March 24, 1994 ~
I Docket No. 50-397 LICENSEE:
'Washington Public Supply System FACILITY:
WPPSS Nuclear Project No.
2 (WNP-2)
SUBJECT:
MEETING
SUMMARY
FOR MARCH'21, 1994 MEETING WITH WASHINGTION PUBLIC SUPPLY SYSTEM (SUPPLY SYSTEM)
We conducted a meeting with the Supply System on March 21, 1994, to discuss licensing issues
'i egarding the WNP-2 plant.
The meeting agenda and a list of attendees are enclosed.
The staff provided presentations on the topics listed.
In addition, the staff provided insights into how it processes amendment and other licensing requests.
There was extensive discussion between the staff and the licensee on the various topics.
The staff and the licensee also discussed numerous examples to clarify staff policy and requirements regarding licensing actions.
No outstanding
- actions, commitments, or questions remain from the meeting.
Original signed by:
James W. Clifford, Senior Project Manager Project Directorate V
Division of Reactor Projects III/IV/V Office of Nuclear Reactor Regulation
Enclosures:
As stated cc w/enclosures:
See next page
,DISTRIBUTION:
!Docket File (T L NRC 5 Local PDRs PDV Reading File WRussell/FHiraglia LReyes JRoe EAdensam TQuay JClifford DFoster-Curseen OGC 940330024b 940324 ACRS (10)
PDR ADOCK 05000397
- EJordan, 3701k PDR NRC Participants
- ARubin, EDO, 17G21
- KPerkins, RV OFFICE PDV/LA PDV/
H PDV D
DFoster-Curseen NAME DATE 03/
/94 OFFICIAL RECORD COPY JClifford 03@3 94 TQua 03 '8 94 DOCUMENT NAME:
WNPVMTGSUM.321
f r
1
'0 1
I I
1.'
Ji 1'i I
4'a, f
lg I
l l
Wo
~P,A RE00 P0 I
00 p g 0
~O
>>>>*<<+
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 2055&0001 March 24, 1994 Docket No. 50-397 LICENSEE:
Washington Public Supply System FACILITY:
WPPSS Nuclear Project No.
2 (WNP-2)
SUBJECT:
MEETING
SUMMARY
FOR MARCH 21, 1994 MEETING WITH WASHINGTION PUBLIC SUPPLY SYSTEM (SUPPLY SYSTEM)
We conducted a meeting with the Supply System on March 21, 1994, to discuss licensing issues regarding the WNP-2 plant.
The meeting agenda and a list of
'ttendees are enclosed.
The staff provided presentations on the topics listed.
In addition, the staff provided insights into how it processes amendment and other licensing requests.
There was extensive discussion between the staff and the licensee
.on the various topics.
The staff and the licensee also discussed numerous examples to clarify staff policy and requirements regarding licensing'actions.
No outstanding
- actions, commitments, or questions remain from the meeting.
J mes W. Cl'ord, 'Senior Project Manager Project Directorate V
Division of Reactor Projects III/IV/V Office of Nuclear Reactor Regulation
Enclosures:
As stated cc w/enclosures:
See next page
Washington Public Power Supply System WPPSS Nuclear Project No.
2 (WNP-2) cc w/enclosures:
Hr. J.
H. Swailes-WNP-2 Plant Manager Washington Public Power Supply System P. 0.
Box 968
- Richland, Washington 99352-0968 G.
E.
C.
- Doupe, Esq.
(Hail Drop 396)
Washington Public Power Supply System 3000 George Washington Way P. 0.
Box 968
- Richland, Washington 99352-0968 Hr. Warren Bishop, Chairman Energy Facility Site Evaluation Council P. 0.
Box 43172 Olympia, Washington 98504-3172 Hr.
H. K. Kook (Mail Drop PE20)
WNP-2 Licensing Manager Washington Public Power Supply System P. 0.
Box 968
- Richland, Washington 99352-0968 Hr. Paul R.
Bemis (Hail Drop PE20)
Regulatory Programs Manager Washington Public Power Supply System P. 0.
Box 968
- Richland, Washington 99352-0968 Regional Administrator, Region V
U.S.
Nuclear Regulatory Commission 1450 Maria Lane, Suite 210 Walnut Creek, California 94596 Chairman Benton County Board of Commissioners P. 0.
Box 190
- Prosser, Washington 99350-0190 Hr.
R.
C. Barr U. S. Nuclear Regulatory Commission P. 0.
Box 69
- Richland, Washington 99352-0968 H.
H. Philips, Jr.,
Esq.
Winston 5 Strawn 1400 L Street, N.W.
Washington, D.C.
20005-3502 Hr. J.
V. Parrish (Mail Drop 1023).
Assistant Managing Director, OPS P. 0.
Box 968
- Richland, Washington 99352-0958
ENCLOSURE LIST OF ATTENDEES WASHINGTON NUCLEAR PROJECT, UNITS 2 LICENSING ISSUES MEETING March 21, 1994 Jim Clifford Sheri Peterson Ted quay Janice Moore Dave Wigginton Jim Luehman Eric Leeds Craig Harbuck Steve Kirkendell Phil Harness Rod Webring John D. Fisher Loren Sharp Herbert E. Kook, Jr.
Paul R.
Bemis Douglas W. Coleman Lourdes Fernandez Marsha Eades David Swank Bruce R.
Hugo Pat Powell Ron Barbee Paul Inserra ORGANIZATION NRC/NRR/DRPW/PDV NRC/NRR/DRPW/PDV NRC/NRR/DRPW/PDV NRC/OGC/DAGC/AR-SP NRC/NRR/DRPW/PDI V-1 NRC/NRR/DORS/OTSB NRC/NRR NRC/NRR/DORS/OTSB WPPSS WPPSS WPPSS WPPSS WPPSS WPPSS WPPSS WPPSS WPPSS WPPSS WPPSS WPPSS WPPSS WPPSS WPPSS
W4-2 LICENSING PROOSS IVlEETING AGENDA MARCH 21, 1994 8:00-9:00 Introduction
~ Jim Clifford Sr. Project Manager 9:00-10:00 Legal Requirements Janice Moore Deputy Assistant General Counsel for Advanced Reactor and Special Proceedir 10:00-10:30 Degraded Conditions and Operability David Wigginton Sr. Project Manager Jim Luehman Sr. Reactor Engineer TS Branch 10:30-12:00 Implementation of Improved Standard TS/Commission Policy on TS Jim Luehman Sr. Reactor Engineer TS Branch 12:00-1:00 Lunch 1:00-2:00 Cost Beneficial Ucensing Actions (CBLA)
Eric Leeds Technical Assistant 2:00-3:00 10 CFR 50.59 Craig Harbuck Sr. Reactor Engineer TS Branch 3:00-5:00 Licensing Issues Jim Clifford Sr. Project Manager