Forwards Special Rept Per Requirements of Facility Tech Spec 3.3.7.2, Seismic Monitoring Instrumentation Which Requires Instruments to Be Operable at All Times
ML17286A875
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 05/24/1991
From: John Baker
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Martin J
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION V)
References
NUDOCS 9106100517
Download: ML17286A875 (5)


Text

ACCELERATED DI~OUTION DEMONST+Ai.TION SYSTEM REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:9106100517 DOC.DATE-'1/05/24 NOTARIZED: NO'OCKET FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH.NAME AUTHOR AFFXLIATION BAKER,J.W.

Washington Public Power Supply System RECXP.NAME RECIPIENT AFFXLIATXON MARTIN,J.B.

Region 5 (Post 820201)

SUBJECT:

Submits special rept pursuant to requirements of facility tech spec 3.3.7.2 "Seismic Monitoring Instrumentation" which requires instruments to be operable at all times.

DISTRIBUTION CODE:

IE01D COPIES RECEIVED:LTR ENCL 0 SIZE:

TITLE: General (50 Dkt)-Insp Rept/Notice of Vio ation Response NOTES:

RECIPIENT ID CODE/NAME PD5 PD

'INTERNAL: ACRS AEOD/DEIIB DEDRO NRR SHANKMAN,S NRR/DOEA/OEAB NRR/DRIS/DIR NRR/PMAS/ILRB12 0

I EG FI ~

02 EXTERNAL: EG&G/BRYCE,J.H.

NSIC COPIES LTTR ENCL RECIPIENT ID CODE/NAME ENG,P.L.

AEOD AEOD/TPAB NRR MORISSEAU,D NRR/DLPQ/LPEB10 NRR/DREP/PEPB9H NRR/DST/DIR 8E2 NUDOCS-ABSTRACT OGC/HDS1 RGN5 FILE 01 NRC PDR COPIES LTTR ENCL 1

1 1

1 1

1 1

1 1

D D

NOTE TO ALL"RIDS" RECIPIENTS:

A D

D PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK, ROOi%1 P 1-37 (EXT. 20079) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OP COPIES REQUIRED:

LTTR, 24 ENCL~

WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O. Box 968

~ 3000 George Washington Way

~ Richland, Washinglon 99352 G02-91-107 Docket No. 50-397 Hay 24, 1991 Hr. J.

B. Hartin Regional Administrator

USNRC, Region V

1450 Maria Lane, Suite 210 Walnut Creek, CA 94596 psq Pl I 1 CD Plo

Dear Mr. Hartin:

Subject:

NUCLEAR PLANT NO. 2, LICENSE NO.

NPF-21 SPECIAL REPORT:

SEISMIC MONITORING INSTRUMENTATION This Special Report is submitted to pursuant to the requirements of WNP-2 Technical Specification section 3.3.7.2 "Seismic Monitoring Instrumentation" which requires the instruments to be operable at all times.

The seismic monitoring system has been designed and installed to record the response of plant buildings and systems to ground motions produced by earthquakes.

Some of this information would then be used by plant operators to immediately determine the relative size of the event.

The remaining information would be used over the long term to determine the plant response to a significant seismic event.

The action statement for this specification requires that "with one or more of the above required seismic monitoring instruments inoperable for more than 30

days, in lieu of any other report required by Specification 6.9.1, prepare and submit a Special Report to the Commission pursuant to Specification 6.9.2 within the next 10 days outlining the cause of the malfunction and the plans for restoring the instrument(s) to operable status."

H 9l0l.100 l7 910. 24 PDFl ADOCK 0500035'7 F

PDR

Page'wo SPECIAL REPORT:

SE ISHIC HONITORING INSTRUHENTATION SE IS-TPA-1 On April 16, 1991, with the plant in Hode 4 (cold shutdown) and preparing to

'nter Hode 5 (refueling) for the annual maintenance and refueling outage, the triaxial peak accelerograph (SEIS-TPA-1) attached to the space frame above the reactor vessel head was taken out of service as the frame was removed for reactor refueling.

