ML17292A404

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/96-15 on 960624-0729.No Violations Noted. Major Areas Inspected:Radiological Waste Effluent Mgt Programs,Including Engineering & Plant Support
ML17292A404
Person / Time
Site: Columbia 
Issue date: 08/09/1996
From: Murray B, Nicholas J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
To:
Shared Package
ML17292A403 List:
References
50-397-96-15, NUDOCS 9608130319
Download: ML17292A404 (22)


See also: IR 05000397/1996015

Text

ENCLOSURE

U.S.

NUCLEAR REGULATORY COMMISSION

REGION IV

Docket No.:

License No.:

Report No.:

Licensee:

Facility:

Location:

Dates:

Inspector:

50-397

NPF-21

50-397/96-15

Washington Public Power Supply System

Washington Nuclear Project-2

3000 George Washington

Way

Richland,

Washington

June

24 through July 29.

1996

J. Blair Nicholas.

Ph.D.

~ Senior Radiation Specialist

Plant, Support

Branch

Approved By:

Blaine Murray, Chief. Plant Support

Branch

Division of Reactor Safety

ATTACHMENT:

Partial List of Persons

Contacted

List of Inspection

Procedures

Used,

List of Items Opened'losed'nd

Discussed

9608130319

960809

PDR

ADQCK 05000397

8

PDR

-2-

EXECUTIVE SUMMARY

Washington Nuclear Project-2

NRC Inspection Report 50-397/96-15

This routine,

announced

inspection

focused

on the licensee's

radiological

waste effluent management

programs.

En ineerin

No deviations to commitments in the Updated Final Safety Analysis Report

were identified (Section

E2. 1).

Plant

Su

ort

The liquid and gaseous

radioactive waste effluent management

programs

were properly implemented

(Section Rl. 1).

I

The radiochemistry counting facility was equipped with state-of-the-art

analytical instrumentation to perform. the required analyses.

Liquid and

gaseous

radioactive waste

management

systems

were installed

and operated

properly (Section

R2. 1).

Several effluent radiation monitors were out-of-service in excess of

Technical Specification requirements

during 1994 and

1995 indicating

poor system reliability. lack of timely engineering

support,

and poor

receipt inspection

performance

(Section R2.2).

An apparent violation involving the incor rect and non-conservative

calibration of the intermediate

range radiation monitor (PRM-RE-18) of

the reactor building stack effluent monitoring system,

which served

as

the required accident noble gas monitor,

was identified (Section R2.3).

Procedures

established

to implement the liquid and gaseous

radioactive

waste effluent management

programs

provided proper guidance.

The

radioactive waste effluent management

programs

were properly

implemented.

Amendments to the Offsite Dose Calculation

Manual were

properly documented.

The Annual Radioactive Effluent Release

Reports

for 1994 and

1995 were submitted in a timely manner

and contained the

required information presented

in the required format (Section

R3. 1)

The chemistry operations

supervisor,

effluents leader,

chemistry

technicians,

and equipment operators

had

an excellent understanding

of

the radioactive waste

management

procedures.

Offsite Dose Calculation

Manual,

and regulatory requirements

(Section

R4. 1).

Training programs

were properly implemented.

The chemistry

and

operations

departments

had well trained

and qualified staffs for

conducting radioactive waste effluent processing

and release

operations

(Section R5.1).

The chemistry technical staff reduction,

during the past

17 months. did

not appear to have

a negative affect on the performance of the

'adiological

waste effluent management

programs

(Section

R6. 1).

Oversight of the radioactive waste effluent management

programs

was

good.

Quality assurance

audits

and survei llances of the radioactive

waste effluent management

programs

and Offsite Dose Calculation

Manual

were technically comprehensive

and provided good program evaluation

and

oversight. identified deficiencies,

and

made

recommendations

for program

improvement.

The corrective action program was proper ly implemented

(Section R7.1).

Re ort Details

Summar

of Plant Status

The plant was undergoing startup testing from a refueling outage during the

inspection period.

There were no operational

occurrences

that impacted the

inspection.

III. En ineerin

E2

Engineering Support of Facilities and Equipment

E2. 1

U dated Final Safet

Anal sis

Re ort Review

a.

Ins ection Sco

e

A recent discovery of a licensee

operating their facility in a manner

contrary to the Updated Final Safety Analysis Report description

highlighted the need for a special

focused

review that compares

plant

practices,

procedures,

and/or parameters

to the Updated Final Safety

Analysis Report descriptions.

