Forwards FEMA Evaluation Rept for out-of-sequence Washington State Lab & Food Control Drills for Washington Nuclear Power Project 2.Rept Indicates That FEMA Did Not Identify Any Deficiences or Areas Requiring C/A During Drills
GO2-99-117, Forwards Response to NRC GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Npps
GO2-99-121, Forwards Addl Info Requested in to Support Review of Pending Response to GL 95-07, Pressure Locking & Thermal Binding of Safety-Related Power Operated Gate Valves
GO2-99-122, Responds to 990623 RAI to Support Review of Evaluation of Planar Indication Found on Weld Number 24RRC(2)A-1 During 1998 RO
GO2-99-123, Provides Notification of Early Completion on 990630 of Exception Noted in .Equipment within Scope of GL 98-01,Suppl 1, Y2K Readiness of Computer Sys at Nuclear Power Plants, Evaluated & Y2K Ready
ML17292B724
GO2-99-128, Forwards NRC Form 396 & NRC Form 398,for If Sumsion,License OP-50487 & Ga Westergard,License SOP-50415 for Renewal of Operator Licenses.Without Encls
ML17292B729
ML17284A864
ML17292B732
ML17292B737
GO2-99-133, Submits Withdrawal of Request for Amend to Secondary Containment & Standby Gas Treatment Sys Ts.Util Currently Plan to re-submit Amend Request in Entirety by 991112
ML17292B740
GO2-99-397, Forwards Rev 23 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b) & 50.54(q) & 10CFR50 App E.Rev 23 Provides Updated Description Re Establishment of Separate Emergency Operation Centers for Benton & Franklin Counties
ML17292B741
GO2-99-139, Clarifies Change of Licensee Name from Wpps to Energy Northwest & Change of Facility Name from WPPSS Nuclear Project Number 2 to WNP-2,as Requested in 990719 Telcon with Js Cushing of NRC.Marked-up OL Pages,Encl
ML17284A829
ML17284A831
GO2-99-148, Forwards Estimate of Number of Licensing Action Requests Planned for Submittal in Future,As Requested in Administrative Ltr 99-02.Twenty-nine Submittals Scheduled for Fy 2000 & Four for Fy 2001
GO2-99-149, Forwards Proprietary Addl Info to Support Review of Pending Request for Amend to MCPR Safety Limit Ts.Info Consists of Proprietary Ltr from ABB Combustion Engineering,Inc.Encl Withheld
ML20210L146
ML17284A857
ML17284A861
ML20211A950
GO2-99-155, Submits Two ISI Program Plan Relief Requests for NRC Review & Approval,Per 10CFR50.55a(a)(3)(i).Proposed Alternatives Provide Acceptable Level of Quality & Safety
ML17284A865
GO2-99-158, Forwards NRC Form 396, Certification of Medical Exam by Facility Licensee & NRC Form 398, Personal Qualification Statement - Licensee, for Jd Prescott (License SOP-50262-1).Without Encls
ML17292B750
GO2-99-163, Requests That Eleven Individuals Listed Below Take BWR Generic Fundamentals Examination to Be Administered on 991006
GO2-99-162, Forwards Fitness for Duty (FFD) Semiannual Performance Data Rept for Jan-June 1999,per 10CFR26.71(d)
ML17284A877
GO2-99-165, Provides Correct Page from License NPF-21 Marked to Show Rev Addressed in 990729 Application for Amend,Which Included Page That Was Inadvertently Included as Attachment 4.Replace Attachment 4 with Attached Page & Disregard Attachment 5
GO2-99-166, Informs Staff of Errors in world-wide-web Database Related to WNP-2 Reactor Vessel Structural integrity.Marked-up Pages Containing Errors or Omissions Will Be Forwarded by 991201
GO2-99-164, Forwards Proprietary Info to Support Review of Request for Amend to License NPF-21,re Min Critical Power Ratio Safety Limits Tss,As Requested During 990816 Conversation. Proprietary Encl Withheld
GO2-99-168, Forwards Rev 40 to Physical Security Plan.Rev Withheld,Per 10CFR2.790(a)(3)
GO2-99-169, Forwards Response to NRC 990623 RAI to Support Review of Pending Request for Amend to Reactor pressure-temp Limit Curve TS
ML17292B756
GO2-99-172, Forwards NRC Forms 396 & 398 for Nl Hancock,License SOP-50027-3,AR Herrington,License OP-50013-3,WH Sawyer, License SOP-50023-3 & Dl Strote,License SOP-50031-3,for Renewal of Licenses.Without NRC Forms 396 & 398
ML17292B757
GO2-99-174, Informs NRC of Change in Schedule Pertaining to Final Implementation of Reactor Stability long-term Solution for WNP-2
GO2-99-173, Forwards Rev 24 to WNP-2 Emergency Plan,Iaw 10CFR50.4(b), 50.54(q) & 10CFR50 App E.Detailed Synopsis of Changes,Encl
ML17284A882
ML17284A906
ML17292B762
GO2-99-182, Forwards Rev 0 to WNP-2 Cycle 15,COLR 99-15, IAW Requirements of TS 5.6.5
~O UNITEDSTATES NUCLEAR REGULATORY COMMISSION REGION IV 611 RYAN PLAZADRIVE, SUITE 400 ARUNGTON,,TEXAS 76011%064 October 19, 1999 Mr. J. V. Parrish (Mail Drop 1023)
Chief Executive Officer Energy Northwest P.O. Box 968 Richland, Washington 99352-0968 SUBJECT'EDERAL EMERGENCY MANAGEMENTAGENCY'S REPORT
Energy Northwest Rodney L. Webring (Mail Drop PE08)
Vice President, Operations Support/PIO Energy Northwest P.O. Box 968 Richland, Washington 99352-0968 Greg O. Smith (Mail Drop 927M)
Vice President, Generation Energy Northwest
'.O.
Box 968 Richland, Washington 99352-0968 D. W. Coleman (Mail Drop PE20) h/lanager, Regulatory Affairs Energy Northwest P.O. Box 968 Richland, Washington 99352-0968 Albert E. Mouncer (Mail Drop 1396)
General Counsel Energy Northwest P.O. Box 968 Richland, Washington 99352-0968 Paul Inserra (Mail Drop PE20)
Manager, Licensing Energy Northwest P.O. Box 968 Richland, Washington 99352-0968 Perry D. Robinson, Esq.
Winston & Strawn 1400 L Street, N.W.
Washington, D.C. 20005-3502 Bob Nichols State Liaison Officer Executive Policy Division Office of the Governor P.O. Box 43113 Olympia, Washington 98504-3113 Training, Exercises, 8 Evaluation Branch Chief FEMA Region X Federal Regional Center 130 228th Street, S.W.
Regional Administrator DRS Director DRP Director Branch Chief (DRPhE)
Project Engineer (DRP>E)
Branch Chief (DRP>TSS)
P. Elkmann C. A. Hackney, RSLO T. Essig, NRR<DIPINIOLB(MS 12 H2)
DOCUMENT NAME: S:iDRSiDRSLTRS'PEP.MLDiWN9902FM.LOO.WPD AI 99-E-064 To receive copy of document, Indicate In box: "C" ~ Cop without enclosures E" ~ Cop with enclosures "N" = No copy RIV:PSB E