ML17289A978

From kanterella
Jump to navigation Jump to search
Insp Rept 50-397/92-27 on 920921-25.No Violations Noted. Major Areas Inspected:Whether Facilities Licensed Operator Initial,Licensed Operator Requalification
ML17289A978
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 10/20/1992
From: Morrill P
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To:
Shared Package
ML17289A977 List:
References
50-397-92-27, NUDOCS 9211120277
Download: ML17289A978 (15)


See also: IR 05000397/1992027

Text

U. S.

NUCLEAR REGULATORY COMMISSION

REGION V

Report Number:

50-397/92-27

Docket Number:

50-397

Licensee

Number:

NPF-21

Licensee:

Mashington Public Power

Supply System

P. 0.

Box 968

3000 George Mashington

May

Richland,

Mashington

99352

Facility Name:

Mashington Public Power Supply System Nuclear

Reactor

Facility, Unit 2 (MNP-2)

Inspection at:

MNP-2 site near Richland,

Mashington

Inspection

Conducted:

September

21-25,

1992

Inspectors:

T. Meadows,

Senior Licensing Examiner,

RV (Lead Inspector)

C. Gratton, Senior Licensing Examiner,

NRR/LOLB

H. Biamonte, Senior Training Specialist,

NRR/LHFB

Approved,by:

~Summar:

P. J

Morrill, Chief'

eactor Operations

Section

Date Signed

Ins ection

on

Se tember 21-25

1992

Ins ection

Re ort No. 50-397 92-27

Areas Ins ected:

This inspection

examined the facility's,licensed operator requali fication

simulator training and evaluator performance.

The inspectors

focused

on the

ability of the facility evaluators

to objectively evaluate

and critique

operator performance.

The inspection also evaluated

whether the facility's

licensed operator initial, licensed operator requalification,

and shift

technical

advisor

(STA) training programs

were in compliance with regulatory

requirements.

Inspection procedure

41500 was used

as guidance for the

inspection.

92iii20277 921020

PDR

ADOCK 05000397

8

PDR

0

1

I

Results:

General

Conclusions

and

S ecific Findin s:

The inspection

team found that, with one exception,

the operators

observed

performed well in the simulator and the facility evaluators

were able to

objectively evaluate

and critique operator performance.

The evaluation

and

feedback process of the licensee's

requalification training program was

adequate.

The one exception

was

a crew failure during a practice scenario.

This failure was correctly identified by the evaluators.

Subsequent

remediation plans

appeared

satisfactory.

The licensed operator initial, licensed operator requalification,

and shift

technical

advisor

(STA) training programs

were also in compliance with

regulatory requirements.

The inspectors identified three areas of potential training program weakness:

(I)

The operations liaison staff person

was not certified as

a training

evaluator,

even though

he conducted evaluations.

This did not appear

consistent with the standards

imposed

on the other training staff

evaluators.

(2)

There

was

no process

to ensure that the training and evaluation

skills developed for the operator requalification program instructors

were transferred to the initial operator

program instructors.

(3)

The licensee

was not adequately

conducting follow-up assessments

of

the effectiveness

of industry events

lessons

learned training conducted

for their operators.

Summar

of Violations and Oeviations:

None

0 en Items

Summar

No items opened or closed

Personnel:

INSPECTION DETAILS

NRC:

  • T. Meadows,

Senior Licensing Examiner,

RV (team leader)

  • C. Gratton, Senior Licensing Examiner,

NRR/LOLB

M; Biamonte,

Senior Training Specialist,

NRR/LHFB

  • W. Ang, Senior

Resident

Inspector

  • D.'roulx, Resident

Inspector

Supply System:

  • J. V. Parrish; Assistant

Managing Director for Operations

  • J. Baker, Plant Manager
  • S. McKay, Nuclear License Training Manager
  • W. Shaeffer,

Operations

Manager

  • M. Mann, Assistant Operations

Manager

  • D. Kobus, Manager,

Technical Training

  • P. Taylor, Operations

Department Liaison

M. Baird, Requalification Training Supervisor

  • J. Gearhart,

Director, guality Assurance

  • G. Sorensen,

Regulatory

Programs

Manager

  • T. Powell, Equipment/Licensed

Training Supervisor

Present at the September

25,

1992 exit meeting.

