Requests Attendance of Appropriate NRC Reviewers at 800327-28 Meeting at Site to Present Changes in Chapter 7 to Fsar.Plant Familiarization Tour Will Be Given & Util Personnel Will Be Available to Answer Questions
ML17272A841
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 02/28/1980
From: Renberger D
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To: Rubenstein L
Office of Nuclear Reactor Regulation
References
GO2-80-42, NUDOCS 8003060534
Download: ML17272A841 (6)


Text

SUBJECT:

Requests attendance of appropriate NRC reviewers at 800327 28 meeting at site to present changes in Chapter 7

to FSAR ~ Plant familiarization tour will be given 8 util personnel will be available to answer questions

~

DISTRIBUTION CODE:

B001B COPIES RECEIVED:LTR f ENCL"'

SIZE:

TITLE: PSAR/FSAR AMDTS and Related Correspondence NOTEO:l d2. 4+2 AkL >2dLP.

RECIP IENT COPIES COPIES ID CODE/NAME LTTR ENCL LTTR ENCL.'ECIPIENT ID CODE/NAME~

REGULATORY ORMATION DISTRIBUTION SYS 1 (RIDS)

ACCESSION NBR:8003060534 DOC ~ DATEi 80/02/28 NOTARIZED:

NO DOCKET FACIL:50 397 HPPSS Nuclear Projects Unit 2g Hashington Public Powe 05000397 AUTH ~ NAME AUTHOR AFF'ILLATION RENBERGER~D ~L','ashington Public Power Supply System RECIP' NAME RECIPIENT AFFILIATION RUBENSTEIN g L, L'ight Hater Reactors Branch ACTION:

05 PM /Pt. LC/+Cg BC E'ER 4'NTERNAL:;

01 REG F I 06 K

09 GEOSCIEN BR il MECH ENG BR 13 MATL ENG BR 16 ANALYSIS BR 18 AUX SYS BR 20 I K

C SYS BR 22 AD SITE'ECH 27 EFFL TRT'YS 29 K IRKHOOD AD PLANT'YS AD SITE. ANLYSIS HYDRO~METEOR BR OKLD EXTERNAL'. 03 LPDR 30 ACRS 1

]

1 1

2 1

2 1

1 1

1 1

1'2 1

1 10 1

AD Cad @

LA LMA 4y'2 NRC PDR 08 OPERA L'IC BR 10 QAB 12 STRUC ENG BR 15 REAC SYS BR 17 CORE. PERF.

BR 19 CONTAIN SYS 21 POHER SYS BR 26 ACCDNT ANLYS 28 RAD ASMT BR AD FOR KNG AD REAC SAFETY DIRECTOR NRR MPA 04 NSIC LW

~DdRF FP8 ~~ <6 KEBCM~E'4

~pg Ww 48 IR 7 1980 57 TOTAL-NUMBER OF COPIES REQUIRED:

LTTR ~

ENCL

~

e

,N i(

4 f

II il l

II aw p

6,i f

'I I

II

4 Washington Public Power Supply System A JOINT OPERATING AGENCY P. O. 8ox 955 3000 Gco WAIIHINCTDNWAY RlcHLAND, W*SHINGI'DN 99352 PHDNK (509) 375 5000 G02-80-42 February 28, 1980 Docket No. 50-397 Director, Nuclear Reactor Regulation U. S. Nuclear Regulatory Commission Washington, D.

C.

20555 Attention:

Mr. L. Rubenstein, Chief Branch No.

4 Division of Project Management

Subject:

WPPSS NUCLEAR PROJECT NO.

2 FSAR CHAPTER SEVEN TELECOPY

Reference:

1)

Letter, D. B. Vasallo to N. 0. Strand (WPPSS),

"First Round guestions on the WNP-2 OL Application

- ICSB,H,dated March 28, 1979.

2)

Letter, WPPSS to NRC, "WPPSS Nuclear Project No.

2 Facilitating the Round 2 Review," dated May 11, 1979

Dear Mr. Rubenstein:

Reference 1 indicated concerns about the adequacy of the Instrumentation and Controls section of the FSAR to support review for the issuance of an operating license.

Reference 1 further requested WPPSS to revise Chagter 7 of the FSAR to remove repetitious design deficiencies and conflicting or vague statements.

Reference 2 advised the NRC that the entire FSAR was being re-reviewed with the FSAR being changed as necessary.

The Instrumentation and Controls section was to be addressed and changed in this re-review process.

Additionally reference 2 requested a meeting

.with the NRC to discuss particular concerns about the Instrumentation and Control section.

The requested meeting was not held due to TMI-2 and its impact on the availability of the NRC staff.

However, WPPSS has since completed an extensive rewrite of. Chapter 7 of the FSAR.

The revised FSAR Chapter 7

will be submitted soon.

To facilitate the review effort, a presentation is planned for March 26, 1980 and March 27, 1980 to explain the changes made to Chapter 7. It is requested that the appropriate Chapter 7

reviewers (sub-contracted reviewers from Dupont deNemours and Company and 8003066

~

~ ~

L. Rubenstein Page 2

GO2-'80-42 February 28, 1980 ICSB staff personnel) be present for this meeting.

The meeting is to be held on site to allow for a site tour during the two day meeting.

Besides the FSAR Chapter 7 changes, outstanding questions previously submitted relating to Chapter 7 will be discussed with regards to intended resolution.

Additionally the plant familiarization tour will be given and WPPSS personnel will be available to discuss and resolve any specific concerns of the reviewers.

It is hoped that the revision of Chapter 7 and the planned meetings and discussions will satisfy the NRC concerns expressed in reference (1) and facilitate completion of the NRC Instrumentation and Control Systems review on WNP-2.

Very truly yours, DLR:PLP:cph D. L.

RENBERGER Assistant Director-Technology cc:

MD Lynch -

NRC R. Satterfied -

NRC JD Lewis, EFSEC, Olympia, Wash.

JR Lewis - Bonneville Power Admin.

M. Goosey - EI Dupont 8 deNemours Co.,

Savannah River Plant NS Reynolds - Debevoise

& Liberman FA MacLean - GE/San Jose E.

Chang - GE/San Jose JJ Verderber - Burns 5 Roe, New York HR Canter - BSR, N.Y.

J. Ellwanger - BSR, N.Y.

RC Root - B8R/site M. Izaak - WPPSS/New York WNP-2 Files