.a of the inspection report.

The responses to the violation and the two unresolved items are addressed in the attachment to this letter.

This document has been prepared following Corporate procedures which incorporate a reasonable set of controls to insure its accuracy and completeness prior to signature by the undersigned.

Very truly yours, nLQ M. P.

A exich Vice President

~i)6'~

cm Attachments cc:

John E. Dolan W. G. Smith, Jr. - Bridgman R. C. Callen G. Charnoff G. Bruchmann NRC Resident Inspector Bridgman 8512020296 85iii8 PDR ADOCK 05000315 PDR NOV2) )g8~

t~

%Ed/

(w y<<h<<

hhr~

>><<)..

'I

",<<W>>I

")

~

$,)l I"

('7 yl"r<<,(rh 7 l

",I I

)1>>

~

~

~

5 (r7>>

I,'(

y

<>

I I')

)

<<yr(

)" <<t' I

) I W I W

7".wfy

'" ))

U (

<<w,y;)I;r 1

I 7

~

~

y>>l

)AJ ry 7

~

,)y I jy y>>

(

yflrf

')'" f y*.)

~,)

"II4

>f)q '": I

)1 th I'i '

yw h

) j("'w hh g

ww f, <<w>>1 )

AEP: NRC: 0961 Attachment Page 1

NRC Violation "10 CFR 50, Appendix B, Criterion XII states,

'Measures shall be established to assure that tools, gages, instruments, and other measuring and testing devices used in activities affecting quality are properly controlled, calibrated, and adjusted at specified periods to maintain accuracy within necessary limits.'ontrary to the above, the licensee failed to control the calibrated condition of the flowmeter that was used for the supplemental test for the Containment Integrated Leak Rate Test.

A small polyflow fitting was installed in the outlet of the flowmeter which altered the calibrated condition of the flowmeter."

Response

to NRC Violation Corrective Action Taken and the Results Achieved Upon being notified by the Inspector on August 21, 1985 (approximately 1430 hours0.0166 days <br />0.397 hours <br />0.00236 weeks <br />5.44115e-4 months <br />) of his concern regarding the calibration status of the flowmeter due to the existence of a small polyflow fitting in the outlet of the flowmeter, the following actions were taken:

a ~

The performance of the supplemental test using the imposed leak method was placed on hold at about 1455 hours0.0168 days <br />0.404 hours <br />0.00241 weeks <br />5.536275e-4 months <br /> pending resolution of the Inspector's concern.

b.

The manufacturer (calibration facility) was contacted at about 1545 hours0.0179 days <br />0.429 hours <br />0.00255 weeks <br />5.878725e-4 months <br /> to determine the "as calibrated" configuration of the flowmeter.

The manufacturer stated that the flowmeter was calibrated without any potentially restrictive fitting being installed in the outlet of the flowmeter.

co The polyflow fitting was removed from the flowmeter and the supplemental test using the imposed leak method was begun at about 1615 hours0.0187 days <br />0.449 hours <br />0.00267 weeks <br />6.145075e-4 months <br />.

The test was successfully completed approximately six hours later on August 21, 1985.

d.

The flowmeter was subsequently shipped to an approved calibration facility on September 3, 1985.

The "as found" calibration data, dated October 21,

1985, compared favorably with previous calibration data.

Corrective Action To Be Taken To Avoid Further Noncom liance Specific training on the use and application of Float Type flowmeters for personnel associated with the performance of leak rate testing will be completed prior to the upcoming Unit 2 refueling outage.

2.

A memo was issued to appropriate plant personnel on November 14,

1985, to ensure that they are cognizant of their responsibility to use and maintain measuring and test equipment in the "as calibrated" configuration.

AEP:NRC:0961 Attachment Page 2

3.

The, Integrated Leak Rate Test procedures for Unit 1 and Unit 2 (12THP 4030 STP.202) will be revised prior to their next use to include requirements for verifying test equipment configuration after completion of test preparation activities.

4.

Plant Manager Instructions PM1-5060 (Control of Special Tools and Measuring and Test Equipment) and PMI-6030 (Instrument and Control:

Maintenance and Calibration) will be revised by February 1,

1986 to include the statements of policy necessary to ensure that plant personnel are aware of the requirement that the "as used" configuration of measuring and test equipment must remain the same as the "as calibrated" configuration and that any deviation from the "as calibrated" requires that an evaluation be performed to ensure calibration status is maintained.