The inspectors

also interviewed other licensee

and contract 'personnel

during the inspection.

Overview of the Ins ection

This inspection

was conducted to evaluate

the adequacy of the

requalification program as it related to accurate

and objective

evaluation of the plant operators.

The inspection

team also examined

other attributes of the licensee's

training programs to determine if

regulatory requirements

were being met.

In regards

to the requalification program the inspectors

focused

on

scenario quality, the implementation of management

expectations,

operator

performance,

the remediation process, facility evaluator

objectivity, and the evaluation

and critique process.

The remainder of the inspection, examined operator

and training staff

perceptions

of the program, training. department organization

and

relations with operations, shift technical

advisor

(STA) training,

training department staffing, operator overtime,

and industry events

training.

Review of 0 erator

Re uglification Trainin

Pro ram

a ~

b.

I'K

Using the guidance of SECY 92-154,

"Guidance for Developing

Dynamic Simulator Scenarios

Used During NRC-Administered

Requalification Examinations,"

the inspectors

analyzed the quality

of eight scenarios

used in training and evaluation of shift crews.

The licensee's

training department

had recently completed

a

revision of the simulator scenario

bank by removing unrealistic

scenarios

and rewriting other scenarios

to ensure that all paths

of the

EOPs were exercised

during each

crew requalification

evaluation.

The team found that the scenarios

were adequately

complex, challenging,

and exercised

the

EOPs without being

unrealistic.

The inspectors

concluded that the scenarios

met the

guidance of SECY 92-154.

Mana ement

Ex ectations

C ~

Senior licensee

management

has developed

and provided training

with technical clari-fication of operating procedures

for steps

that require interpretation.

The licensee referred to these

clarifications as management

expectations.

They were developed to

promote operational

consistency primarily for the emergency

operating procedures

(EOP).

The team found that management

expectations

were appropriately placed in the training materials.

Observations of training and evaluations

scenarios

demonstrated

that this was effective in promoting consistent

actions

by crews.

The licensee's

actions

appeared

to have corrected inconsistent

training and operations

which were observed

in the past.

An example of a clarifying management

expectation

was within one

training scenari o involving an interpretati on of the

EOPs.

Thi s

clarification was

boxed in bold lines and stated:

"When

suppression

pool

(SP) level cannot

be maintained

above the heat

capacity level limit (HCLL): Direct termination of injection

sources."

A side note further clarified: "It is expected that

when the source of makeup to the

SP is lost, emergency

depressurization

(ED) will be directed

when the

HCLL is approached

-NOT- when it is reached."

When to take action in this situation

had been

a source of. confusion in the past for both trainers

and

operators.

The inspectors

concluded that the licensee's

management

expectations

appeared

to be an effective device to

clarify procedure

steps

to both trainers

and operators.

0 erator Performance

Operator

performance

was examined

by observing

one staff crew and

one control

room crew in the simulator.

A total of eight

simulator scenarios

were observed for each

crew.

The shift crew was evaluated

in their

normal shi ft configuration.

With one exception,

the inspectors

concluded that the performance

of both crews

was satisfactory.

In general,

the inspectors

observed

good crew communications skills and procedure

usage

during both training and evaluation scenarios.

The shift crew failed one practice scenario

for two reasons.

First, the crew lost control of reactor

system pressure

and

cooldown rate.

The facility evaluators

determined that the crew

had not adequately

monitored cooldown rate and failed the crew in

the competency for'pressure

control.