While performing the inspections

discussed

in this report, the inspector

reviewed the applicable portions

of the Updated Final Safety Analysis Report that related to the areas

inspected.to

ensure

agreement

with any commitments contained therein

pertaining to this inspection.

b. Observations

and Findin s

The inspector verified that the Updated Final Safety Analysis Report

wording was consistent with the observed plant practices.

procedures,

and/or parameters.

c. Conclusion

No deviations to commitments in the Updated Final Safety Analysis Report

were identified.

-5-

IV.

Plant

Su

ort

Radiological Protection

and Chemistry Controls

Radiolo ical Waste Effluent Mana ement

Pro rams

Ins ection Sco

e

84750

Implementation of the liquid and gaseous

radioactive waste effluent

management

programs

as described

in the Offsite Dose Calculation

Manual

including effluent waste processing.

effluent waste sampling

and

analyses,

analyses sensitivities,

analytical results. offsite dose

results,

and performance of required surveillance tests

were reviewed.

Observations

and Findin s

The inspector

reviewed approximately

12 batch radioactive liquid waste

effluent release

permits for the period January

1995 through

May 1996.

The inspector determined that the processing,

sampling,

and analyses

of

radioactive liquid waste effluent and the approval

and performance of

batch radioactive liquid waste discharges

were conducted in accordance

with Offsite Dose Calculation

Manual requirements.

'guantities of

radionuclides

released

in the radioactive liquid waste effluents were

within the limits specified in the Offsite Dose Calculation Manual.

Offsite doses

were calculated

according to the Offsite Dose Calculation

Manual

and were within the requi red limits.

Offsite Dose Calculation

Manual requi red analyses

on composite

samples of batch radioactive

liquid waste effluent releases

for gross alpha. tritium, strontium-89,

strontium-90,

and iron-55 were performed.

The inspector

observed

a chemistry technician collect

a sample from

Equipment Drain Tank 4B on June 26.

1996,

perform. a radiochemistry

analysis

(principal

gamma emitters)

on the sample,

and prepare the

radioactive liquid waste effluent batch release

permit.

The inspector

also accompanied

an equipment operator while performing the discharge

valve lineup and visited the control

room to verify that the instrument

and controls technicians

had properly set the alarm setpoints for the

liquid radwaste effluent radiation monitor as required

by the release

permit.

All aspects

of the equipment drain tank release

were performed

in accordance

with approved

procedures.

Selected

gaseous

waste effluent sample analyses

for samples

from the

main plant vent, turbine building vent,

and

r adwaste building vent

continuous

releases

and selected

gaseous

waste release

permits for batch

releases

for containment

vents

and purges

for the period January

1995

through

May 1996 were reviewed.

Sampling. analyses'nd

discharge of

the radioactive

gaseous

effluents

and the approval of the radioactive

gaseous

waste containment

vents

and purges

were conducted in accordance

with Offsite Dose Calculation

Manual requirements

and station

procedures.

-6-

R2

R2.1

It was noted that the sampling

and analysis

requirements

for containment

vents were changed in the Offsite Dose Calculation Manual since the

~ prior NRC inspection of this area.

This change stated,

that prior to

venting containment,

sampling

and analysis

were not required for primary

containment

vents. when the vent path was through the standby

gas

treatment

system,

and when containment

noble gas monitoring

instrumentation

indicated less than the alarm setpoint.

Therefore,

the

previous

requirement

to always sample the containment

atmosphere prior

to venting containment

had been eliminated.

This change

was part of

Amendment

18 to the Offsite Dose Calculation

Manual that was approved

by

the Plant Operations

Committee in April 1995.

This change to the

sampling

and analysis

requi rements for containment

vents in the Offsite

Dose Calculation

Manual

was unique to this licensee.

Quantities of gaseous

and airborne particulate radionuclides

released

were within the limits specified in the Offsite Dose Calculation Manual.

Offsite doses

were calculated

according to Offsite Dose Calculation

Manual methodologies

and were within required limits.

Particulate

effluent composite

sample analyses

for gross alpha,

strontium-89,

and

strontium-90 were performed

and met Offsite Dose Calculation

Manual

requirements.

The licensee

reported

no abnormal

releases

of radioactive liquid or

gaseous

waste during 1994 and 1995.

Conclusions

The liquid and gaseous

radioactive waste effluent management

programs

were properly implemented.

Quantities of radionuclides

released

in the

liquid and gaseous

radioactive waste effluents were within the Offsite

Dose Calculation

Manual limits.

Offsite doses to the environment

from

the liquid and gaseous

radioactive waste effluents were calculated

using

Offsite Dose Calculation

Manual methodologies,

and the dose results

were

within Offsite Dose Calculation

Manual limits.

