Responds to NRC Re Violations Noted in IE Insp Repts 50-315/80-19 & 50-316/80-15.Corrective Actions: Repaired Penetration Fire Seals.Memo Issued Re Fire Seals Requirements
ML17319A739
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 01/28/1981
From: Dolan J
INDIANA MICHIGAN POWER CO.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
Shared Package
ML17319A738 List:
References
AEP:NRC:00511, AEP:NRC:511, NUDOCS 8103060297
Download: ML17319A739 (5)


Text

el

. INDIANA IIt MICHIGAN ELECTRIC COMPANY P. O. BOX 18 Bo WLIN G G R E EN ST ATION NEW YORK, N. Y. 10004

'I

,d January 28, 1981 AEP:NRC;00511 Donald C.

Cook Nuclear Plant Unit Nos.

1 and 2

Docket Nos.

50-315 and 50-316 License Nos.

DPR-58 and; DPR-74 IE Inspection Report Nos.

50-315/80-19 and 50-316/80-15, Nr. James G. Keppler, Regional Director U. S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region III Glen Ellyn, Illinois 60137

Dear Nr. Keppler:

The attachment to this letter provides our response to the Notice of Violation contained in Appendix A of IE Inspection Report 'Nos. 50-315/

80-19 and 50-316/80-15 which we received on January 6, 1981.

On January 15, 1981 Hr. Heishman of your Staff granted our request for an extension to respond to the Notice of Violation within 25 days from the date on which we received the inspection report.

Very truly yours, CC:

R.

C. Callen ohn E. Dolan ice President G. Charnoff R. S. Hunter R.

M. Jurgensen D. V. Shaller - Bridgman Region III Resident Inspector at Cook Plant - Bridgman 33l 9998 9 QQ

STATE OF NEW YORK COUNTY OF NEW YORK John E. Dolan, being duly sworn, deposes and says that he is the Vice President of Licensee Indiana 8 Michigan Electric Company, that he has read the foregoing response to the notice of violation contained in IE Inspection Report Nos.

50-315/80-19 and 50-316/80-15 and knows the contents thereof; and that said contents are true to the best of his knowledge and belief.

Subscribed and sworn to before me this 8

day of J aaY 981 GRc33icY 4).

Cilmi:AM Noiay pvo!:"..":-:o "'iow York Quatiflcd in 1". VYo.k Coonhf Colntnl$5ion Expifcs h/c foil 30'igni%

II,I

)

ATTACHMENT TO AEP:NRC:0511 In accordance with the requirements of the notice subject of this response we provide the following information:

a)

The reason for the items of noncompliance is that dur ing the period of time that this inspection was conducted we were implementing design changes in the Cook Plant which required pulling cables through penetration fire seals in the cable vault.

It was during the implementation of these changes that the two of them were made non-functional thereby exceeding the limiting condition of operation of Technical Specification 3/4.7.10.

l~h b)

The corrective steps taken were to immediately repair the penetration fire seals by either the plant approved temporary repair mechanism or repaired permanently utilizing the plant approved repair procedure.

They were subsequently inspected and accepted on December 4,

1980, by the Plant gC Department..

c)

To preclude further items of non-compliance, a memo from the Cook Plant Construction Department was trans-mitted on December 8, 1980 to all contractors reiterating the Donald C.

Cook Nuclear Plant's requirements on pene-tration fire seals.

In addition Plant Manager Instruction PMI-2270, entitled "Fire Protection and Safety Equipment",

was revised by a temporary change sheet which amplifies the requirements and the responsibilities for those people who have the potential for breaching or coming across a fire seal within the plant that has been breached.

Full compliance was achieved by the issuance of these documents.

~~-)