Date When Full Com liance Will Be Achieved Full compliance was achieved on August 21,

1985, when the polyflow fitting was removed.

Plant Manager Instructions (PMI-6030, PMI-5060) and the ILRT procedure will be revised as committed above.

The specified training will be completed prior to the start of the 1986 Unit 2 refueling outage.

NRC Unresolved Item 315/85025-03 "The inspector performed a pretest containment inspection to ensure the proper placement of test instrumentation.

The inspector noted the close proximity of RTD's to the containment walls.

The reason for this was that each RTD had associated with it a junction box in which permanent wiring had been run for the specific purpose of performing a CILRT.

The inspector asked the licensee if they had determined sensor location by performing a temperature survey or equivalent as required by ANSI N45.4 1972.

During the inspection period, the licensee was unable to determine if they had ever performed a temperature survey.

In order to resolve this matter, the licensee is requested to submit to Region III information showing either; that a temperature survey was performed or; justification for not conducting a temperature survey.

This is considered an unresolved item 315/85025-03(DRS),

pending the inspector's review of the licensee's submittal."

~Res ense The Inspector notes that the proper location of the test temperature instrumentation was not verified by a Temperature Survey.

This survey is a requirement of ANSI N45.4-1972.

The Inspectors statement is correct in that we cannot document that a temperature survey was ever performed prior to an ILRT.

This is required by section 7.4 of ANSI N45.4-1972.

The last sentence of this section states that "Where testing experience with containment structures has established appropriate locations for reference vessels or temperature

sensors, temperature surveys may be eliminated for those containment structures of similar proportions."

Since Unit 1 6 2 containment structures and temperature sensor locations are virtually identical, it is felt that the intent of this requirement has been met for the following reasons:

0,

AEP:NRC:0961 Attachment Page 3

A)

'Temperature Sensor placement has not changed since the initial pre-operational tests.

The validity of every test was verified by a supplemental test as required by 10CFR50 Appendix J.

B)

"The original locations were determined considering the impact of physical barriers and expected temperature gradients.

C)

There is no guidance relative to the minimum number of sensors required in either Appendix J to 10CFR50 or ANSI N45.4-1972.

ANSI N56.8-1981 does state that no sensor should represent more than 10%

of-the containment volume.

Using this guidance, calculations were performed using different combinations of the 46 temperature sensors used during this test.

These combinations were both randomly and systematically selected using 12 to 14 RTDs per calculation.

The instrument Selection Guide (Test System Instrument Error Analysis) was recalculated based on using 14 RTDs vs the 46 RTDs used during the test.

The variance between the actual test calculated leak rate and the worst case condition using the various combinations of RTDs was less than 4 of the Instrument Selection Guide Value for 14 RTDs.

It is believed that these calculations verify that the placement of the RTDs was suitable.

D)

The Type A supplemental test was performed to verify the accuracy of the Test, Instrumentation.

The Appendix J acceptance criteria for this test is for the two tests to correlate within 0.25La.

The correlation for this set of tests was 0.026La.

Again, this verifies the adequacy of the Test Instrumentation.

It is felt that the existing temperature sensor locations for both units are adequate and have been verified by test experience.

Future tests will not require temperature surveys.

NRC Unresolved Item 315/85025-06 "The licensee's local leak rate test (LLRT) results for this outage were far in excess of the 0.6 La Technical Specification and Appendix J requirement for the sum of penetration and isolation valve leakages.

Additional review revealed that previous refueling outages also had excessive LLRT results.

This violation of the 0.6 La limit for penetration and isolation valve leakage and the continuing failure of isolation valves may be indicative of inadequate corrective action taken by the Licensee.

In order to resolve this matter, the licensee is requested to submit a list of isolation valves that have been consistently failing their local leak rate test, a summary of the corrective actions taken to correct the

failures, and current plans to preclude the continuing failures of these valves.

Review of this information relative to the adequacy of past and planned corrective action will be tracked as an unresolved item (315/85025-06(DRS))."

