UNITED STATES NUCLEAR REGULATORY COMMISSION REGION V
~
1450 NIARIALANE. SUITE 210 WALNUTCREEK, CALIFORNIA94596-5368 October 11, 1991 Docket No. 50-397 Washington Public Power Supply System P. 0.
Box 968 3000 George Washington Way Richland, Washington 99352 Attention:
Mr. G.
C. Sorensen
- Manager, Regulatory Programs
SUBJECT:
WNP-2 ANNUAL EXAMINATION OBSERVATION/OPERATIONAL EVALUATION, EXAMINATION REPORT 50-397/OL-91-03 Cenitleman:
This refers to the evaluation conducted from August 22, 1991, through September 25, 1991, to assess your requalification program and operating crew performance.
This was accomplished through inspector interviews of your staff, the review of your test materials, and the assessment by our
- examiners of your evaluators ability to prepare and administer annual examinations to three operating crews.
This report also discusses the results of the Operational Evaluations, conducted by the NRC on September 9, 1991, and September 25, 1991, to assess an additional operating crew.
At the conclusion of the Operational Evaluation on September 25, 1991, the NRC'iscussed the preliminary findings with those members of your staff identified in the enclosed examination report, Enclosure l.
After this meeting, the NRC concluded that, regarding the matters discussed in our Confirmatory Action Letter (CAL) V-91-01, your corrective actions to resolve those matters were sufficiently complete to warrant resumption of power operations at WNP-2 (see letter, J. 'B. Martin to A. L. Oxsen, dated 9/25/91).
As noted in the referenced CAL, the WNP-2 Licensed Operator Requalification Program will not be provisionally satisfactory until a determination has been made by the NRC that your short and intermediate term corrective actions have been substantially completed in an effective manner.
The NRC will notify you when this determination has been made.
9110220130 9iiOii PDR ADOCK 05000397 V
October ll, 1991 Again, it is our understanding that in the event you decide to alter the composition of any of your operating
- crews, you wi 11 notify the NRC Regional Office of the changes until such time that your reoualification program is found satisfactory or provisionally satisfactory.
Should you have any questions concerning this letter, please contact us.
Sincerely, Dennis F. Kirsch, Chief Reactor Safety Branch
Enclosures:
(lf Examination Report 50-397/OL-91-03 (2)
Simulation Facility Report
cc w/enclosures (1) and (2):
Nr. J.
W. Baker, WNP-2 Plant Manager Nr. A.
G. Hosier, WNP-2 Licensing Manager Nr.
G.
D. Bouchey, Director, Assurance 5
Licensing Nr.
G. E. Dovpe, Esq.,
WPPSS Nr. D.
W. Nazur, Managing Director Nr. A. Lee Oxsen, Deputy Managing Director
bcc w/enclosures (1) and (2):
T. Meadows, RV R. Cross, RV (two copies)
D. Topley, WNP-2 Requalification Supervisor bcc w/enclosure (1) only:
J. Martin, RV R.
Zimmerman, RV K. Perkins, RV D. Kirsch, RV L. Miller, RV P. Johnson, RV T. Sundsmo, RV C. Sorensen, SRI P.
Eng, Project Manager, NRR/PD5 J. Munro, NRR/LOLB T. Walker, RI bcc w/enclosure (2) only:
N. Hunemuller, NRR/LOLB bcc w/enclosures (1) and (2):
U C
E C
P
/
NO
/
NO
/
NO MEADOWS ~~~
P JOHNSON LMILLER 10/I //91 10/
/91 10//Q 91 RE C
/
NO KIRSCH 10/I1/91 C
/NO
ENCLOSURE 1
EXAMINATION REPORT 50-397/OL-91-03