Monthly Operating Rept for Apr 1990 for WPPSS Nuclear Plant Unit 2
ML17285B265
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 04/30/1990
From: Hutchison L, Powers C
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9005160350
Download: ML17285B265 (8)


Text

ACCELERATED D STPJBUTION DEMONSTPATION SYSTEM

'REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

ACCESSION NBR:9005160350 DOC.DATE: 90/04/30 NOTARIZED:

NO DOCKET g

FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH.NAME AUTHOR AFFILIATION HUTCHISON,L.B.

Washington Public Power Supply System POWERS,C.M.

Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly operating rept for Apr 1990 for WPPS Nuclear Plant Unit 2.W/900505 ltr.

DISTRIBUTION CODE:

IE24D COPIES RECEIVED:LTR ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Specs)

NOTES:

RECIPIENT ID CODE/NAME PD5 LA SAMWORTH,R INTERNAL: ACRS AEOD/DSP/TPAB N

Q/ PEB10 EG FI 01 EXTERNAL EGGG STUARTiV A NRC PDR COPIES LTTR ENCL 3

3 1

1 10 10 1

1 1

1 1

1 1

1 1

1 RECIPIENT ID CODE/NAME PD5 PD AEOD/DOA IRM TECH ADV NRR/DOEA/OEAB11 RGN5 LPDR NSIC COPIES LTTR ENCL 1

1 1

1 2

2 1

1 1

1 1

1 1

1 pqg pe ~ds7a NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WAS'ONTACTTHE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 20079) TO ELIMINATEYOUR NAMEFROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED:

LTTR 27 ENCL 27

WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O. Box 968

~ 3000 George Washington Way

~ Richland, Washinglon 99352 Docket No.

50-397 May 5, 1990 U. S.

Nuclear Regulatory Commission Document Control Desk Washington, D. C. 20555

Dear Sir:

SUBJECT:

NUCLEAR PLANT NO.

2 MONTHLY OPERATING REPORT APRIL 1990 Transmitted herewith is the Monthly Operating Report as required by our, Technical Specifications 6.9.1.6.

Vel.y Truly Youl s, C.

M. Powers (M/D 927M)

WNP-2 Plant Manager CMP/lc Enclosure cc: Mr.

Mr.

Ms.

Mr.

Ml.

J.

B. Martin-C. J. Bosted-Dottie Sherman J. T. Wheelock W.

H. Lovelace NRC Region V

NRG Resident Inspector (901A)

- ANI, Farmington GT

" INPO

- NRG, Washington D.C.

p~PP>>6P~:,p

~

RDR ADOC<

ppypp P5ppp3~~

F'DC P 7@3 god S7$

e

AEPCAT PEAIOO A'PRIL 19 90 men th, year

'NIT SIOTDONNS / AEDUCTIONS

~

~

DOCKET HO.

50-397 UNIT l'Nl)E DME 5

1 90 COMPLETED DY LB HUTCHISON TELEPI GlC (509) 377-24B6 FRI.

DRK 'f7'IKIIIh m*iigigl ~Ilia 90-02 4/21/90 S

239.5 C

1

~W ttlWIEw~.

1 H

RC FUEL XX;'lant shutdown as scheduled for refueling outage R-5 WRP-2 operated routinely in APRIL, completing the end of cycle on a fuel coastdown.,

Plant was shutdown on 21st for scheduled refueling outage.

F-Forced S-SchKI A-Equi.p Failure 0-Maint or Test

~

C-Aefue1 jng 0-Aequlatory Aes triction E-Operator Training h License Examination F-hdmin 0-Oper Error H-Other MFAf00 I-Manual 2-Manual Scratch 3-Iluto Scram 4-Continued I lie~iced Load 9-Other SYSTEM k COWPOM:.NT Exhibit F h H Instructions f'r Preparation ol'ata Entry Sheet Licensee Event Aepnrt (LEA) Filo (NUAEG-0161)

OPERATING DATA REPORT WNP-2 01-May-90 1.

DOCKET: 50-397 2.

REPORTING PERIOD:

Apr-90 3.

UTILITY CONTACT:

OUTAGE + ON-LINE HOURS LEONARD HUTCHISON (509) 377-2486 719 4.

LICENSED THERMAL POWER (MWt):

5.

NAMEPLATE RATING (GROSS MWe):

6.

DESIGN ELECTRICAL RATING (NET MWe):

7.

MAXIMUM DEPENDABLE CAPACITY (GROSS MWe):

8.

MAXIMUM DEPENDABLE CAPACITY (NET MWe):

9.

IF CHANGES OCCUR ABOVE SINCE LAST REPORT, GIVE REASONS:

3323 1200.9 1100 1140 1095 10.

POWER TO WHICH RESTRICTED, IF ANY (NET MWe):

ll. REASONS FOR RESTRICTIONS, IF ANY:

None 12.

REPORT PERIOD HOURS 13.

HOURS REACTOR CRITICAL 14.

RX RESERVE SHTDWN HRS 15.

HRS GENERATOR ON LINE 16.

UNIT RESERVE SHUTDOWN HOURS 17.

GROSS THERMAL ENERGY (MWH) 18.

GROSS ELECTRICAL ENERGY (MWH) 19.

NET ELECTRICAL ENERGY (MWH) 20.

UNIT SERVICE FACTOR 21.

UNIT AVAILABILITYFACTOR 22.

UNIT CAPACITY FACTOR (MDC NET) 23.

UNIT CAPACITY FACTOR (DER NET) 24.

UNIT FORCED OUTAGE RATE 25.

FORCED OUTAGE HOURS MONTH 719 493.8 0.0 479.5 0.0 1397909 461570 439296

66. 7>o 66.74
55. 8~o
55. 5>o 0.04 0.0 YEAR CUMULATIVE 2879 47143.2 2653.8 35729.1 0.0 340.4 2639.5 34487.4 0.0 381.7 8233337 96577777 2739380 32143330 2640193 30926336 91 '~o 73 '+o 91.74 74.04 83.74 59.9%

83.4~o 59.64 0.0<

8. 0>o 0.0 2996.2 26.

SHUTDOWNS SCHEDULED OVER THE NEXT 6 MONTHS (TYPE, DATE, DURATION):

27. IF CURRENTLY SHUTDOWN ESTIMATED STARTUP DATE:

6/5/90

t r l

~ ~

AYERAGE GAILY UNIT PURER LEVEL~

DOCKET NO.

UNIT WNP-2 DATE 5/1/90 MONTH APRIL 1990 DAY AVERAGE DAILY POWER LEVEL (MwE-Net) 923 17.

COMPLETED BY LB HUTCHISON TELEPHONE (509) 377-2486 DAY AVERAGE DAILY POWER LEVEL (MwE-Net) 918 2.

3.

4, 5.

6.

7.

8.

9.

10.

12.

13.

14.

15.

16.

957 958 953 950 946 940 937 937 932 922 928 926 933 924 920 18.

19.

20.

21.

22.

23.

24.

25.

26.

27

'8.

29 ~

30.

31.

916 909 719 INSTRUCTIONS On this form, list the average dai'ly unit power level in MWe-Net for each day in the reporting month.

Compute to the nearest whole megawatt.

These figures will be used to plot a graph for each reporting month.

Note that when maximum dependable capacity is used for the net electrical rating of the unit, there may be occasions when the daily average power level exceeds the 100 line (or the restricted power level line).

In such

cases, the average daily unit power output sheet should be footnoted to explain the apparent anomaly.

t~

C g ~

Jt

~

Ilb