REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)
ACCESSION NBR:9807170136
. DOC.DATE: 98/07/14
NOTARIZED: NO
DOCKET
FACIL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public
Powe
05000397
AUTH.NAME
AUTHOR AFFILIATION
MURRAY,B.
Region
4 (Post
820201)
RECIP.NAME
RECIPIENT AFFILIATION
PARRISH,J.V.
Washington Public Power Supply System
SUBJECT: Forwards insp rept 50-397/98-17
on 980629-0702.No violations
,noted.Insp
reviewed radiological environ
&: meterological
monitoring programs. Overall, programs
were effectively
implemented.
T
DISTRIBUTION CODE:
IEOSF
COPIES
RECEIVED:LTR J
ENCL g
SIZE: f g I
TITLE: Environ
& Radiological
(50 DKT) -Insp Rept/Notice of Violation Responsa
NOTES:
RECIPIENT
ID CODE/NAME
PD4-2
COPIES
LTTR ENCL
1
1
RECIPIENT
ID CODE/NAME
POSLUSNY,C
COPIES
LTTR ENCL
1
1
INTERNAL:
FILE
R
R/DRPM/PERB
, OE DIR
RGN4
FILE
01
2
2
1
1
1
1
1
1
1
1
AEOD/TTC
NMSS/SFPO
06F18
NUDOCS-ABSTRACT
OGC/HDS3
1
1
1
1
1
1
1
1
EXTERNAL: NOAC
NUDOCS FULLTEXT
1
1
'
1
NRC
II-O~MGNm
NRC FLOPPy
NOTE TO ALL "RIDS" RECIPIENTS:
PLEASE HELP US TO REDUCE WASTE.
TO HAVE YOUR NAME OR ORGANIZATION REMOVED FROM DISTRIBUTION LISTc
OR REDUCE THE NUMBER OF COPIES RECEIVED BY YOU OR YOUR ORGANIZATION
CONTACT THE DOCUMENT CONTROI
DESK
(DCD)
ON EXTENSION 415-2083
TOTAL NUMBER OF COPIES
REQUIRED:
LTTR
15
ENCL
15
I
Qi
g,>> Rfggi
'P~
J'
g~
/y
"
~
1
<<<< ~ >>>>
UN I T E 0 STATE 6
NUCLEAR REGULATORY COMMISSION
REGION IV
611 RYAN PLAZA DRIVE, SUITE 400
ARLINGTON,TEXAS 76011 8064
Ju1y
14;
1998
Mr. J. V. Parrish (Mail Drop 1023)
Chief Executive Officer
Washington Public Power Supply System
P.O. Box 968
Richland, Washington
99352-0968
SUBJECT:
NRC INSPECTION REPORT 50-397/98-17
Dear Mr. Parrish:
From June 29 through July 2, 1998, radiological environmental and meteorological monitoring
programs inspection was conducted at your Washington Nuclear Project-2 reactor facility. The
enciosed report presents the scope and results of that inspection.
The inspection reviewed the radiological environmental and meteorological monitoring
programs.
Overall, the programs were effectively implemented.
In accordance with 10 CFR 2.790 of the NRC's "Rules of Practice," a copy of this letter and its
enclosure will be placed in the NRC Public Document Room (PDR).
Should you have any questions concerning this inspection, we will be pleased to discuss them
with you.
Sincerely,
Blaine Murray, Chief
Plant Support Branch
Division of Reactor Safety
Docket No.:
50-397
~
License No.:
Enclosure:
NRC Inspection Report
50-397/98-17
cc w/enclosure:
Chairman
Energy Facility Site Evaluation Council
P.O. Box 43172
Olympia, Washington
98504-3172
9807i70i36 9807i4
ADOCK 050003'P7
8
Washington Public Power Supply System
Mr. Rodney L. Webring (Mail Drop PE08)
. Vice President, Operations Support/PIO
Washington Public Power Supply System
P.O. Box 968
Richland, Washington
99352-0968
Mr. Greg O. Smith (Mail Drop 927M)
WNP-2 Plant General Manager
Washington Public Power Supply System
P.O. Box 968
Richland, Washington
99352-0968
Mr. D. W. Coleman (Mail Drop PE20)
Manager, Regulatory Affairs
Washington Public Power Supply System
P.O. Box 968
Richland, Washington
99352-0968
Mr. Albert E. Mouncer (Mail Drop 396)
Chief Counsel
Washington Public Power Supply System
P.O. Box 968
Richland, Washington
99352-0968
Mr. Paul Inserra (Mail Drop PE20)
Manager, Licensing
Washington Public Power Supply System
P.O. Box 968
Richland, Washington
99352-0968
Perry D. Robinson, Esq.
Winston 8 Strawn
1400 L Street, N.W.
Washington, D.C. 20005-3502
Washington Public Power Supply System
-3-
E-Mail report to T. Frye (TJF)
E-Mail report to D. Lange (DJL)
E-Mail report to NRR Event Tracking System (IPAS)
E-Mail report to Document Control Desk (DOCDESK)
bcc to DCD (IE06)
bcc distrib. by RIV:
Regional Administrator
DRS Director
DRP Director
Branch Chief (DRP/E, WCFO)
Senior Project Inspector (DRP/E, WCFO)
Branch Chief (DRP/TSS)
WCFO File
WNP-2 Resident Inspector
DRS Deputy Director
DRS-PSB
MIS System
RIV.File
DOCUMENT
Pgf
(rl"
p4iV
E::i WN2)WN817RP.MCH
To receive cop
of do
me, indicate in box: "C" = Copy without enclosures
"E" = Copy with enclosures "N" = No cop
HWong
MCHay:nh
RIV:RS:PS
E
C:DRPiE
N
C:DRS>PS
N
BM
ray
07/
98
07
8
07
98
OFFICIAL R CORD COPY
Washington Public Power Supply System
-3-
E-Mail report to T. Frye (TJF)
E-Mail report to D. Lange (DJL)
E-Mail report to NRR Event Tracking System (IPAS)
E-Mail report to Document Control Desk (DOCDESK)
bcc to DCD (lE06)
bcc distrib. by RIV:
Regional Administrator
DRS Director
DRP Director
Branch Chief (DRP/E, WCFO)
Senior Project Inspector (DRP/E, WCFO)
Branch Chief (DRP/TSS)
WCFO File
'I
WNP-2 Resident Inspector
DRS Deputy Director
DRS-PSB
MIS System
RIV File
DOCUMENT
E..h WN2 WN817RP.MCH
To receive cop
of do m, indicate In box: "C" = Copy without enclosures
"E" = Copy with enclosures "N" = No copy
RIV RS P
E
C DRPllE
N
C:DRSiPS
N
MCHay:nh
07/
98
HWong
07
8
BM
ray
07
98
OFFICIAL R CORD COPY