Status of Radiological Protection

and Chemistry Facilities and Equipment

Radiochemistr

Countin

Facilit

and Radioactive

Waste Effluent

Processin

S stems

Ins ection

Sco

e

84750

The radiochemistry counting facility and associated

analytical

instrumentation

were inspected to verify if adequate calibration and

quality control programs

were in place.

The radioactive liquid waste

processing

equipment

was inspected to ensure

compliance with Updated

Final Safety Analysis Report

and Offsite Dose Calculation

Manual

requirements.

-7-

R2.2

a.

Observations

and Findin s

The radiochemistry counting facility maintained sufficient

state-of-the-art

analytical

instrumentation to perform the required

radiochemistry analytical

measurements

of the radioactive waste

effluents.

The radwaste building and the liquid radioactive waste

processing

equipment were inspected.

The floor drain tank, the two

equipment drain tanks'nd

the local sample points at each of the

radioactive liquid waste storage

tanks were inspected.

The liquid

radioactive waste processing

and storage

systems

were installed

as

described

in the Updated Final Safety Analysis Report

and were operated

in accordance

with station procedures.

No major equipment or design modifications were

made to the liquid or

gaseous

radioactive waste

managem'ent

systems

during 1995.

Conclusions

The radiochemistry counting facility was equipped with state-of-the-art

analytical instrumentation to perform the required analyses.

Liquid and

gaseous

radioactive waste

management

systems

were installed

and operated

properly.

Li uid and Gaseous

Effluent Radiation Monitors

Ins ection Sco

e

84750

The liquid and gaseous

effluent radiation monitors were inspected for

operation. calibration

~

and reliability.

Observations

and Findin s

The main plant vent release

monitor (reactor building effluent monitor)

was out-of-service for greater

than 30 days

from May 14.

1994. through

September

23." 1994.

A loss of vacuum

on the high purity germanium

detector

caused

the monitor to be inoperable.

The detector

is located

on the station's

refueling floor.

Therefore. it was not accessible

during refueling operations.

When the detector

repairs

began after

refueling operations

were completed.

the exact nature

and reason for the

detector failure was not known.

This resulted in an extended repair and

testing period.

The circumstances

which caused this extended

outage of

the monitor were documented

in Plant Evaluation Request

294-0563.

The turbine building ventilation exhaust

monitor was out-of-service for

greater than

30 days

from May 6,

1994, through July 24.

1994.

During

this equipment outage,

the turbine building exhaust

fan motors were

modified.

The modification increased

the maximum exhaust flow rate for

the turbine building from 320

F 000 cubic feet per minute (cfm) to 360,000

cfm.

This modification also required

a modification in the sampling

-8-

system to retain its ability to collect an isokinetic sample.

These

modifications required the monitor to be out-of-service for greater than

30 days.

The circumstances

which caused this extended

outage of the

monitor were documented

in Plant Evaluation Request

294-0702.

The reactor building effluent monitor (low range channel)

was

out-of-service greater

than 30 days

from October

19,

1995, through

December

27,

1995.

The replacement 'for the failed part, which was

stored in the onsite warehouse,

was

damaged in shipment.

This damage

was not recognized during the receipt inspection.

This extended the

monitor outage

because

the part was unique to the system.

and it had to

be returned to the manufacturer for repai r.

A detailed description of

the circumstances

associated

with the extended

outage of the monitor

were documented in Plant Evaluation Request

295-1207-01.

Conclusions

Each of the three Technical Specification required stack ventilation

effluent radiation monitors were out-of-service in excess of Technical

Specification requirements

during 1994 and 1995.

This indicated poor

system reliability, lack of timely engineering

support.

and poor receipt

inspection

performance.

Reactor

Bui ldin

Stack Effluent Monitor

PRM-RE-1B

Calibration Error

Ins ection Sco

e

84750

The inspector

reviewed the licensee's

preoperational

testing

and initial

primary calibration of the intermediate

range of the reactor building

stack effluent monitor (PRM-RE-lB), which was incorrectly and

non-conservatively calibrated.

Observations

and Findin s

Plant Modification Request

90-0305 (reactor building stack effluent

monitor) was developed to replace the original post-accident

grab sample

system with an on-line. continuous operating,

gamma spectroscopy

system

that would monitor both the normal operating

and post-accident

elevated

effluent releases

from the reactor building.

The intermediate

and high

range monitors of the reactor building stack effluent monitoring system.

governed

by the Technical Specifications.

were to provide the reactor

accident noble gas effluent monitoring capability required for

compliance with the requirements

in NUREG-0737

and Regulatory

Guide 1.97.

This complex, first of a kind, system design

was developed

and engineered

by the licensee

and completed in February

1993.

Three high purity germanium detectors

were installed in the reactor

building elevated

release

discharge

duct to identify and quantify

gaseous

radionuclide releases.