Second,

the evaluators

observed that the crew did not secure all emergency

core cooling

before 'emergency depressurization.

This could have resulted in an

overcooling of the reactor vessel

when low pressure

injection

'ccurred.

The licensee

evaluators

concluded that the crew had

a

significant weakness

and- required remediation.

The inspectors

concluded that the failure was

a conservative

decision,

and that the evaluators

were effective in identifying

performance

problems.

The inspectors

observed that the shift crew

had satisfactorily passed their previous evaluation

scen'arios.

Remediation

Process

After the scenario described

above,

the facility evaluators

completed the critique process

(described in paragraph

3.e').

The

failed crew appeared

to recognize their errors

and was eager to

learn from their mistakes.

The 'crew and the shift manager

(who

observed

the scenario)

met with the operations liaison and

training staff to conduct

a formal

exam failure analysis

as

required

by Licensed Training Procedure

(LTI) 5.8, "Licensed

Operator

Requal

(LORg) Evaluation Failures."

The lead crew

evaluator established

a timeline for actions during the scenario

as well as the thought processes

involved for the steps

taken.

After the scenario details

and crew deficiencies

had been

identified, the crew's senior reactor operators,

the operations

liaison, the requalification training supervisor,

key evaluator

staff,

and the operations

manager

convened to formalize the causes

of the failure and to determine the required corrective actions.

This included remediation training for the failed crew as well as

correction to parts of the general

operator training program.

The inspectors

observed that the licensee

had accurately

determined

the sequence

of events

and identified the crew'

weaknesses.

The remediation

and corrections to the training

program were reviewed.

Licensee

personnel

appeared

to have

a good

understanding of their procedures

and followed them properly.

The

operations

department

was very involved in the process.

The team

.,

concluded that the remediation

process for the crew was

satisfactory.

Evaluator Ob'ectivit

The team observed five evaluators. conducting evaluation scenarios

on the staff and operating crew.

The team concluded

from these

observations

that the evaluators

were knowledgeable

and objective

and applied the performance

standards

from NUREG-1021, "Operator,

Licensing Examiner Standards,"

in a consistent

manner.

The

following are

some examples of the evaluator perceptiveness

and

objectivity during the simulator observations:

(1)

In one scenario

a reactor operator

(RO) misaligned the feed

and condensate

system during a recovery from a compounded

LOCA event.

The error was subtle, involving one manual

.

valve with no direct indication.

The facility evaluator

immediately perceived

the error and subsequently

the

operator

was appropriately

downgraded in his control board

competency.

Since this item was not a individual simulator,

critical task

(ISCT) and would not have led to an unsafe

condition, the oper'ator did not fail the evaluation.

(2)

During a scenario involving an anticipated transient without

scram

(ATWS), one

RO was required to implement

a scram-

reset-scram

procedure to attempt to scram the control

rods.'oncurrently

with this evolution,-the

emergency operating

procedures

(EOPs) required that the

RO insert individual

rods using the normal control rod drive

(CRD) system.

When

the reactor level reached -50'n automatic rod insertion

(ARI) signal occurred which decreased

control rod drive

.water pressure.

The

RO appeared

to be unaware of the ARI

and

seemed to be confused

as to why he could no longer

manually insert. the control rods.

~"

The RO's evaluator followed up by asking several

probing

questions

about the system status

and the inability to drive

the rods.

During the evaluation process,

the instructor

appropriately

downgraded the

RO for his weakness

in system

knowledge

and event diagnosis.

The weakness

was'iscussed

in the post evaluation

caucus with the crew.

Because'his

was. not an

ISCT and would not have

made the accident worse,

the

RO did not fail the evaluation.

The inspectors

concluded that the five observed facility

evaluators

were sufficiently objective and probing to accurately

evaluate

the crews being tested.

f.

Evaluation Criti ue Process

The licensee. has developed

a new evaluation

process that was

developed

based

on feedback

from the operations staff, the

training staff, peer evaluators,

and the plant operators.

