Forwards Insp Rept 50-397/92-08 on 920323-27.No Violations or Deviations Noted.Rept Indicates That Licensee Behind Schedule in Processing Work Packages Through ALARA Planning & Work Control Groups
ML17289A522
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 04/23/1992
From: Yuhas G
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
To: Sorensen G
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
Shared Package
ML17289A523 List:
References
NUDOCS 9205110089
Download: ML17289A522 (5)


See also: IR 05000397/1992008

Text

~R IIEOy

Cy

An0

IIll0

+a*++

UNITED STATES

NUCLEAR REGULATORY COIHINISSION

REGION V

1460 MARIALANE, SUITE 210

WAlNUTCREEK, CAUFORNIA$40964li368

g,'I; g S

$0",0

Docket No. 50-397

License

No.

NPF-21

Washington Public Power Supply System

P.O.

Box 968

3000 George Washington

Way

Richland,

Washington

99352

Attention:

Mr.

G.

C. Sorensen,

Manager

Regulatory

Programs

SUBJECT:

NRC INSPECTION

REPORT

NO. 50-397/92-08

OF WPPSS

NUCLEAR PROJECT

2

(WNP-2)

This letters refers to the inspection

conducted

by Mr. L.C. Carson II, on

March 23 through 27, 1992,

and subsequent

telephone

conversations

on March 31,

April 13,

and April 15, 1992, of activities authorized

by

NRC License

No.

NPF-21.

The inspector discussed

our findings with Mr. L. Harrold and other

members of the WHP-2 staff at the conclusion of the inspection.

Areas examined during this inspection are described in the enclosed

inspection

report.

Within these

areas,

the inspection consisted 'of selective

examinations of procedures

and representative

records,

interviews with

personnel,

and observations

by the inspectors.

Within the scope of this inspection,

no violations or deviations

were

identified.

Section 2(b) of the enclosed report indicates that you were behind schedule

in

processing

work packages

through your ALARA planning and work control groups

for the

R-7 outage.

Based

on our discussions

with Mr. Baker and Mr. Pisarcik

of your staff,

we understand that additional

resources

were applied

and that

most work packages

for the first month of the outage

have

been processed

through the

ALARA planning group.

In accordance

with 10 CFR 2.790 of the NRC's "Rules

and Practices,"

a copy of

this letter and the enclosure will be placed in the Public Document

Room.

Should you have

any questions

concerning this inspection,

we will be glad to

discuss

them with you.

Sincerely,

GP.

G.P.

as,

Chief

Reactor Radiological Protection

Branch

9205110089

920423

PDR

ADOCK 05000397

Q

PDR

rg

,

0'

Enclosure:

Inspection

Report

No. 50-397/92-08

cc w/enclosures:

Mr. J.

W. Baker,

WNP-2 Plant Manager

Mr. A.

G. Hosier,

WNP-2 LIcensing Manager

Mr.

L.

L. Grumme, Acting Director, Licensing and Assurance

Mr.

G.

E.

Doupe,

Esq.,

WPPSS

Mr. A. Lee Oxsen,

Deputy Managing Director

Mr.

M.

H. Phillips, Esq.

(Winston

8 Strawn)

State of Washington

APR 23 "8>

bcc w/enclosures:

Oocket File

Resident Inspector

Project Inspector