Installation of the reactor building

stack effluent monitoring system

was completed during the station's

refueling outage in the spring of 1993.

Preoperational

testing of the

system

was started

on June

20,

1993,

using Procedure

PPM 8.3.286,

"Reactor Building Stack Effluent Radiation Monitoring System

Preoperational

Test." issued

June

19.

1993.

In order to verify the

performance of the three high purity germanium detectors

(low,

intermediate,

and high range) with the collimators in place, it was

necessary

to maximize the amount of radioactivity seen

by the detectors

in the reactor building stack.

Therefore.

the station

had to be at

power to conduct the reactor building stack effluent monitoring system's

preoperational

testing

and initial primary calibration.

When the monitor readings for the detectors

stabilized

about midnight on

July 4,

1993. calibration of the low, intermediate,

and high range

channels

commenced.

Monitor readings for the detectors

were taken from

the logarithmic rate meter located

on the 525-foot level of the reactor

building and were recorded

on Attachment

6 of the reactor building stack

effluent monitor's preoperational

test procedure.

Grab samples of the

reactor building stack effluent were collected

and analyzed

by the

chemistry department.

This test evolution was completed

about

0500 on

July 5,

1993.

During the reading

and recording of the gross

count rate

value from the intermediate

range monitor, the wrong logarithmic rate

meter scale

was referenced.

This resulted in recording

an erroneous

value of 8,000 counts per second

(cps) instead of the correct value of

2.400 cps.

The data

recorded

was not verified as correct against other

alternate

sources of data.

The erroneous

data

was subsequently

used to

develop

a relationship

between the detector

response

and the gaseous

radioactivity in the stack

as determined

by the grab samples

analyzed

by

the chemistry department.

The intermediate detector efficiency factor

was calculated to be

1.457E+7 counts

per second

per microcurie per cubic centimeter

(cps/pCi/cc)

using the erroneous

data

recorded in the preoperational

test procedure.

This resulted in a non-conservative

gas calibration

efficiency factor and an incorrect.

non-conservative

alarm setpoint.

The correct detector efficiency factor was later determined to be 3.3E+6

cps/yCi/cc.

The erroneous

detector efficiency factor

was put into the reactor

building stack effluent monitoring system's

software to convert future

detector

readings to an equivalent radioactivity concentration.

This

erroneous

detector efficiency factor was also used in the emergency

dose

projection system software to calculate the source term and offsite

doses

during and following an accident.

The result of the erroneous

detector efficiency factor

was that the monitoring system's

software

would have calculated

a lower level of radioactivity released

from the

stack for a given detector

response.

This would have resulted in

offsite dose projections during an accident

being under-estimated

by

a

factor of approximately five.

NRC Inspection Report 50-397/96-03

had

previously identified the under-estimation

of dose

as

20 times lower

than the actual

dose values.

The under-estimating of the offsite doses

-10-

during an accident could have resulted in a failure to correctly

classify an emergency

event,

and also

a failure to correctly establish

appropriate protective action recommendations

to the offsite agencies

in

accordance

with the licensee's

emergency

plan implementing procedures.

The reactor building stack effluent monitor preoperational

test

procedure

was completed

on July 13,

1993.

The test results

were

approved

by the Plant Operations

Committee

on July 14,

1993,

and the

monitor was declared

operable.

The inspector

observed that this

appeared to be insufficient time to properly review the approximately

400 pages of data

and calculations.

When the preoperational

test procedure

was completed.

two of the

acceptance criteria were not completed.

One acceptance criteria was for

an additional modification to the monitoring system's

software,

which

was to be made later but in fact,

was never performed.

The other

acceptance

criteria requi red verification of the monitoring system's

performance

standards

against

ANSI N42. 18-1980 criteria.

This was not

performed in a timely manner.

After placing the reactor building effluent stack monitor in operation,

the preoperational

test procedure results

were not reviewed in detail

until the responsibility to review the preoperational

test data

was

assigned to the chemistry department

on December

20,

1995.

While

performing the ANSI N42. 18 review of the monitoring system's

preoperational

test results,

the discrepancy

in the intermediate

range

detector

response

and efficiency calculation

was discovered

by the

licensee.

Based

on the review of the original calibration data for the

intermediate

and high range radiation monitors. the licensee

determined

that both monitors were incorrectly calibrated in July 1993.

Subsequent

calibrations,

which were based

on the original calibration,

were also

determined to be invalid since July 1993.

It was determined that both

monitors detected

and correctly counted

gaseous

radioactivity levels in

the reactor building elevated

release

discharge

duct.