The

grading process for evaluation of scenario

performance

occurs in

four steps.

(I) An initial post-scenario

caucus of the evaluators

reviews the performance of the crew executing individual

simulator critical tasks

and formulates follow-up questions

for those operators that displayed performance

weaknesses

during the scenario.

(2) Follow-up questions

are administered individually by .the

evaluators

to determine

the basis of the operators'ctions

and to probe their knowledge.

(3) The evaluators

and the crew separately

grade the

individual crew members

and the crew using competency

check-

sheets similar to those

used in the Operator Licensing

Examiner Standards,

NUREG-1021,

ES-604 "Requalification

Dynamic Simulator Examination."

(4)

A joint caucus of the evaluators

and the crew members is

held to compare

and contrast the findings of each group.

The inspectors

observed

the grading of two weekly evaluation

scenarios

and found the evaluations

to be accurate.

The

inspectors

also observed that the results of the evaluators

and.

the crews evaluated

wer e consistent.

(see

paragraph

3.c,

above)

9.

~Summa@

The inspection

team found that the operators

observed during the

training week performed well in the simulator and that the

facility evaluators

were able to objectively evaluate

and critique

operator performance.

The evaluation

and feedback

process of the

licensee's

training program appeared

to be satisfactory.

Trainin

Ins ecti on

41500

0 erator

and Instructor Interviews

Interviews with eight operators

revealed that they have

a high

level of satisfaction with the training they are currently

receiving.

The operators

stated that the level of the training

effort was appropriate

given the goals they have established

to

prepare for the upcoming requalification examinations.

They

stated that the complexity of the simulator scenarios

remained

high, but the crews felt that the scenarios

were more realistic

than those

used in the past.

6

The six licensee instructors interviewed noted that improvements

in scenario

timing allowed for more realistic malfunction response

times resulting in more realistic scenarios.

Each operator

inter viewed stated that the methods currently used for evaluating

simulator performance

were more effective then what had been

done

in the past.

The greatest

improvement

was attributed to the crew

self-evaluation

sessions.

The operators specifically mentioned

that identifying and discussing

performance

weaknesses

within the

crew-first, improved the sessions

with the evaluators

(when the

formal evaluation is given).

This method has reduced

the-need for

the evaluators

to list and discuss

in detail all the performance

errors

and allows the evaluation sessions

to focus

on areas

where

differences in perceived

performance exist.

This approach

has

also increased

the effectiveness

of the evaluation

sessions

by

keeping

them more focused

and making them less confrontational.

Trainin

De artment

Or anization

and Relationshi

with 0 erations

In addition to the refinement of the evaluation

and critique

process

discussed

in paragraph 3.f, several

additional actions

have

been

taken to improve the relationship

between training and

operations.

The plant o'perations

manager

has

been

moved to the training

department

as the supervisor of operations training.

An

operations liaison position has been established

in training and

was currently filled by a former. control

room supervisor

(CRS).

The operations liaison worked with the instructors to evaluate

operator

performance in the simulator.

He also provided an

operations

management

perspective

in assuring consistent

incorporation of management

expectations.

Solutions to identified program deficiencies

were "fed back" into

the system through training curriculum modifications, procedural

changes,

or both; depending

on the appropriate resolution

determined

by the operations

manager.

All interviewed operators

indicated that they thought'his

process

worked,

and felt that

their role was important.

The organizational

changes

appeared

to have significantly

increased

the credibility of the training staff with the

operators.

At the end of the training week, the operators

were

.

given the opportunity to evaluate

the performance of the

instructors.

The inspectors

observed that this process of

operator

feedback

was improving the communications

between

the

operations staff members

and the training staff.

The inspectors

reviewed the training used to prepare

the

instructors for evaluation of operator technical

performance

in

the simulator (including discussions

on management

expectations)

and found this training to be adequate.

