II May 9, 1996 Mr. J.
V." Parrish (Mail Drop 1023)
Chief Executive Officer 3000 Ge'orge Washington Way
,Washington Public Power Supply System
'.O.Box 968
- Richland, Washington 99352-0968
SUBJECT:
RELIEF, REQUEST 2ISI-17 REGARDING CATEGORY B-F NOZZLE-TO-SAFE-END WELDS FOR THE, WASHINGTON PUBLIC POWER SUPPLY SYSTEM (WPPSS)
NUCLEAR PROJECT NO'.
2 (WNP-2)
Dear Mr. Parrish:
By letter dated December 13, 1995, you requested approval of a relief request from the requirements of the American Society of American Engineers (ASME)
- Code,Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components."
The relief requested was for the requirement to perform a
volumetric examination of Examination Category B-F welds, specifically the reactor vessel nozzle-to-safe-end welds.
We have completed our review of your request and determined that, pursuant to 10 CFR 50.55a(g)(6)(i),
completion of the volumetric examination of the nozzle-to-safe-end welds is impractical for WNP-2 and granting of relief is authorized by law, will not endanger life, property or the common defense and
- security, and is otherwise in the public interest.
This relief has been granted giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility.
This completes our work on TAC No. M94332.
Please contact Mr. J.
W. Clifford at 301-415-1352 if you have any questions.
Sincerely, Original siqned by:
William H. Bateman, Director Project Directorate IV-2 Division of Reactor Projects III/IV Office of Nuclear Reactor Regulation Docket No.. 50-397 DISTRIBUTION:
1 Docket File
Enclosure:
Sa'fety Evaluation PUBLIC PDIV-2 Reading JRoe OGC, 015818 cc w/ encl:, See next page '
EAdensam
- KPerkins, WCFO WBateman
- JDyer, RIV JClifford
- HWong, WCFO EPeyton JMitchell GBagchi GHill (2)
- DOCUMENT 'NAME:.'WNP94332.1tr~'+For,,
revious concurrence see attached ORC OFC -'-"
PD IV-2
'AME ey on DATE 5/g 96 f
i I
>PDIV-2
'JCli, ord 5,.5 96,
'OGC*
MYoun 4 29 96 PDIV-2 WBatema 8'6
~ ~ ~ ~ g OFFICIAL RECORD 'OPY 9605170i60 96050'P PDR ADQCK 05000397 P
PDR liJIIC PlK KREIS KPV
r k'
t(
I l.
t t
r 5 'I r
H gl I
'i O
'/
I 1
ll
May 9, 1996 Hr. J. V. Parrish (Hail Drop 1023)
Chief Executive Officer 3000 George Washington Way Washington Public Power Supply System P.O.
Box 96&
Richland, Washington 99352-0968
SUBJECT:
RELIEF REQUEST 2ISI-17 REGARDING CATEGORY 8-F NOZZLE-TO-SAFE-END WELDS FOR THE WASHINGTON PUBLIC POWER SUPPLY SYSTEM (WPPSS)
NUCLEAR PROJECT NO.
2 (WNP-2)
(TAC NO. H94332)
Dear Hr. Parrish:
" By letter dated December 13, 1995, you requested approval of a relief request from the requirements of the AmerIcan Society of American Engineers (ASHE)
Code,Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components."
The relief requested was for the requirement to perform a volumetric examination of Examination Category B-F welds, specifically the reactor vessel nozzle-to-safe-end welds.
We have completed our review of your request and determined that, pursuant to 10 CFR 50.55a(g)(6)(i),
completion of the volumetric examination of the nozzle-to-safe-end welds is impractical for WNP-2 and granting of relief is authorized by law, will not endanger life, property or the common defense and
- security, and is otherwise in the public interest.
This relief has been granted giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility.
This completes our work on TAC No. M94332.
Please contact Mr. J.