However, the

erroneous calibration efficiency factor resulted in a non-conservative

correlation

between the intermediate

and high range radiation

'monitors'ount

rate

and the specific gaseous

radionuclide concentration

in the

discharge

duct.

This would have resulted in under-estimating

the amount

of gaseous

radioactive effluent had there

been

an accident.

Consequently,

based

on the results of the licensee's

review, the reactor

building stack effluent monitoring system

was declared

inoperable

from

July 1993 to March 1996 (approximately

32 months)

due to the incorrect

calibration of the intermediate

and high range radiation monitors.

Technical Specification 3.3.7.5,

Table 3.3.7.5-1,

Item 31, requires

both

the intermediate

and high range radiation monitors of the reactor

building stack effluent monitoring system to be operable during Modes

1,

2

~

and 3.

The intermediate

and high range radiation monitors of the

reactor building stack effluent monitoring system were declared

inoperable at

1531 hours0.0177 days <br />0.425 hours <br />0.00253 weeks <br />5.825455e-4 months <br />

PST on March 6.

1996.

The plant was in Mode 4

-11-

at the time.

The plant was not returned to power

(Modes

1, 2, or 3)

until the vendor

recommended

conservative detector efficiency factor was

installed in the appropriate monitoring system

and emergency

dose

projection system software programs.

Subsequently,

the licensee

calculated

and installed the correct calibration efficiency factor in

the appropriate monitoring system

and emergency

dose projection system

software programs.

The licensee notified the

NRC via the event notification system at

1630 hours0.0189 days <br />0.453 hours <br />0.0027 weeks <br />6.20215e-4 months <br />

PST on March 6,

1996, of a loss-of-emergency

assessment

capability, in accordance

with 10

CFR 50.72(b)(v).

The licensee

took

the action required

by Action 81 in Table 3.3.7.5-1

and initiated the

preplanned alternate

method of monitoring the appropriate

parameters

as

described

in Plant Procedures

Manual

Procedure

13.8.2.

"Backup Emergency

Dose Projection System Operations,"

Revision 16, dated

October

30,

1995.

The licensee

also issued

a Special

Report to the

NRC. dated

March 20,

1996, pursuant to Technical Specification 6.9.2 within 14 days following

the event.

10 CFR 50.54(q) states.

"A licensee

authorized to possess

and operate

a

nuclear

power reactor shall follow and maintain in effect emergency

plans which meet the standards

in 10

CFR 50 '7(b)

.

.

. ."

10

CFR

50.47(b) states,

"The onsite

and

.

.

. offsite emergency

response

plans

for nuclear

power reactors

must meet the following standards:

.

.

. (9)

Adequate

methods,

systems,

and equipment for assessing

and monitoring

actual or potential offsite consequences

of a radiological

emergency

condition are in use."

Based

on the review of the initial calibration

and operability status of the reactor building stack effluent monitoring

system.

the intermediate

range monitor PRM-RE-1B and high range monitor

PRM-RE-1C were found to be incorrectly calibrated.

Therefore.

the

reactor building stack effluent accident monitors were inoperable

and

not capable of accurately

measuring concentrations

of noble gas fission

products in plant gaseous

effluents during and following an accident

from July 14, '1993,

through March 6.

1996, resulting in the failure to

implement planning standard

10

CFR 50.47(b)(9).

This is considered

an

apparent violation.

(397/9615-01)

c. Conclusions

An apparent violation involving the incorrect and non-conservative

calibration of the intermediate

range radiation monitor

(PRM-RE-1B) of

the reactor building stack effluent monitoring system,

which served

as

the required accident

noble gas monitor,

was identified (Section R2.3).

-12-

R3

Radiological Protection

and Chemistry Procedures

and Documentation

R3. 1

Radioactive

Waste Effluent Procedures

Offsite Dose Calculation Manual

and Annual

Re orts

a.

Ins ection

Sco

e

84750

Procedures

for the sampling,

analysis,

and release of radioactive liquid

and gaseous

waste effluents were reviewed.

Amendments to the Offsite

Dose Calculation

Manual were reviewed.

The annual

reports concerning

radioactive waste

systems

and effluent releases

were reviewed.

b.

Observations

and Findin s

Procedures

governing the release of liquid radioactive waste effluents

were reviewed.

These procedures

provided for the following:

Prior to release:

recirculation,

sampling,

and

r adionuclide analysis of the

radioactive liquid waste

~

calculations of effluent release

rate, effluent radiation monitor

setpoints,

projected offsite radionuclide concentrations,

and

offsite doses

During the release:

~

verification and recording of effluent discharge

flow rates,

effluent volume discharged,

effluent discharge

radiation monitor

readings.

and dilution parameters

Procedures

governing the continuous

and batch releases

of gaseous

radioactive waste effluents were reviewed.

