Requests 90-day Extension to Complete Nondestructive Examination Required by IE Bulletin 79-17,Item 2.Delay Due to Shortage of Trained Personnel
ML17318A402
Person / Time
Site: Cook  American Electric Power icon.png
Issue date: 10/23/1979
From: Dolan J
AMERICAN ELECTRIC POWER CO., INC.
To: James Keppler
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION III)
References
IEB-79-17, NUDOCS 7911090072
Download: ML17318A402 (2)


Text

AMERICANELECTRIC POWER Service Corporation AEP 2 Broadway, Now York, N. Y. 10004 (212) 440-9000 JOHN E. DOLAN Vice Chairman Eagiaccriag aad Construction (2J2) 440-8200 October 23, 1979 AEP:NRC:00255B Donald C, Cook Nuclear Plant Units 1

and 2

Dockets No. 50-315 and 50-316 Licenses No.

DPR-58 and DPR-74 Inspections Required by IE Bulletin 79-17 Nr. J.

G. Keppler, Regional Director U.S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region I'II 799 Roosevelt Road Glen Ellyn, IL.

60137

Dear Hr. Keppler:

We have been informed by our nondestructive examination (NDE) contractor that they will not be able to complete the NDE required by Item 2 of IE Bulletin 79-17 according to 'the schedule indicated in Item 6 of the same Bulletin.

The inability to meet the Bulletin's schedule is due primarily to the shortage of trained personnel re-quired to perform the NDE and prepare the report.

We therefore re-quest an extension of 90 days beyond the deadlines of Item 6 for both the completion of the inspections and the submittal of the re-port.

This request supercedes the request for an extension made in our submittal AEP:NRC:00255A to Nr. fhrold R. Denton dated September 27, 1979.

Very truly yours, JED:em T. /

ohn E, Dolan CC:

Norman C. Noseley -

NRC R.

C. Callen G. Charnoff D. V. Shaller

-Bridgman R.

S.

Hunter R.

W. Jurgensen