Summary of 820430 Meeting W/Util in Bethesda,Md Re Continued Safe Operation of Plant.Attendee List Encl
ML17319B348
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 05/21/1982
From: Cilimberg R
Office of Nuclear Reactor Regulation
To:
Office of Nuclear Reactor Regulation
References
NUDOCS 8206030323
Download: ML17319B348 (11)


Text

Docket Nos. 50-315 and 50-316 IH~v 2)

~gyp

"~C>VEQ

~<<~8 ~982~

'P LICENSEE; Indiana and Michigan Electric Company FACILITIES:

Donald C.

Cook Nuclear Plant Unit Nos.

1 and 2

SUMMARY

OF MEETING HELD ON APRIL 30, 1982 TO DISCUSS CONTINUED SAFE OPERATION OF D. C.

COOK PLANT

~kd The meeting was held in room P-422 in the NRC headquarters at 7920 Norfolk Avenue, Bethesda, Maryland.

Attendees are listed in Enclosure 1.

In a memo from R. L. Spessard to D. G. Eisenhut dated April 23, 1982, NRR was advised that the D. C. Cook Nuclear Plant Units 1 and 2 do not meet 10 CFR 50, Appendix R requirements.

Region III requested technical assistance from NRR to evaluate the safety significance of the findings of the fire protection inspection of Cook plant conducted on April 12-16, 1982.

NRR responded to that request with this ex'peditious meeting with the licensee.

~ti t

k The NRC position was stated as follows:

The Appendix R inspection conducted at the D. C. Cook Nuclear Plant on April 12-16, 1982, has raised questions about the continued safe operation of the plant should a fire occur in the Sable vault.. The licensee was asked to provide NRC with the basis and justification for continued safe operation.

R. S. Hunter replied that he did not know when the Cook plant would be in coppliance with Appendix R, because he thought he knew what Appendix R meant and now he realizes that his interpretation was incorrect.

Mr. Hunter fOr ther stated that since he can not guar'ahtee that a fire will not occur in the cable vault that concentrated short'term effort. was on fine tuning administrative procedures.

Those procedures for hot and cold shut down were presented by the licensee but will not be discussed her e because they are detailed in the licensee's letter to H. Denton dated May 4, 1982.

S206030323 82052i PDR ADOCK 050003l5 P

PDR OFFICE 0

~

SURNAME/.

DATE0 NRC FORM 318 (10-80) NRCM 0240

~ d ~ ~ 0 ~ ~ ~ 0 ~ Od ~ d ~ d ~ 00 ~ d ~ d ~

I OFFICIAL RECORD COPY USGA): 1981-388-980

C

~

~

U

\\

2 Ih. Hunter assured the NRC that INEC is diligently addressing al.l of the questions associated with the findings of fire protection inspections conducted by Region III.

D. G. Eisenhut emphasized the concern of NRC over the safety of the plant and agreed with continued operation provided the licensee would respond to his specific direction.

R. S. Hunhpr stated that INEC would respond to that specific direction.

D. G. Eisenhut directed R. 8. Hunter. of AEP to do the fohIowing:

l.

Send a letter to NRC by COB May 3, 1982, which addresses D. C.

Cook plant safety relative 2 fire protection as follows:

a.

Recognition by the licensee of the problems and corrective action needed.

b.

Basis for contiq ed safe operation of the plant.

c; Descifbe a complete program to be implemented by June 4, 1982 which will provide equipment and trained personnel to achieve hot and cold shutdown 4f -the plant if a fire occurs in the cable vault.

d.

Desc'bribe a program for emergency lighting along with the schedule for completion, e.

Explain why there is no problem with oil collection.

f.

Reassess whether D.

C.

Cook meets Appendix R and request anrtexemption.

2.

Send a letter to NRC by COB May 10, 1982, which describes what the licensee will do to comply with the requirements of Appendix R to -CAGlude

)jt not be limited to the following:

a.

Describe a long term program with schedule for meeting Appendix R.

b.

Provide a list of systems and scope of work which deals sp~fically with hot and cold shutdown should a fire occur in the cable vault.

c.

Explain what AEP/IHEC management is doing to expedite a

NRC requirement which is over one year late.

OFFICEIp SURNAME/

DATE0 NRG, FORM 318 (10-80) NRCM 0240 OFFICIAL RECORD COPY USQ PO: 1981~5.960

r r l

~ -

lb'"

II

~

El' t

II

3 Nr. Eisenhut emphasized again that the purpose of the meeting was to Justify continued operations and the safety of the D. C.

Cook Nuclear Plant.

Future Actions Licensee submittals will be reviewed by NRC tIlith further action to be determined by the r esults of these reviews and licensee responsiveness.

