MONTHYEARML24260A2152024-09-16016 September 2024 Confirmation of Initial License Examination ML24179A1752024-06-27027 June 2024 Form 5.1-1 Post Examination Check Sheet ML24179A1742024-06-11011 June 2024 Form 2.1-1 Examination Preparation Checklist ML24179A1732024-06-11011 June 2024 Form 1.3-1 - Exam Security Agreement ML24179A1722024-06-0707 June 2024 2024-301 Post Exam SVP Letter ML24120A2032024-04-29029 April 2024 Operator Licensing Exam Approval - Dresden Nuclear Power Station, May 2024 ML24179A2152024-04-25025 April 2024 Form 3.4-1 Events and Evolutions Checklist ML24179A2142024-04-25025 April 2024 Form 2.3-1 Examination Outline Quality Checklist ML24179A2242024-04-23023 April 2024 Form 2.3-2 - Operating Test Quality Checklist ML24179A2252024-04-22022 April 2024 Form 2.3-4 - Written Examination Quality Checklist ML24179A2232024-02-12012 February 2024 ILT 23-1 (2024-301) SVP Letter - 24-007 ILT Exam Submittal ML24179A2122023-11-0808 November 2023 ILT 23-1 (2024-301) Exam Outline Submittal SVP Letter 23-0036 ML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1552021-12-0303 December 2021 Nov 2021 Ile ES-401-9 Written Exam Review Worksheet - Final ML22195A1422021-12-0303 December 2021 Nov 2021 Ile ES-301-7 Operating Test Review Worksheet - Final ML22195A1522021-12-0303 December 2021 Nov 2021 Ile ES-401-4 - Record of Rejected KAs-Final ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1702021-12-0303 December 2021 Nov 2021 Ile Outline Submittal Review Comments ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML22195A1872021-11-0808 November 2021 Nov 2021 Ile Administered Simulator and Inplant JPMs-FINAL ML22195A1932021-11-0808 November 2021 Nov 2021 Ile Administered RO and SRO List of Reference Handouts-FINAL ML22195A1882021-11-0808 November 2021 Nov 2021 Ile As-administered Simulator Scenarios-FINAL ML22195A1792021-11-0808 November 2021 Nov 2021 Ile Administered RO and SRO Admin JPMs-FINAL ML22195A1912021-11-0808 November 2021 Nov 2021 Ile Administered Written Exam-FINAL ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2522021-09-19019 September 2021 Nov 2021 Ile Proposed RO and SRO Written Exam ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2462021-09-19019 September 2021 Nov 2021 Ile Proposed Simulator and Inplant JPMs ML22195A2482021-09-19019 September 2021 Nov 2021 Ile Proposed Simulator Scenarios ML22195A2422021-09-19019 September 2021 Nov 2021 Ile Proposed RO and SRO Admin JPMs ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 2024-09-16
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML24260A2152024-09-16016 September 2024 Confirmation of Initial License Examination ML24179A1752024-06-27027 June 2024 Form 5.1-1 Post Examination Check Sheet ML24179A1732024-06-11011 June 2024 Form 1.3-1 - Exam Security Agreement ML24179A1742024-06-11011 June 2024 Form 2.1-1 Examination Preparation Checklist ML24179A1722024-06-0707 June 2024 2024-301 Post Exam SVP Letter ML24120A2032024-04-29029 April 2024 Operator Licensing Exam Approval - Dresden Nuclear Power Station, May 2024 ML24179A2142024-04-25025 April 2024 Form 2.3-1 Examination Outline Quality Checklist ML24179A2152024-04-25025 April 2024 Form 3.4-1 Events and Evolutions Checklist ML24179A2242024-04-23023 April 2024 Form 2.3-2 - Operating Test Quality Checklist ML24179A2252024-04-22022 April 2024 Form 2.3-4 - Written Examination Quality Checklist ML24179A2232024-02-12012 February 2024 ILT 23-1 (2024-301) SVP Letter - 24-007 ILT Exam Submittal ML24179A2122023-11-0808 November 2023 ILT 23-1 (2024-301) Exam Outline Submittal SVP Letter 23-0036 ML23285A2342023-10-13013 October 2023 Confirmation of Initial License Examination RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23160A1712023-06-0909 June 2023 Form 5.1-1 Post Examination Check Sheet ML23160A1672023-05-18018 May 2023 