These procedures

provided

for the sampling

and analysis of the radioactive

gaseous

and airborne

particulate waste effluents; verification of effluent discharge

flow

rates, effluent volume discharged'nd

dilution parameters

during the

release;

and calculation of effluent release

rate

and offsite

radionuclide concentrations

and doses.

The inspector

reviewed changes

(Amendments

17-23) to the Offsite Dose,

Calculation Manual, which were made

and approved

by the Plant Operations

Committee during 1994 and 1995.

The changes

were documented

in the

Radioactive Effluent Release

Reports

as required

by the Offsite Dose

Calculation Manual.

The Annual Radioactive Effluent Release

Reports for 1994 and

1995 were

reviewed.

The reports

were written in the format described in NRC

Regulatory Guide 1.21, Revision

1. June

1974,

and contained the

information required

by the Offsite Dose Calculation Manual.

-13-

R4

R4.1

C.

Summaries of the quantities of radioactive liquid and gaseous

effluents

released to the environment

and their associated

doses to members of the

public for 1994 and 1995 were properly presented

in the annual

reports.

Conclusions

Procedures

established to implement the liquid and gaseous

radioactive

waste effluent management

programs

provided proper guidance.

The

radioactive waste effluent management

programs

were properly

implemented.

Amendments to the Offsite Dose Calculation Manual were

properly documented.

The Annual Radioactive Effluent Release

Reports

for

1994 and

1995 were submitted in a timely manner

and contained the

required information presented

in the requi red format.

Staff Knowledge and Performance

Chemistr

Staff

Ins ection Sco

e

84750

The chemistry operations

supervisor,

effluents leader.

chemistry

technicians.

and equipment operators

were interviewed with regard to

regulatory

and Offsite Dose Calculation Manual requirements

for the

implementation of the radiological waste effluent management

programs.

Observations

and Findin s

The chemistry operations

supervisor,

effluents leader,

chemistry

technicians,

and equipment operators

were knowledgeable of the

programmatic procedures,

Offsite Dose Calculation

Manual requirements,

and regulatory requirements

and maintained

a high level of performance.

Batch radioactive liquid waste effluent releases

and continuous

radioactive

gaseous

waste effluent releases

were properly performed

during the inspection.

Conclusions

The chemistry'perations

supervisor,

effluents leader,

chemistry

technicians,

and equipment operators

had an excellent understanding

of

the radioactive waste

management

procedures,

Offsite Dose Calculation

Manual,

and regulatory requirements.

-14-

R5.1

R6

R6.1

b.

Staff Training and gualification

Chemistr /Radioactive

Waste Effluent Trainin

and

uglification

Ins ection Sco

e

84750

Training and qualification programs for chemistry technicians

and

equipment operators

involved with conducting the radioactive waste

effluent management

programs

were reviewed.

Training and qualifications

of the chemistry technicians

and equipment operators

were verified.

Observations

and Findin s

The chemistry technician qualification matrix and personnel training

records for all

15 chemistry technicians

and for 22 equipment operators

were reviewed.

It was verified that all of the chemistry technicians

had completed the training required to perform radioactive waste

effluent releases.

Similarly, the equipment operators

assigned to six

rotating shifts were trained

and qualified to conduct radioactive waste

effluent batch releases

and operate radioactive waste processing

equipment.

Conclusions

Training programs

were properly implemented.

The chemistry

and

operations

departments

had well trained

and qualified staffs for

conducting radioactive waste effluent processing

and release

operations.

Radiological Protection

and Chemistry Organization

and Administration

Chemi str

Or ani zati on and Sta ffin

,Ins ection Sco

e

84750

The organization

and staffing regarding the radioactive waste effluent

management

programs

were reviewed.

Observations

and Findin s

The inspector

verified that the chemistry organization

and staff, which

are responsible for the implementation of the radioactive waste effluent

management

programs,

was recently combined with the radiation protection

organization

and staff into one department

under the direction of a

newly appointed radiation protection/chemistry

manager.

The chemistry

organization

was assigned

the sole responsibility for implementing the

radioactive waste effluent management

programs effective October

1993.

The chemistry organization

was divided into four functional areas

each

R7

R7.1

a.

-15-

headed

by a supervisor

or the effluents leader,

who reported directly to

the chemistry operations

supervisor.

The functional area

headed

by the

effluents leader

was responsible for implementing the radioactive waste

effluent management

programs.

Administrative and departmental

procedures

were reviewed for the

assignment of responsibilities

for the management

and implementation of

the radioactive waste effluent management

programs.