Tar e5 Dates

Response

to NRC May 3, 1982

Response

to NRC Hay 10, 1982 Short Term program in

'Uune 4, 1982 place (includes training, marking of equipment, and walkthrough)

Enclosure:

List of Attendees jc w/encl osur es See next page ORIGIN, SZGNgg Ramon L. fklimberg, Project Manager Operating Reactors Branch Pl Division of Licensing ORBIIIl:

OFFICE)

~ ~ e ~i~ ~ ~ ~ ~ ~ ~ o ~ ~ ~

~

RCilim erg ORBImr1: DL SVarga I~ 0 ~ ~ ~ 0 ~

~ ~t ~ ~ 0 ~I~ ~ 0 ~ 0 ~I

~I~ 0 ~ ~ ~ ~ OtÃ1 ~ 0 ~ JHOW ~ 0 ~ 0 NRG FORM 318 u0-80) NRCM 0240 OFFlCIAL RECORD COPY USGPO: 1981~5.960

1 II

MEETING

SUMMARY

OPERATING REACTORS BRANCH NO.

1 DIVISION OF LICENSING Docket File NRC PDR Local PDR ORB 1 File J.

Heltemes, AEOD B. Grimes S.

Varga Project Manager OELD OIaE (1)

ACRS (10)

NRC Participants NSIC cc:

Licensee with Service List

NAME ENCLOSURE ATTENDANCE LIST D.

C.

COOK FIRE PROTECTION MEETING APRIL 30, 1982 ROOM P-422 ORGANIZATION E.

D.

T.

R.

D.

T.

R.

L.

V.

T.

G.

G.

M.

L.

L.

V.

J.

S.

W.

L.

Case Eisenhut Novak Cilimberg Wigginton Wambach Mattson Rubenstein Panciera Chan NRR NRR/DL NRR/DL NRR/DL/ORB-1 NRR/DL/ORB-1 NRR/DL/ORB-5 NRR/DSI NRR/DS I/CPS NRR/DS I/CPS/ASB NRR/DSI/CPS/ASB W.

V.

R.

R.

V. Johnston Benaroya L. Ferguson Eberly NRR/DE/MQE NRR/DE/CHEB NRR/DE/CHEB NRR/DE/CHEB H.

D.

H.

P.

J.

J.

C.

L.

L.

B.

R.

M.

C.

J.

Thompson, Jr.

Ziemann Clayton Mathews Taylor Stone Haughney NRR/HFS NRR/HFS/PTRB NRR/HFS/PTRB NRR/DST/LGB OIE/DRP OI E/DRP OIE/DRP R.

J.

C.

E.

R.

R.

H.

J.

S.

A.

R.

R.

S.

G.

S.

Spessard A. Grobe C.

R.

S.

W.

L.

G.

H.

S.

Williams Swanson Hunter Jurgensen Sobel DelPercio Steinhart Grimes M.

P.

N.

E.

Fox Field Horowitz King L..'Schoberg J.

Daley RGN III/EDO RGN III/EDO RGN III/EDO RGN III/SRI - D.

C.

Cook AEP/IMEC AEP/IMEC AEP/IMEC AEP/IMEC AEP/IMEC AEP/IMEC AEP/IMEC AEP/IMEC AEP/IMEC AEP/IMEC AEP/IMEC AEP/IMEC

NAME W.

G. Smith, Jr.

B. L. Svensson L.

K. Smith ORGANIZATION D.

C.

Cook P1ant Manager D.

C.

Cook Asst.

P1ant Manager D.

C.

Cook Staff

Mr. John Dolan Indiana and Michigan Electric Company CC:

Mr. Robert W. Jurgensen Chief Nuclear Engineer American Electric Power Service Corporation 2 Broadway New York, New York 10004 Gerald Charnoff, Esquire

Shaw, Pi ttman, Potts and Trowbridge 1800 M Street, N.W.

Washington, D. C.

20036 Maude Preston Palenske Memorial Library 500 Market Street St. Joseph, Michigan 49085 W.

G. Smith, Jr., Plant Manager Donald C. Cook Nuclear Plant P. 0.

Box 458 Bridgman, Michigan 49106 U. S. Nuclear Regulatory Commission Resident Inspectors Office 7700 Red Arrow Highway Stevensville, Michigan 49127 William J. Scanlon, Esquire 2034 Pauline Boulevard Ann Arbor, Michigan 48103 The Honorable Tom Corcoran United States House of Representatives Washington, D. C.

20515 James G. Keppler Regional Administrator - Region III U. S. Nuclear Regulatory Commission 799 Roosevelt Road Glen Ellyn, Illinois 60137

t P

Kv

~

~