In addition to meeting

the requirements

of the licensee's

in'structor training program,

l

'

7

evaluator s parti ci pated in a week

of preparati on prior to the

start of each requal cycle.

During the p'reparation

week, the

simulator

scenarios

for that cycle were conducted with the

instructors in the role of the operators.

The instructors

validated the effectiveness

of the scenario in achieving the

.identified training objectives for the week and ensure their own

'nderstanding

of the various operator actions required.

The inspectors

concluded that the licensee

evaluation

team

observed evaluating the operators

in the simulator was performing

satisfactorily.

However,

two issues

involving evaluator

qualification should

be addressed,

by the licensee to ensure

consistent

operator

evaluations

in the future.

(I)

-The licensee staff assigned

to evaluate

operator

performance in the 'simulator met the instructor

qualification requirements

and participated in the

preparation

week activities.

However, the inspectors

found

no procedural

requirement for the operations liaison staff

person to be qualified as

a simulator instructor.

This

practice

appeared

inconsistent with the standards

of the

other evaluators.

(2) It appeared that the licensee

had not established

a

program to retrain initial license training instructors with

the

new simulator performance

standards.

This could result

in different evaluation

standards

between initial operator

training and requalification training.

The licensee

acknowledged

these

two issues

and stated that they

would evaluate corrective actions for them.

The Shift Technical Advisor

STA

Trainin

Pro

ram

The inspectors

interviewed two STAs and observed their performance

during the requalification training week for the shift and staff

crews discussed

in paragraph

3.c.

Both STAs stated that they were

satisfied with the training program.

They said that the program

has

a specialized training segment for the entire

STA staff,

as

well as

STA integration into..the'equalification

week with

operating

cr ews.

This plan allows the

STAs to receive specialized

training,

such

as would be required for a nuclear engineer,

while

exposing the

STAs to different crews during the training weeks.

The

STA training program was

a rotational training program

centered

on a

STA specific training schedule

and the operator

requalification simulator training cycle.

The inspectors

found that the two STAs observed'n

the simulator

supported their assigned

crews well.

Their performance

was

consistent.

The operators

had high regard for their

STAs'bilities

and opinions.

The lead

STA evaluated

the

STA

performance

during the simulator scenarios.

The one-on-one

coaching of the senior

STA trainer/evaluator

appeared particularly

effective for training.

Trainin

De artment Staffin

Operator requalification training is currently being handled

by a

staff of eleven,

which includes six contractors.

Contractors

have

been

used

as

a result of four open instructor positions.

A site-

wide effort is under way.to reduce

the number of- contractor

workers.

Current plans call for filling the open training

positions

by December

1992.

However, the licensee

stated that

they plan to keep the contractors

on staff to allow time for

training and orientation of new training staff.

This is intended

to ensure consistent

evaluation of operators

during the

transition.

The inspectors

concluded this plan appeared

acceptable.

0 erator Overtime

The team evaluated

the use of overtime for operator training.

Early in 1992, validation of EOP revisions

was completed

by

operators

on overtime.

Overtime was scheduled for and limited to

the validation effort.

During the last several

months,

the

operators

have

been working three

days of overtime {approximately

4 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per day) during their training week to get additional

training on the simulator prior to the November requalification

examination.

The licensee

explained that after a program review earlier in the

year,

both operators

and management

had agreed to increase

and

revise the requal cycle content.

The revised content

was designed

to ensure that the operators

would be involved with an adequate

number of appropriately

complex simulator scenarios

addressing

a

variety of specific competencies.

This required additional

simulator time.

Eight operators

were interviewed to determine their view of using

overtime for training.

All of the interviewed operators

agreed

with the licensee's

strategy to prepare for the upcoming

examinations.

Several

operators

stated that the training week was

tiring.

The current level of overtime combined with the knowledge

that the training program status will be determined

based

on the

November

exam results

appeared

to contribute to the pressure

being

experienced

by the operators.