The chemistry

organization

was assigned

the responsibility for preparing radioactive

waste effluent release

permits. evaluating the radioactive waste

effluent releases,

calculating the radiation

doses resulting from the

effluent releases

to the environment,

and maintaining the radioactive

waste effluent release

data.

The inspector

determined that the duties

and responsibilities of the chemistry organization specified in the

procedures

were being implemented.

A group of ten chemistry technicians staffing six rotational shifts

within the chemistry operations

functional

area

along with four nonshift

chemistry technicians

and the effluents leader assigned to the

radioactive waste effluents f'unctional

ar ea were responsible for

collecting and analyzing radioactive waste effluent samples,

preparing

the effluent release permits'nd

implementing the radioactive waste

effluent management

programs.

The inspector

reviewed the staffing of the chemistry organization

and

determined it to be adequate

and in accordance

with licensee

commitments.

There

had

been

a reduction in technical staff within the

chemistry organization since the previous

NRC inspection of this area in

January

1995.

This staff reduction did not appear to have

a negative

affect on the performance of the radiological waste effluent management

programs.

Conclusions

The chemistry organizational

structure

and staffing met Technical

Specification requirements.

The chemistry organization

had experienced

a reduction in technical staff during the past

17 months.

This

chemistry technical staff reduction did not appear to have

a negative

affect on the performance of the radiological waste effluent management

programs.

Quality Assurance in Radiological Protection

and Chemistry Activities

Radi oact ive Waste Effluent

ua1 it

Assur ance

Pro

ram

Ins ection Sco

e

84750

The quality assurance

audit and surveillance

programs

regarding the

radioactive waste effluent program activities were reviewed.

The

following quality assurance

audits were reviewed.

-16-

~

Quality Assurance Audit Report 293-618.

"Radiological

and

Non-Radiological

Environmental

and Effluent Monitoring." dated

November

19,

1993

~

Quality Assurance Audit Report 294-066,

"Radiological

and Non-

Radiological

Environmental

and Effluent Monitoring Programs,"

dated

November

18,

1994

~

Quality Assurance Audit Report 295-072,

"Radiological

and

Non-Radiological

Environmental Monitoring Programs."

dated

November

27,

1995

~

Quality Assurance Audit Report 295-061.

"WNP-2 Training and

Qualification," dated

September

19,

1995

The following quality assurance

survei llances

were reviewed.

~

Quality Assurance Surveillance

295-008,

"Radioactive Liquid Batch

Releases

to the Columbia River," dated June

7.

1995

~

Quality Assurance Surveillance

295-026.

"Chemistry Laboratory

Observations."

dated April 19,

1995

~

Quality Assurance Surveillance

296-005,

"Radwaste Deficiency

Identification Stickers,". dated January

14,

1996

~

Quality Assurance Surveillance

296-015,

"Annual Radioactive

Effluent Release

Report," dated

March 22,

1996

~

Quality Assurance Surveillance

296-023,

"Stack Monitoring System

Operation," dated

June

12,

1996

b.

Observations

and Findin s

The inspector

reviewed the quality assurance

audit schedules

for 1995

and 1996. the chemistry functional area planning guide from the

master critical attribute data

base.

and the qualifications of the

quality assurance

auditors,

who performed the audits

and survei llances

of the radiological

and nonradiological

environmental

and effluent

monitoring programs

and Offsite Dose Calculation Manual.

The review of

the quality assurance

audit schedules

indicated that the audits of the

radiological

and nonradiological

environmental

and effluent programs

were scheduled

on

a 12-month frequency in accordance with Technical Specifications 6.5.2.8.j

and 6.5.2.8.m.

The quality assurance

audit

of the Offsite Dose Calculation

Manual

and its implementing procedures

was scheduled

on

a 24 month frequency

(even

number years) in accordance

with Technical Specification 6.5.2.8.k.

The audits were scheduled

in

compliance with Technical Specification audit frequency requirements.

-17-

R8

R8.1

Reports of quality assurance

audits

and surveillances

performed during

the period January

1993 through June

1996 of the areas

related to

the performance. of the radioactive waste effluent management

programs

were performed in accordance

with the quality assurance

procedures

and

schedules

by qualified auditors.

The reviewed audits

and survei llances

of the radiological

and nonradiological

environmental

and effluent

monitoring programs

and the Offsite Dose Calculation

Manual

and its

implementing procedures

were of good quality and provided satisfactory

oversight

and evaluation of the licensee's

performance in implementing

the radioactive waste effluent management

programs

and meeting the

Technical Specification

and Offsite Dose Calculation

Manual

requirements.

To ensure that all aspects

of the station's

programs

were reviewed, the

quality assurance

organization maintained lists of "critical attributes"

associated

with each

program.

