Amend 74 to License DPR-18,revising Plant Improved TSs Battery Cell Parameters Limit for Specific Gravity (SR 3.8.6.3 & 3.8.6.6)
ML17265A632
Person / Time
Site: Ginna Constellation icon.png
Issue date: 04/23/1999
From: Bajwa S
NRC (Affiliation Not Assigned)
To:
Shared Package
ML17265A633 List:
References
NUDOCS 9904300157
Download: ML17265A632 (6)


Text

~g8 A500

+

0 Cy 00 IVl0

/J

~O

+a*++

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 ROCHESTER GAS AND ELECTRIC CORPORATION DOCKET NO. 50-244 R. E. GINNA NUCLEAR POWER PLANT AMENDMENTTO FACILITYOPERATING LICENSE Amendment No. 74 License No. DPR-18 1.

The Nuclear Regulatory Commission (the Commission or the NRC) has found that:

A.

The application for amendment filed by the Rochester Gas and Electric Corporation (the licensee) dated March 1, 1999, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commission's rules and regulations set forth in 10 CFR Chapter I; B.

The facilitywilloperate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.

There is reasonable assurance:

(i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commission's regulations; D.

The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.

The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commission's regulations and all applicable requirements have been satisfied.

Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. DPR-18 is hereby amended to read as follows:

v9ohsooxs7 wqoczs PDR ADOCK OS000244 P

PDR

(2) Technical S ecifications The Technical Specifications contained in Appendix A, as revised through Amendment No.

74, are hereby incorporated in the license.

The licensee shall operate the facility in accordance with the Technical Specifications.

3. This license amendment is effective as of its date of issuance and shall be implemented within 30 days.

FOR THE NUCLEAR REGULATORYCOMMISSION S. Singh Bajwa, Section Chief, Section 1

Project Directorate I

Division of Licensing Project Management Office of Nuclear Reactor Regulation

Attachment:

Changes to the Technical Specifications Date of Issuance:

April 23, 1999

ATTACHMENTTO LICENSE AMENDMENTNO. 74 FACILITYOPERATING LICENSE NO. DPR-18 DOCKET NO. 50-244 Replace the following page of the Appendix A Technical Specifications with the attached page.

The revised page are identified by Amendment number and contain vertical lines indicating the area of change.

Remove 3.8-19 Insert 3.8-19

\\

Battery Cell Parameters 3.8.6 SURVEILLANCE REI0UIREHENTS SURVEILLANCE

,FREQUENCY SR 3.8.6.1 Verify electrolyte level of each connected battery cell is above the top of the plates and not overflowing.

31 days SR 3.8.6.2 Verify the float voltage of each connected battery cell is ) 2.07 V.

31 days SR 3.8.6.3 Verify specific gravity of the designated pilot cell in each battery is ~ 1. 195.

31 days SR 3.8.6.4 Verify average electrolyte temperature of

.the designated pilot cell in each battery is z 55'F.

31 days SR 3.8.6.5 Verify average electrolyte temperature of every fifth cell of each battery is ~ 55'F.

92 days SR 3.8.6.6 Verify specific gravity of each connected battery cell is:

a.

Not more than 0.020 below average of all connected cells, and b.

Average of all connected cells is z 1.195.

92 days R.E.

Ginna Nuclear Power Plant 3.8-19 Amendment No. Q 74