AMERICANELECTRIC POWER Service Corporation AEP 2 Broadway, Now York, N. Y. 10004 (212) 440-9000 JOHN E. DOLAN Vice Chairman Eagiaccriag aad Construction (2J2) 440-8200 October 23, 1979 AEP:NRC:00255B Donald C, Cook Nuclear Plant Units 1
and 2
Dockets No. 50-315 and 50-316 Licenses No.
DPR-58 and DPR-74 Inspections Required by IE Bulletin 79-17 Nr. J.
G. Keppler, Regional Director U.S. Nuclear Regulatory Commission Office of Inspection and Enforcement Region I'II 799 Roosevelt Road Glen Ellyn, IL.
60137
Dear Hr. Keppler:
We have been informed by our nondestructive examination (NDE) contractor that they will not be able to complete the NDE required by Item 2 of IE Bulletin 79-17 according to 'the schedule indicated in Item 6 of the same Bulletin.
The inability to meet the Bulletin's schedule is due primarily to the shortage of trained personnel re-quired to perform the NDE and prepare the report.
We therefore re-quest an extension of 90 days beyond the deadlines of Item 6 for both the completion of the inspections and the submittal of the re-port.
This request supercedes the request for an extension made in our submittal AEP:NRC:00255A to Nr. fhrold R. Denton dated September 27, 1979.
Very truly yours, JED:em T. /
ohn E, Dolan CC:
Norman C. Noseley -
NRC R.
C. Callen G. Charnoff D. V. Shaller
-Bridgman R.
S.
Hunter R.
W. Jurgensen