The inspector

reviewed the chemistry

functional area

planning guide from the master critical attribute data

base

and compared the list of critical attributes

associated

with the

chemistry,

radioactive waste effluents,

and radiological environmental

monitoring programs with areas of inspection included in NRC inspection

procedures

and concluded that the licensee's list of critical attributes

was comprehensive.

The inspector

noted that the list of critical

attributes

was comprehensive.

Conclusions

Oversight of the radioactive waste effluent management

programs

was

good.

In general,

quality assurance

audits

and survei llances of the

radioactive waste effluent management

programs

and Offsite Dose

Calculation Manual were technically comprehensive

and provided good

program evaluation

and oversight, identified deficiencies,

and

made

recommendations

for program improvement.

The corrective

action program

was properly implemented.

Miscellaneous

Radiological Protection

and Chemistry Issues

Closed

Ins ection Fol 1 owu

Item 397/9523-01:

Tr ainin

for

Envi ronmenta

1 Sci enti st

This item involved the lack of meteorological

monitoring technical

training for an environmental scientist recently assigned

the

responsibility for compiling, analyzing,

and reporting the station's

meteorological

data.

This environmental scientist

had not received

specific training on the station's meteorological

monitoring systems

and

was not knowledgeable of the recommendations

contained in the industry

standards

involving meteorological

monitoring activities.

A consultant

was hired to conduct

an independent

audit of the meteorological

monitoring program and present

a 2-day meteorological training seminar.

-18-

The inspector

reviewed the results of the audit and the training seminar

outline and content.

The inspector verified that the environmental

scientist

and other appropriate staff were trained in meteorological

principles

and the interpretation of meteorological

monitoring data.

R8.2

Closed

Unr esolved

Item 397/9603-07:

Reactor Buildin

Effluent Monitor

Calibration Error

This item involved the resident inspectors'eview of the licensee's

notification to the

NRC that the Reactor Building Effluent Monitor

PRM-RE-18 had been incorrectly calibrated since its installation in July

1993 and was, therefore.

inoperable since that time.

The licensee

determined that the gas calibration efficiency factor was incorrectly

calculated

because

a value from the wrong logarithmic scale

on the

monitor's count rate meter was used.

The inspector

reviewed the

licensee's

Plant Evaluation Request

296-0176.

which was issued to

evaluate the problem and determine corrective actions.

A 14-day Special

Report was submitted to the

NRC on March 20.

1996.

The inspector's

review of the problem resulted in the identification of an apparent

violation as discussed

in Section

R2.3 of this report.

V. Mana ement Meetin s

Exit Meeting Summary

The inspector presented

the results of the inspection to members of

licensee

management

at the conclusion of the inspection

on June

28.

1996.

The licensee

acknowledged

the findings presented.

A followup

telephone exit meeting

was also conducted

on July 29,

1996 'to inform

the licensee of the enforcement

panel's disposition of the inspection

results.

The inspector

asked the licensee

whether

any materials

examined during

the inspection

should

be considered proprietary.

No proprietary

information was identified.

Licensee

ATTACHMENT

PARTIAL LIST OF

PERSONS

CONTACTED

R. Abdella.

Lead Training Specialist.

Chemistry

A. Alexander.

Effluents Leader

~ Chemistry

W. Barley,

Manager.

Quality

C. Foley. Licensing Engineer

H. Hedges'cting

Chemistry Manager

R. James.

Acting Supervisor.

ALARA

T. Love. Manager.

Radiation Protection/Chemistry

C.

McDonald

~

Supervisors'ealth

Physics/Chemistry

Training

J. Huth. Manager. Quality Services

J. Parrish.

Chief Executive Officer

L. Rathbun.

Supervisors'adiation

Protection Support

G. Smith. Plant General

Manager

'.

Swanky

Manager.

Regulatory Affairs

R. Webring. Vice President.

Operations

Support

V. Harris.

Hanager.

Maintenance

L. Fernandez.

Manager,

Licensing

R. Winslow. Acting Radiation Protection

Manager

NRC

~

~

G. Replogle.

Resident

Inspector

H.

Wong, Chief. Reactor

Programs

Branch

E. Division of Reactor Projects

INSPECTION

PROCEDURES

USED

IP 84750

Radioactive

Waste Systems:

Water Chemistry: Confirmatory

Measurements

and Radiological

Environmental

Monitoring

ITEMS OPENED

CLOSED

AND DISCUSSED

O~ened

50-397/9610-01

VIO

Reactor Building Stack Effluent Monitor Calibration

Error

Closed

50-397/9523-01

IFI

Training for Environmental Scientist

50-397/9603-07

URI

Effluent Honitor Calibration Error

Discussed