Validation Operating Exam Admin JPMs SRO A-1
- 1. Change Cue
- 1. Put actual dates in for current and predicted data sets
- 2. Look up reasons for differences in HPSI between sections 4 and 5
- 1. Add time critical JPM ROA-1
- 1. Fix cue to remove leading statement ROA-2
- 1. Fix cue to disregard volume of piping ROA-3
- 1. Fix cue, correct guide pg 6, correct Attachment pg 8 of 9 ROA-4 System JPMs S-1 (MS-270) EOP 2532 LOCA Cooldown S-2 (MS-284) Respond to CEA misalignment S-3 (MS-243) SP-2604T ESAS Actuation test
- 1. Reword cues and initial conditions
- 2. Identify critical steps S-4 (MS-211) Pump Containment sump S-5 (MS 285) Energize 24E from U3
- 1. Rewrite initial conditions
- 2. Task #1 energize 24E bus from U3, Task #2 swap SW pumps if operator does not identify faulted bus S-6 (MS-288) Control PZR Level from C-21
- 1. Split tasks to make a. Pressure control, b. Level control
- 2. Establish appropriate failure criteria for each task S-7 (MS-011) Evaluate RCP conditions
- 1. Wrote new JPM for bearing failure, loss of oil reservoir.
S-8 (MS-230) LPSI pump failure to trip post SRAS
- 1. Reword cue sheet
- 2. Provide EOP copy marked up to step 45