AEP:NRC:0961 Attachment Page 4

~Res ense Maintenance of containment isolation valves has not been ignored.

Over the life of the Plant substantial numbers of valves have been replaced or reworked.

The attached Table 1 is a summary of all valves which have required repair or replacement since the first set of periodic tests in 1976.

Please note that of the 210 valves tested, 106 have leaked at some time.

Of these 106 valves, 52 have been successfully replaced or reworked to eliminate leakage.

Of the remaining 54 valves, only 11 have leaked on 3 or more ocassions.

Of these 11 valves (indicated by an

  • in Table 1),

5 are check valves, 4 are globe valves on air or air sample

systems, and 2

are globe valves on the containment ventilation unit drain lines.

As shown in Table 1, during the 1985 Unit 1 refueling 'outage one of these valves was completely replaced with a new valve, four of the valves had the internals replaced and the remaining 6 valves were repaired or maintained.

We will continue to monitor valve performance to determine if further action is required.

Additional information on this topic will be included in the final test report for this ILRT.

TABLE l Valve NSW-415-1 76 77 Unit 81 Leak Rate Test Failures 78 79 80 81 82 X

X XD 83 85 NSW-415-2 NSW-415-3 NSW-415-4 NSW-417-3 NSW-417-4 X

X X

X X

XD XD XD X

X X

X X

XD XD XD

'SW-419-1 X

NSW-419-2 NSW-419-3 NSW-419-4 D

X X

XD X

-X X

X D

NSW-244-1 X

XD X

X NSW<<244-2 NSW-244-3 NSW-244-4 X

X X

XD XD X

X X

WCR-902 WCR-903 WCR-905 WCR-906 X

X X

X X

XD

Valve 76 77 TABLE 1 (cont')

78 79 80 81 82 83 85 WCR-907 X

X WCR-909 WCR-910 WCR-911 WCR-913 X

X X

X WCR-914 X

X WCR-915 WCR-921 WCR-922 X

X X

X X

X XD WCR-923 WCR-925 WCR-926 WCR-929 X

X D

WCR-930 X

WCR-931 WCR-933 WCR-934 X

WCR-935

Valve 76 77 TABLE 1

(cont'd) 78 79 80 81 82 83 85 WCR-945 X

D WCR-946 X

X X

XD WCR-947 WCR-958 WCR-965 X

X WCR-966 WCR-967 VCR-103 VCR-203 VCR-104 X

X XD

-VCR-204 X

VCR-105 VCR-205 VCR-106 X

X X

X X

X D

D X

X VCR-206 X

X VCR-10 VCR-11 X

VCR-20 VCR-21 X

TABLE 1 (cont'd) er Valve 76 77 78 79 80 81 82 83 85 ECR-15 X

X

  • ECR-31 X

X XR

  • ECR-32 XR ECR-33 DCR-611 X
  • DCR-620
  • DCR-621 DCR-205 DCR-206 X

X X

X X

X X

XR XR NCR-105 NCR-106 X

NCR-252 X

XCR-101

  • XCR-102 XCR-103
  • XCR-100 X

X X

X GCR-314 GCR-301 X

X

  • CA-181-N

Valve 76 77 TABLE 1 (cont'd) 78 79 80 81 82 83 85 CA-181-S

  • SI-189 ICM-260 ICM-265 ICM-306 CCR-457 CCR-460 X

X X

X X

X X

X CCR-462

  • CCW-135 CCR-440 CCR-441 X

X X

X X

CCW-243-72 X

X CCW-244-72 CCW-243-25 R-156 X

X X

X R-159 R-157 R-158 N-102 X

X

Valve 76 77 TABLE 1 (cont'd) 78 79 80 81 82 83 85 sI

  • N-159 N-160 CM-250 CM-350 SF-159 X

X X

XR XP X

X XR SF-160 CS-321 CS-442-3 X

DW-275 X

PPP-303 NS-357

  • SM-1 SM-2 X

X X

NOTE:

X Denotes valve repaired R Denotes valve replaced or valve internals replaced D Denotes valve replaced with valve of different design or design change to existing valve P Denotes change to piping

  • Denotes problem valves

I g BENT)