UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 RIZONA PUBLIC SERVICE COMPANY ET AL.
DOCKET NO.
STN 50-528 PALO VERDE NUCLEAR GENERATING STATION UNIT NO.
1 MENDMENT TO FACILITY OPERATING LICENSE Amendment No.
112 License No.
NPF-41 1.
The Nuclear Regulatory Commission (the Commission) has found that:
A.
B.
C.
The application for amendment by the Arizona Public Service Company (APS or the licensee) on behalf of itself and the Salt River Project Agricultural Improvement and Power District, El Paso Electric Company, Southern California Edison Company,,'Public Service Company, of New Mexico, Los Angeles Department of Water and
- Power, and Southern California Public Power Authority dated December 27,
- 1996, as supplemented by letter dated March 18,
- 1997, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; There is reasonable assurance (i) that the activities authorized by-this amendment can. be conducted without endangering the health and safety.of the public, and (ii) that such activities will be conducted in compl.iance with the Commission's regulations; 2.
D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
Accordingly, the license is amended to authorize changes to the Updated Final Safety Analysis Report and paragraph 2.C.(14) of Facility Operating License 'No. NPF-41 is hereby amended to read as follows:
9704070303 970326 PDR ADOCK 05000528 P
II 0
~ '
3.
(14) dditional Conditions The Additional Conditions contained in Appendix D, as revised through Amendment No. 112, are hereby incorporated into this license.
Arizona Public Service Company shall operate the facility in accordance with the Additional Conditions.
This license amendment is effective immediately, and shall be implemented within 60 days of the date of issuance.
Implementation of the amendment is the incorporation into the Updated Final Safety Analysis Report of the changes to the description of the facility as described in the licensee's application dated December 27,
- 1996, as supplemented by letter dated March 18,
- 1997, and evaluated in the staff's Safety Evaluation attached to this amendment.
FOR THE NUCLEAR REGULATORY COMMISSION Jk William H. Bateman, Director Project Directorate IV-2 Division of Reactor Projects III/IV Office of Nuclear Reactor Regulation
Attachment:
Appendix D-Additional Conditions Date of Issuance:
March 26, 1997
0
!l
PPENDIX 'D ADDITIONAL CONDI ONS ACILITY OPERATING LICENSE NO. NPF-41 Arizona Public 'Service Company shall comply with the following condi.tions on the schedules noted below:
Amendment Number 112 dditional Condi tion This amendment authorizes the licensee to incorporate in the Updated Final Safety Analysis Report (UFSAR) certain changes to the description of the facility.
Implementation of this amendment is the incorporation of these changes as described in the licensee's application dated May 2,
- 1995, as supplemented by letter dated March 7,
- 1996, and evaluated in the staff's Safety Evaluation dated March 17, 1997..
This amendment authorizes the licensee to incorporate in the Updated Final Safety Analysis Report (UFSAR) certain changes to the description of the facility.
Implementation of this amendment is the incorporation of these changes as described in the licensee's application dated December 27,
- 1996, as supplemented by letter dated March 18,
- 1997, and evaluated in the staff's Safety Evaluation dated March: 26, 1997.
Implementation Date 60 days from the date of issuance.
60 days from the date of issuance.
.Amendment No.
khan, 112
41 0
II
gAS RE00
~4
~o Cy A,
p OO O
+~
~o
++*++
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON> D.C. 205554001 RIZONA PUBLIC SERVICE COMPANY ET AL.
OCKET NO.
STN 50-529 PALO VERDE NUCLEA GENERATING STAT ON UNIT NO.
2 MENDMENT TO FACILITY OPERAT NG LICENSE Amendment No.
104 License No. NPF-51 The Nuclear Regulatory Commission (the Commissioh) has found that:
A.
The application for amendment by the Arizona Public Service Company (APS or the licensee) on behalf of itself and the Salt River Project Agricultural Improvement and Power District, El Paso Electric Company, Southern California Edison
- Company, Public Service Company of New Mexico, Los Angeles Department of Water and
- Power, and Southern California Public Power Authority dated December 27,
- 1996, as supplemented by letter dated March 18,
- 1997, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B.
The facility will operate in tonformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted wi,thout endangering the health and safety of the public, and (ii') that such activities will.be conducted in compliance, with the Commission's regulations; 2.
D.
The issuance of this amendment will not be 'inimical'o the common defense and security or, to the health; and safety of, the public; and E.
The issuance of this amendment is.in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
Accordingly, the license is amended to authorize changes to the Updated Final Safety Analysis Report and paragraph 2.C.(9) of Facility Operating License No.
NPF-51 is hereby amended to read as follows:
Cl
3.
(9) dditional Conditions r
The Additional Condi,tions contained in Appendix D; as revised through Amendment No. 104, are hereby incorporated into this license.
Arizona Public Service Company shall operate the facil.ity in accordance with the Additional Conditions.
This license amendment is effectivq immediately, and shall be implemented within 60 days of the date of issuance.