Form 1.3-1 Post Examination Security Agreement ML23160A1702023-05-18018 May 2023 Form 2.1-1 Examination Prep Checklist SVPLTR 23-0019, ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1)2023-05-0101 May 2023 ILT 22-1 (2023-301) Svpltr 23-0019 Post-Exam Submittal Letter (1) ML23087A0482023-03-28028 March 2023 Operator Licensing Examination Approval - Dresden Nuclear Power Station, April 2023 ML23160A1832023-03-16016 March 2023 3.4-1 Events and Evolutions Checklist ML23160A1802023-03-16016 March 2023 2.3-1 Examination Outline Quality Checklist SVPLTR 23-0002, 2.3-4 - Written Examination Quality Checklist2023-03-16016 March 2023 2.3-4 - Written Examination Quality Checklist ML23160A0542023-03-16016 March 2023 2.3-2 - Operating Test Quality Checklist ML23160A1782023-03-0606 March 2023 ILT Exam Outline Submittal Letter ML23160A0522023-01-25025 January 2023 ILT Exam Submittal Letter RS-22-045, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations2022-03-25025 March 2022 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2022-01, Preparation and Scheduling of Operator Licensing Examinations IR 05000237/20213022021-12-29029 December 2021 NRC Initial License Examination Report 05000237/2021302; 05000249/2021302 ML22195A1422021-12-0303 December 2021 Nov 2021 Ile ES-301-7 Operating Test Review Worksheet - Final ML22195A1272021-12-0303 December 2021 Nov 2021 Ile ES-201-1 Exam Prep Checklist ML22195A1552021-12-0303 December 2021 Nov 2021 Ile ES-401-9 Written Exam Review Worksheet - Final ML22195A1342021-12-0303 December 2021 Nov 2021 Ile ES-403-1-Written Exam Grading Quality Checklist-Signed ML22195A1312021-12-0303 December 2021 Nov 2021 Ile ES-201-3 - Exam Security Agreement ML22195A1702021-12-0303 December 2021 Nov 2021 Ile Outline Submittal Review Comments ML22195A1522021-12-0303 December 2021 Nov 2021 Ile ES-401-4 - Record of Rejected KAs-Final ML22195A1352021-11-15015 November 2021 Nov 2021 Ile Post-Exam Package Submittal Letter 11/15/2021 ML22195A1792021-11-0808 November 2021 Nov 2021 Ile Administered RO and SRO Admin JPMs-FINAL ML22195A1912021-11-0808 November 2021 Nov 2021 Ile Administered Written Exam-FINAL ML22195A1932021-11-0808 November 2021 Nov 2021 Ile Administered RO and SRO List of Reference Handouts-FINAL ML22195A1872021-11-0808 November 2021 Nov 2021 Ile Administered Simulator and Inplant JPMs-FINAL ML22195A1882021-11-0808 November 2021 Nov 2021 Ile As-administered Simulator Scenarios-FINAL ML21287A0442021-10-18018 October 2021 Operator Licensing Examination Approval ML22195A2222021-09-19019 September 2021 Nov 2021 Ile Es 301-3 Operating Test Quality Checklist-Signed ML22195A2522021-09-19019 September 2021 Nov 2021 Ile Proposed RO and SRO Written Exam ML22195A2262021-09-19019 September 2021 Nov 2021 Ile Es 301-4 Simulator Scenario Quality Checklist-Signed ML22195A2312021-09-19019 September 2021 Nov 2021 Ile Es 401-6 Written Exam Quality Checklist-Signed ML22195A2462021-09-19019 September 2021 Nov 2021 Ile Proposed Simulator and Inplant JPMs ML22195A2482021-09-19019 September 2021 Nov 2021 Ile Proposed Simulator Scenarios ML22195A2282021-09-19019 September 2021 Nov 2021 Ile Es 301-6 Competencies Checklist ML22195A2422021-09-19019 September 2021 Nov 2021 Ile Proposed RO and SRO Admin JPMs ML22195A2372021-09-0707 September 2021 Nov 2021 Ile Written Exam Submittal Letter 09-07-2021 2024-09-16
[Table view] |
Text
ES-201 Examination Preparation Checklist Form ES-201-1 Facility: DRESDEN Date of Examination: August 2017 Developed by: Written: Facility NRC // Operating: Facility NRC Chief Target Task Description (Reference) Examiners Date*
Initials
- 1. Examination administration date confirmed (C.1.a; C.2.a-b). For NRC-prepared exams,
-240 arrangements are made for the facility to submit reference materials (C.1.e; C.3.c; RKW 1/25/2017 Attachment 3).