The licensee

has stated that the

1993 requalification training schedule will not require using

routine overtime to meet anticipated training needs.

The

1 i censee

'

Techni cal

Speci ficati ons

(TS) state that adequate

shift coverage shall

be maintained without routine heavy use of

overtime.

However, the

TS allow substantial

overtime use in the

event of "unforseen

problems."

Even so, the following guidelines

still apply: (I) an individual should not work more than

16

consecutive

hours,

(2)

an individual should not work more than

16

hours in any 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period,

24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> in any 48 hour5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> period, or 72

hours in any 7-day period,

(3) a break of at least

8 hours9.259259e-5 days <br />0.00222 hours <br />1.322751e-5 weeks <br />3.044e-6 months <br /> should

be allowed between

work periods,

and (4) except during extended

shutdown periods,

the use of overtime should

be considered

on an

individual basis

and not for the entire crew.

The plant manager

must authorize

any deviations

from these guidelines.

The inspectors

determined that the licensee

had not violated

Technical Specification overtime guidelines.

The inspectors

also

concluded that the use of operator overtime for the simulator

appeared

appropriate.

Industr

Events Trainin

The inspectors

reviewed the lesson

plans

and scenarios

used for

industry events training for three recent industry events:

(I)

the core instability event at MNP-2, (2) the loss of annunciators

and

RPV level instrumentation at Nine Nile Point-2,

and (3) the

refueling cavity seal failure at Connecticut

Yankee.

The

'nspectors

then developed test questions

from this material

and

verbally interviewed six operators

to .determine their

understanding

of the lessons

learned

from these

events.

All but

one of the operators

adequately

answered

the questions.

One senior operator could not recall all of the immediate actions

required

when moving irradiated fuel and reactor cavity inventory

began to visibly decrease.

The expected

responses

included:

(a)

notify the control

room supervisor

(CRS),

(b) move irradiated fuel

in transit back into the nearest

storage location,

and (c)

evacuate

the refueling floor.

The senior operator said that he

would try to stop the inventory loss but gave

no indication that

he would contact the

CRS.

He did not recall

any other immediate

actions without prompting from the inspectors.

During subsequent

follow-up, the inspectors

determined that the licensee

had no

formal method for assessing

operator retention of event lessons

,

learned

between

the 'time of the initial event debrief and the

implementation of appropriate

changes into the training programs.

The inspectors

observed that the recent

NRC augmented

inspection

team

(AIT) also found that operators

had poor recall of previous

training dealing with reactor

power oscillations.

Based

on this

AIT finding and the deficiency outlined above,

the inspectors

concluded that the licensee

may not be adequately

assessing

the

effectiveness

of industry events

lessons

learned training

conducted for their operators.

10

The licensee

acknowledged

the concern

and agreed to reassess

their

events training process.

5.

Summar

of 0 en Issues

The inspectors identified three areas of potential training program

weakness.

The licensee

acknowledged

these

concerns

and stated

they

would consider corrective actions for them.

~

The operations liaison staff person

was not certified as

a

training evaluator,

even though

he conducted training evaluations.

~

There

was

no process

to transfer the lessons

learned

and

. improvements

made in the operator requalification simulato'r

evaluation

process

to the initial operator

program.

~

The licensee

did not adequately

evaluate

the operators for

retention of lessons

learned

from industry events.

No .deviations or violations were identified.

Exit Meetin

30702

n

An exit meeting

was held by the

NRC with representatives

of the

licensee's staff on September

25,

1992 to discuss

the

NRC inspection

results identified above.

The inspectors.requested

a response

to the

three areas of concern identified above.

The inspectors

stated that the

response

should contain

a plan for corrective actions, if appropriate,

and the projected date

by which the licensee

expects to complete those

corrective

actions.

The licensee

acknowledged

the inspectors'oncerns,

and agreed to

respond

as requested.