Informs That 990406 Request to Extend Second ten-year ISI Program Plan Interval for WNP-2 to Dec 12,2005,within Provisions of ASME Section XI,IWA-2430, Insp Intervals, Paragraph (D) & Acceptable to Staff
ML17292B670
Person / Time
Site: Columbia 
Issue date: 05/20/1999
From: Jack Cushing
NRC (Affiliation Not Assigned)
To: Parrish J
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
References
NUDOCS 9905250323
Download: ML17292B670 (5)


Text

REGULATO Y INFORMATION DISTRXBUTION SYSTEM (RXDS)

RECIPIENT AFFILIATION Washington Public Power Supply System

SUBJECT:

Xnforms that 990406 recpxest to extend second ten-year ISI program plan interval for WNP-2 to Dec 12,2005,within

'rovisions of ASME Section XI,IWA-2430, "Insp Intervals,"

Paragraph (d)

& acceptable to staff.

DISTRIBUTION CODE:

DF01D COPIES RECEIVED:LTR i

ENCL g TITLE: Direct Flow D'stribution:

50 Docket (PDR Avail)

SIZE:

~

NOTES:

ACCESSION NBR:9905250323 DOC.DATE: 99/05/20 NOTARIZED: NO FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe AU~i'H. NA'HE AUTHOR AFFILIATION CUSHXNG,J; RECXP.NAME PARRXSH,J.V.

DOCKET ¹ 05000397 E

RECIPIENT ID CODE/NAME INTERNA

. FILE CENTER 01 EXTERNAL: NOAC COPIES LTTR ENCL RECIPIENT XD CODE/NAME NUDOCS-ABSTRACT NRC PDR COPIES LTTR ENCL D

0 NOTE TO ALL "RIDS" RECZPZENTS:

PLEASE HELP US TO REDUCE WASTE.

TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM'DISTRIBUTION LISTS OR REDUCE THE NUMBER OF COPZES RECEIVED BY YOU OR YOUR ORGANIZATION, CONTACT THE DOCUMENT CONTROL DESK (DCD)

ON EXTENSION 415-2083 0

TOTAL NUMBER OF COPIES REQUIRED:

LTTR 4

ENCL

Nay 20, 1999 Mr. J. V. Parrish

'hief'Executive Officer Washington Public Power Supply System P.O. Box 968 (Mail Drop 1023)

Richland, WA 99352-0968

SUBJECT:

EXTENSION OF SECOND 10-YEAR INSERVICE INSPECTION PROGRAM PLAN

Dear Mr. Parrish:

On April6, 1999, Washington Public Power Supply System (Supply System) informed the staff of its plan to extend the Second Ten-Year Inservice Inspection Program Plan interval for WNP-2 one year to December 12, 2005. The one-year extension is needed due to changes in the refueling outage schedule for WNP-2. The extension is within the provisions of the American Society of Mechanical Engineers (ASME)Section XI, IWA-2430, "Inspection Intervals," Paragraph (d), and is acceptable to the staff.

Ifyou have any questions, please contact me at (301) 415-1424.

Sincerely,

/s/

Docket No. 50-397 cc: See next page Jack Gushing, Project Manager, Section 2 Project Directorate IV& Decommissioning Division of Licensing Project Management Office of Nuclear Reactor Regulation DISTRIBUTION Docket File PUBLIC PDIV-2 Reading JZwolinski/S Black S Richards JCushin EPeyton OGC ACRS LSmith, RGN-IV KBrockman, RGN-IV Glmbro OFFICE PDIV-2/PM PDIV-2/LA NAME JCushin:rb 5

~eon DATE 5

/99 5/5/99 OFFICIAL RECORD COPY DOCUMENT NAME: G:iWNP2iLTRISI.WPD 1

99Omsoms 9eOS2o PDR ADQCK Q5000397 8

PDR L'I

'.I.'

RRV PMlhu 5 /9/99 PDIV-2/SC SDembe 5/

/9

11 4

1 fh I

I I,I I

gP,R R500

~o Cy ClO C

+~

~0

++*++

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 May'20, 1999 Mr. J. V. Parrish Chief Executive Officer Washington Public Power Supply System P.O. Box 968 (Mail Drop 1023)

Richland, WA 99352-0968

SUBJECT:

EXTENSION OF SECOND 10-YEAR INSERVICE INSPECTION PROGRAM PLAN

Dear Mr. Parrish:

On April 6, 1999, Washington Public Power Supply System (Supply System) informed the staff of its plan to extend the Second Ten-Year Inservice Inspection Program Plan interval for WNP-2 one year to December 12, 2005. The one-year extension is needed due to changes in the refueling outage schedule for WNP-2. The extension is within the provisions of the American Society of Mechanical Engineers (ASME)Section XI, IWA-2430, "Inspection Intervals," Paragraph (d), and is acceptable to the staff.

Ifyou have any questions, please contact me at (301) 415-1424.

Sincerely, Docket No. 50-397 cc: See next page Jack Gushing, Project Manager, Section 2 Project Directorate IV& Decommissioning Division of Licensing Project Management Office of Nuclear Reactor Regulation

Nuclear Project No. 2 CC:

Mr. Greg O. Smith (Mail Drop 927M)

Vice President, Generation Washington Public Power Supply System P. O. Box 968 Richland, Washington 99352-0968 Mr. Albert E. Mouncer (Mail Drop 1396)

Chief Counsel Washington Public Power Supply System, P.O. Box 968 Richland, Washington 99352-0968 Ms. Deborah J. Ross, Chairman Energy Facility Site Evaluation Council P. O. Box 43172 Olympia, Washington 98504-3172 A

Mr. D. W. Coleman (Mail Drop PE20)

Regulatory Affairs Manager Washington Public Power Supply System P.O. Box 968 Richland, Washington 99352-0968 Mr. Paul Inserra (Mail Drop PE20)

Manager, Licensing Washington Public Power Supply System P.O. Box 968 Richland, Washington 99352 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower & Pavilion 611 Ryan Plaza Drive, Suite 400 Arlington, Texas 76011-8064 Chairman Benton County Board of Commissioners P.O. Box 69 Prosser, Washington 99350-0190 Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O. Box 69 Richland, Washington 99352-0968 Mr. Rodney L. Webring (Mail Drop PE08)

Vice President, Operations Support/PIO Washington Public Power Supply System P. O. Box 968 Richland, Washington 99352 Perry D. Robinson, Esq.

Winston 8 Strawn 1400 L Street, N.W.

Washington, DC 20005-3502 Mr. Bob Nichols Executive Policy Division Office of the Governor P.O. Box 43113 Olympia, Washington 98504-3113