REGULAT INFORMATION DISTRIBUTIO STEM (RIDS)
ACCESSION NBRg 8103170634 DOC ~ OATEN'1/03/1-0 NOTARIZED:
NO DOCKET' FACILt50 397 WPPSS Nuclear Projects Unit'i Washington Public Powe 05000397 AUTH,NAME AUTHOR AFFILIATION MATLOCKER~ G.
Washington Public Power Supply System RECIP ~ NAME RECIPIENT AFFILIATION ENGELKENER'OH'egion Si San Franciscog Office of the Director SUBJECT; Inter im de'ficiency r ept r e design ver ification of 'Seismic Category I>> Quality Glass I heatdngiventilation 8 air condit4oning, sys hangersiinitially -reported on 801215
~
Revised contractor procedures have-been
- approved, DISTRIBUTION CODE; SOISS COPIES RECEIVED:LTR J:ENCL SIZE TITLE.: Construction Deficiency Rep'or t" (lOCI-R50,55E)
NOTES;PM:
~ 2" copies of all matet ial, 05000397 RECIPIENT ID CODE/NAMEI ACTION:
A/D L'ICENSNG 00 RUSHBROOKpM ~
06 INTERNAL: AD/RCI/IE "1 7 D/DIR HUM FAC15 EQUIP QUAL BR11.
ILhI 09 MPA'0.
OELD 21 QA BR RUTHERFORDgW,IE>>
COP I E'S LTTR ENCL 1
1 1i 1
RECIPIENT ID CODE/NAME YOUNGBLOODgB 05:
LYNCHED'7 ASLBP/J ~ HARD EDO 8
STAFF 19 HYD/GEO BR 22 LIC'UAL>> BR 1,2" NRC PDR" 02 P
REV 13 Ol S
DEV 21 COPIES LTTR ENCL EXTERNAI.: ACRS NSIC 16 08 16 1
1 LPDR 03
$0 TOTAl NUMBER OF COPIES'EQUIRED!
lTTR ENCL"
A P
NI NN N
1 t
N N
fI IT
Washington Public Power Supply System A JOINT OPERATING AGENCY.;..
P.O. BOX 968 3000 GEO. WASHINGTONWAY RICHLAND,WASHINGTON 99352 PHONE (509) 372.5000 March 10, 1981 G02-81-52 Docket File 50-397 Nuclear Regulatory Commission Region V
Suite 202, Walnut Creek Plaza 1990 N. California Boulevard Walnut Creek, California 94596 eEPEPE),
MAR 16 ]98t I>>.
9 U,~,~ BCIMtOl%
COAIAII$$ON Attention:
Mr. R.
H. Engelken, Director
Dear Mr. Engelken:
Subject:
WPPSS NUCLEAR PROJECT NO.
2 DOCKET NO. 50-397, CPPR-93 POTENTIALLY REPORTABLE 10CFR50.55(e)
CONDITION, WNP-2 106 DESIGN VERIFICATION OF SEISMIC CATEGORY I EQUALITY CLASS I HVAC SYSTEM HANGERS
Reference:
G02-80-293, dated December 15, 1980 The referenced letter provided an interim report of the subject poten-tially reportable condition.
This letter reports on the status of planned actions and the expected date a final report can be provided to the Commission.
It is expected the Contractor can complete the review of the installed hanger designs and provide the required design verifications or identi-fication of deficiencies prior to June 1, 1981.
Any deficiencies identified will be documented by Noq-Conformance Reports.
yol~
To date, revised Contractor procedures, assuring hanger designs are adequately verified, have been approved and the Contractor has been directed to provide design verification, in accordance with the revised procedures, for hangers considered to be permanently installed.
OXO3 Z9O gP
"r
Washington Public Power Supply System RH Engelken Page 2
March 10, 1981 G02-81-52 A final report on the subject concern will be provided to the Commission within one month following receipt of the Contractor's response.
Please contact us if you have additional questions.
Very truly yours, G. Matlock Program Director, WNP-2 cc:
JJ Verderber - Burns 5 Roe RE Snaith - Burns IE Roe RC Root - Burns 5 Roe Site WS Chin - Bonneville Power Administration TA Mangelsdorf - Bechtel wY..-Stel 1 o---NRC AD Toth -
NRC Resident Inspector W.
Wood -
NUS Corporation WNP-2 Files