This action makes the instrument inoperable and caused entry into Technical Specification Action Statement 3.3.7.2.

Triaxial peak accelerograph SEIS-TPA-l,is a sensitive, wide band, low frequency, acceleration recording instrument.

Permanent records are scribed by diamond styli on replaceable metal plates.

The peak acceleration is computed by multiplying the maximum excursion of the trace by the acceleration sensitivity of the recorder.

This passive instrument is used to capture the response of the space

frame, a steel structure located between the reactor vessel head and containment head structures.'he data collected is for subsequent engineering analysis and does not provide any external parameter display, annunciation, or initiate any automatic action.

This data, does not play a role in the immediate determination of plant operability following a seismic

event, Any loss of data from this instrument can best be characterized as a lost opportunity to aid in an analysis to support a

decision to restart should a significant seismic event have been experienced.

A review of previous plant outages shows that SEIS-TPA-1 was necessarily removed from service along with the disassembly of the reactor head components.

Each period was for greater than 30 days and should have been reported in a special report in accordance with Technical Specification requirements, but was overlooked.

This condition will be reported in the future.

~SEIS-TPA-1 will be restored to operable status at the completion of refueling when the reactor head components are reinstalled.

During the interim, the occurrence of a seismic event will be captured by other seismic instruments.

Plant restart is currently scheduled for early-June following the conclusion of the maintenance and refueling outage.

SEIS-TPA-2 and SEIS-RSR-1/1 1/2 1/3 On April 26, 1991 during annual maintenance of the High Pressure Core Spray (HPCS) seismic instruments, it was noted that the as-found condition would have precluded full recording capability during a real seismic event.

Ooth SEIS-TPA-2 and SEIS-RSR-1 were found to have recorded accelerations on the permanent scratch plates which would have likely masked any record produced by a seismic event if one had occurred.

These instruments are, therefore, considered inoperable and are being reported in accordance with the action statement described above.

~ Page'hree SPECIAL REPORT'EISMIC MONITORING INSTRUMENTATION SEIS-TPA-2 is a triaxial peak accelerograph located on the HPCS injection line inside primary containment at elevation 538 feet.

Its operation is identical to SEIS-TPA-1 previously described.

Recorder SEIS-RSR-1/1, 1/2, and 1/3 is a

triaxial response spectrum recorder located on a

HPCS injection line pipe support in the HPCS pump room at the 448 feet elevation of the reactor building.

Its operation is different from the TPA instrument in that it monitors 12 discreet frequencies between 2 and. 25 Hz.

All the accelerometers use diamond-tipped styli to inscribe permanent records of displacement on special record plates.

These plates are only capable of a single recording.

Subsequent actuations without plate replacement will only produce records if they exceed the previous displacement, although there is no way to distinguish between the sources of acceleration.

In the case of SEIS-TPA-2 and SEIS-RSR-1/1, 1/2, and 1/3 it is postulated that the accelerations generated by the HPCS system actuations produce records which would effectively mask and seismic events.

Evaluation-of the records'rom SEIS-RSR-1 show that below 8 Hz the records were less than the OBE basemat spectrum.

Above 8

Hz the records were larger than the spectrum and, therefore, would mask any actual records around this critical area of interest.

The as-found records from SEIS-TPA-2 were for all practical purposes off-scale high.

There is no way with certainty to determine when these records were made and thus how long the instruments would have been rendered inoperable.

A test involving a HPCS system injection to the vessel was conducted in November 1990 and is the most likely source of the high accelerations.

To prevent the occurrence of this event plant procedures will be changed to require checking the HPCS seismic instruments if a vessel injection is performed.

Engineering evaluations have determined that these instruments must be moved to prevent recurrence of this data masking problem.

A selection process is currently underway to determine small displacement locations along the HPCS system.

This process will involve a routine test actuation of an instrumented HPCS system.

The test will include operation of the HPCS system with water returned to the Containment Suppression Pool or the Condensate Storage Tank.

These two instruments will be installed at their new locations prior to plant restart from the outage which is currently scheduled for early-June.

Very truly yours, J.W.

Baker WNP-2 Plant Manager cc: