Text
FORD I REGULAT INFORMATION DISTRIBUTIO?
zZSTEM (RIDS)
J ACCESSION NBR:9311190050 DOC.DATE: 93/11/05 NOTARIZED: NO FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe AUTH.NAME AUTHOR AFFILIATION LUEHMANFJ.
Ofc of Enforcement (Post 870413)
LIEBERMAN,J.
Ofc of Enforcement (Post,870413)
RECIP.NAME RECIPIENT AFFILIATION DOCKET,, ¹ 05000397
SUBJECT:
EN-93-110:on 931110 proposed imposition of civil penalty in amount of
$ 75,000 issued to licensee. Action based on failure to follow procedural requirements re RHR sys.State of Washington notified.
DISTRIBUTION CODE:
IE33D COPIES RECEIVED:LTR ENCL SIZE:
TITLE: Enforcement Notice (EN)
NOTES:
RECIPIENT ID CODE/NAME INTERNAL: AEOD/DOA AEOD/DSP/TPAB NRR/DRSS/PEPB NUDOCS FULL TXT OE FILE 01 EXTERNAL: NRC PDR COPIES LTTR ENCL RECIPIENT ID CODE/NAME AEOD/DSP/ROAB NRR/DORS/OEAB NRR/PMAS/ILPB OE DIR cga 02 NSIC COPIES LTTR ENCL NOTE TO ALL RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK.
ROOM PI-37 (EXT. 504-2065) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!
TOTAL NUMBER OF COPTER REQUIRED:
LTTR l2 ENCL Pf
Novebmer 5, 1993 93-110 OFFICE OF ENFORCEMENT NOTIFICATION OF SIGNIFICANT ENFORCEMENT ACTION Licensee:
Washington Public Power Supply System (EA 93-191)
(WNP-2)
Docket No.
50-397
~Sub'ect:
PROPOSED IMPOSITION OF CIVIL PENALTY $75,000 This is to inform the Commission that a Notice of Violation and Proposed Imposition of Civil Penalty in the amount of
$75,000 will be issued on or about November 10, 1993 to the Washington Public Power Supply System.
This action is based on the failure to follow procedural requirements with regard to simultaneously placing both trains of the residual heat removal system in the suppression pool cooling mode while the plant was in operation.
The three separate occasions that this occurred have collectively been classified as a Severity Level III violation.
The base civil penalty was escalated by 50 percent after partially offsetting escalation for prior poor performance and corrective actions with mitigation for licensee identification.
It should be noted that the licensee has not been specifically informed of the enforcement action.
The schedule of issuance and notification is:
Mailing of Notice November 10, 1993 Telephone Notification of Licensee November 10, 1993 The State of Washington will be notified.
The licensee has thirty days from the date of the Notice in which to respond.
Following NRC evaluation of the response, the civil penalty may be remitted, mitigated, or imposed by Order.
Contact:
J.
- Luehman, OE, 504-3280 J.
Lieberman, OE, 504-2741 Distribution:
OWFN ~O.
Chairman Selin Comm.
Rogers Comm.
Remick Comm.
de Planque SECY OCA OSP GPA OWFN ~0.
EDO DEDR DEDS OE NMSS NRR OI OGC MNBB 10'.CQ OC AEOD Op Ctr Regional Offices RI LQDD RIV (0 60 RII g:W RV ~Q'.c7Q RIII ~Q:BC)
MAIL ADM: Doc. Mgt. Br.
PDR ACRS RES OIG PHIL (O.OD NL ~O:O~
IRM PRELIMINARY INFORMATION NOT FOR PUBLIC DISCLOSURE UNTIL PUBLICLY ANNOUNCED 9311190050 931105."
PDR ISrE EN-93-110 PDR-