W. Clifford at 301-425-1352 if you have any questions.
Sincerely, Original signed by:
William H. Bateman, Director Project Directorate IV-2 Division of Reactor Projects III/IV Office of Nuclear Reactor Regulation Docket No. 50-397
Enclosure:
Safety Evaluation cc w/ enci:
See next page DOCUMENT NAME:.WNP94332.1tr
~UTRI UT IIN:
Docket File
- OGC, 01581&
EAdensam
- KPerkins, WCFO WBateman
- JDyer, RIV JClifford
- HWong, WCFO EPeyton JHitchell GBagchi GHill (2)
- For revious concurrence see attached ORC OFC PDIV-2 PDIV-2 OGC*
PDIV-2 NAME e
on JCli ord HYoun WBatema DATE 5 8 96 5 596 4 29 96 96 OFFICIAL RECORD COPY
em~ RE00+
~o Cy Cl C
O I
~,
IA0
+r
+~
~O
++*+~
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 2055&4001 May 9, 1996 Hr. J.
V. Parrish (Hail Drop 1023)
Chief Executive Officer 3000 George Washington Way Washington Public Power Supply System P.O.
Box 968
- Richland, Washington 99352-0968
SUBJECT:
RELIEF RE(UEST 2ISI-17 REGARDING CATEGORY B-F NOZZLE-TO-SAFE-END'ELDS FOR THE WASHINGTON PUBLIC POWER SUPPLY SYSTEH (WPPSS)
NUCLEAR PROJECT NO.
2 (WNP-2)
(TAC NO. H94332)
Dear Hr. Parrish:
By letter dated December 13, 1995, you requested approval of a relief request from the requirements of the American Society of American Engineers (ASHE)
- Code,Section XI, "Rules for Inservice Inspection of Nuclear Power Plant Components."
The relief requested was for the requirement to perform a volumetric examination of Examination Category B-F welds, specifically the reactor vessel nozzle-to-safe-end welds.
We have completed our review of your.request and determined that, pursuant to 10 CFR 50.55a(g)(6)(i),
completion of the volumetric examination of the nozzle-to-safe-end welds is impractical for WNP-2 and granting of relief is authorized by law, will not endanger life, property or the common defense and
- security, and is otherwise in the public interest.
This relief has been granted giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility.
This completes our work on TAC No. H94332.
Please contact Hr. J.
W. Clifford at 301-415-1352 if you have any questions.
Sincerely, Qx William H. Bateman, Director Project Directorate IV-2 Division of Reactor Projects III/IV Office of Nuclear Reactor Regulation Docket No. 50-397
Enclosure:
Safety Evaluation cc w/encl:
See next page
Hr. J..V. Parrish CC:
Hr. G. 0. Smith WNP-2 Plant General Hanager Washington Public Power Supply System.
P. 0.
Box 968
- Richland, Washington 99352-0968 Chief Counsel (Mail Drop 396)
Washington Public Power Supply System P.O.
Box 968
- Richland, Washington 99352-0968 Mr. Frederick S. Adair, Chairman Energy Facility Site Evaluation Council P. 0.
Box 43172 Olympia, Washington 98504-3172 Hr. D. A. Swank (Mail Drop PE20)
Regulatory and Industry Affairs Washington Public Power Supply System P.O.
Box 968
- Richland, Washington 99352-0968 Mr. Paul R. Bemis (Mail Drop PE20)
Vice President, Nuclear Operations Washington Public Power Supply System P.O.
Box 968
- Richland, Washington
.99352 Regional Administrator, Region IV U.S. Nuclear Regulatory Commission Harris Tower 5 Pavilion 611 Ryan Plaza Drive, Suite 400 Arlington, Texas 76011-8064 Chairman Benton County Board of Commissioners P.O.
Box 69
- Prosser, Washington 99350-0190 Mr. R.
C. Barr, Senior Resident Inspector U.S. Nuclear Regulatory Commission P.O.
Box 69
- Richland, Washington 99352-0968 H. H. Philips, Jr.,
Esq.
Winston
& Strawn 1400 L Street, N.W.
Washington, DC 20005-3502