Implementation of the amendment is the incorporation into the Updated Final Safety Analysis Report of the changes to the description of the facility as described in the licensee's application dated December 27,
- 1996, as supplemented by letter, dated March 18,
- 1997, and evaluated in the staff's Safety Evaluation attached to this amendment.
FOR THE NUCLEAR REGULATORY COMMISSION William H. Bateman, Director Project Directorate IV-'
Division of Reactor Projects III/IV Office of Nuclear Reactor Regulation
Attachment:
Appendix 0-Additional Conditions Date of Issuance:
March 26, 1997
41 II
APPENDIX D DDITIONAL CONDITIONS ACILITY OPERATING L CENSE NO.'NPF-51 Arizona Public Service Company shall comply with the following conditions on the schedules noted below:
Amendment Number dditional Condition.
Implementation Date 103 104 This amendment authorizes the licensee to incorporate in the Updated'inal Safety Analysis Report (UFSAR) certain changes to the description of the facility.
Implementation of this amendment is the incorporation of these changes as described in the licensee's application dated May 2,
- 1995, as supplemented by letter dated March 7,
- 1996, and evaluated in the staff's Safety Evaluation dated March 17, 1997.
'This amendment authorizes the licensee to incorporate in the Updated Final Safety Analysis Report (UFSAR) certain changes to the description of the facil,ity.
Implementation of this amendment is the incorporation of these changes as described in the licensee's application, dated December 27,
- 1996, as supplemented by
. letter dated March 18,
- 1997, and evaluated in the staff's Safety Evaluation dated
.March 26, 1997.
60 days from. the date of issuance.
60 days from the date of issuance.
Amendment No. 493,104
4l II
gAg RE00
~4
~o Cy ClO I
%0 C
O~
V/
gO
++**+
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 2055&4001 RIZONA PUBLIC SERVICE COMPANY ET AL.
OCKET NO.
STN 50-530 P
LO VERDE NUCLEAR GENERATING STATION UNIT NO.
3 MENDMENT TO FACILITY OPERATING ICENSE Amendment No. 84 License No. NPF-74 1.
The Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by the Arizona Public Service Company (APS or the licensee) on behalf of itself and the Salt River Project Agricultural Improvement and Power District, El Paso Electric Company, Southern California Edison
- Company, Public Service Company of New Mexico, Los Angeles Department of Water and
- Power, and Southern California Public Power Authority dated December 27,
- 1996, as supplemented by letter dated March 18,
- 1997, compl'.ies with the standards and requirements of the Atomic Energy Act of 1954, as -amended (the Act) and the Commission's regulations set forth in 10 CFR Chapter I; B.
C.
The facility will operate in tonformity with the application, the provisions of the Act, and the rules and regulations of the Commission; There is reasonable assurance,(i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.
2.
Accordingly, the license is amended to authorize changes to the Updated Final Safety Analysis Report and paragraph 2.C.(5) of Facility Operating License No. NPF-74 is hereby amended to read as follows:
II I
P
3.
(5) dditional Condi tions The Additional Condi tions contained in Appendi x D, as revi sed through Amendment No. '84, are hereby incorporated into this license.
Arizona Public Service Company shall operate the facility. in accordance with the Additional Conditions.
This license amendment is effective immediately, and shall be implemented within 60 days of the date of issuance.
Implementation of the amendment is the incorporation into the Updated Final Safety Analysis Report of the changes to the description of the facility as described in the licensee's application dated December 27,
- 1996, as supplemented by letter dated Narch 18,
- 1997, and evaluated in the staff's Safety Evaluation attached to this amendment.
FOR THE NUCLEAR REGULATORY COMMISSION William H. Bateman, Director Project Directorate IV-2 Division of Reactor'Projects III/IV Office of Nuclear Reactor Regulation
Attachment:
Appendix D-Additional Conditions Date of Issuance:
Narch 26, 1997
0 Cl I'
APPENDIX D DDITIONAL CONDITIONS FACILITY OPERATING L'ICENSE NO.
NPF-74 Arizona Public Service Company shall comply with. the following conditions. on the schedules noted below:
Amendment Number 83 84 dditional'ondition This amendment authorizes the licensee. to incorporate in. the Updated Final Safety Analysis 'Report (UFSAR) certain changes to the description of the facili.ty.
Implementation of this amendment is the incorporation of these changes as described, in the licensee's application dated Nay 2,
- 1995, as supplemented by letter dated Narch 7.,
- 1996, and evaluated in the staff's Safety Evaluation dated'arch 17, 1997.
This amendment authorizes the l.icensee to incorporate in the Updated Final Safety Analysis Report (UFSAR) certain changes
.to the description of the facility.
Implementation of this amendment is the incorporation of these changes as described in, the licensee's application dated December 27,
- 1996, as supplemented by letter'ated Parch
-18,
- 1997, and evaluated in the staff's Safety Evaluation dated March 26, 1997.
Implementation Date 60 days from the date of issuance.
60 days from the date of issuance.
Amendment No. 88,84
Ol