-210 2. NRC examiners and facility contact assigned (C.1.d; C.2.f). RKW 1/25/2017
- 3. Facility contact briefed on security and other requirements (C.2.c). As applicable, the facility contact submits to the NRC any prescreened K/As for elimination from the written RKW 1/25/2017
-210 examination outline, with a description of the facilitys prescreening process (ES-401, D.1.b).
-210 4. Reference material due for NRC-prepared exams (C.1.e; C.3.c; Attachment 3). N/A
-210 5. Corporate notification letter sent (C.2.e). RKW 3/13/2017
- 6. NRC-developed written examination outline (ES-401-1/2 or ES-401N-1/2 and ES-401-3 or
-195 ES-401N-3) sent to facility contact (must be on the exam security agreement) (C.1.e-f; RKW 3/16/2017 C.2.h; C.3.d-e).
- 7. Operating test outline(s) and other checklists due, including Forms ES-201-2, ES-201-3,
-150 RKW 5/1/2017 ES-301-1, ES-301-2, ES-301-5, and ES-D-1, as applicable (C.1.e-f; C.3.d-e).
- 8. Operating test outline(s) reviewed by the NRC and feedback provided to facility licensee
-136 RKW 5/4/2017 (C.2.h; C.3.d-e).
- 9. Proposed examinations (written, JPMs, and scenarios, as applicable) and outlines (Forms ES-301-1, ES-301-2, ES-D-1, ES-401-1/2 or ES-401N-1/2, and ES-401-3 or ES-401N-3); Deliver on 6/26
-75 supporting documentation (including Forms ES-301-3, ES-301-4, ES-301-5, ES-301-6, RKW 6/26/2017 ES-401-6, ES-401N-6, and any Form ES-201-2 and ES-201-3 updates); and reference materials due (C.1.e-h; C.3.d).
- 10. Examinations prepared by the NRC are approved by the NRC supervisor and forwarded
-75 N/A for facility licensee review (C.1.i; C.2.h; C.3.f-g).
-60 11. Preliminary waiver/excusal requests due (C.1.m; C.2.c; ES-202). N/A
-50 12. Written exam and operating test reviews completed (C.3.f). RKW 7/10/2017
- 13. Examination review results discussed between the NRC and facility licensee (C.1.i; C.1.k-
-35 RKW 7/11/2017 l; C.2.h; C.3.g). The NRC and the facility licensee conduct exam preparatory week.
- 14. Preliminary license applications and waiver/excusal requests, as applicable (NRC Form
-7 RKW 8/1/2017 398) due (C.1.m; C.2.i; ES-202).
- 15. Final license applications and waiver/excusal requests, as applicable (NRC Form 398),
-7 RKW 8/4/2017 due and Form ES-201-4 prepared (C.1.m; C.2.k; ES-202).
-7 16. Written examinations and operating tests approved by the NRC supervisor (C.2.j-k; C.3.h). RKW 8/14/2017
-7 17. Request facility licensee management feedback on the examination (C.2.l). RKW 8/29/2017
- 18. Final applications reviewed; one or two (if more than 10) applications audited to confirm
-7 qualifications/eligibility; and examination approval and waiver/excusal letters sent (C.2.k; RKW 7/27/2017 Attachment 5; ES-202, C.3.j; ES-204).
- Target dates are based on facility-prepared examinations and the examination date identified in the corporate notification letter. These dates are for planning purposes and may be adjusted on a case-by-case basis in coordination with the facility licensee.