ML17265A525

From kanterella
Jump to navigation Jump to search
Forwards SE for Action Items Identified in Insp Rept 50-244/91-201.Based on 920409 & 871104 Responses, Administrative Controls Requiring Operability of Three SW Pumps Can Now Be Removed
ML17265A525
Person / Time
Site: Ginna 
Issue date: 01/29/1999
From: Vissing G
NRC (Affiliation Not Assigned)
To: Mecredy R
ROCHESTER GAS & ELECTRIC CORP.
Shared Package
ML17265A526 List:
References
50-244-91-201, TAC-M84947, NUDOCS 9902030181
Download: ML17265A525 (9)


See also: IR 05000244/1991201

Text

a

gP,R A500

+4

po

Cy

i~

O

IVl

Cy

~o~

++*++

Dr. Robert C. Mecredy

Vice President, Nuclear Operations

Rochester Gas and Electric Corporation

89 East Avenue

Rochester, NY 14649

UNITED STATES

NUCLEAR REGULATORY COIVIMISSION

WASHINGTON> D.C. 20555-0001

january

29,

1999

SUBJECT: SERVICE WATER SYSTEM AT R.E. GINNA NUCLEAR POWER PLANT

(TAC NO. M84947)

Dear Dr. Mecredy:

The service water (SW) system operational performance inspection was conducted from

December 2 through 20, 1991, at the Ginna Nuclear Power Plant. The findings were reported

in Inspection Report 50-244/91-201.

Several outstanding issues were identified in the

inspection report for further licensee review and resolution.

Six issues were identified for

further review by the NRC staff. The issues are as follows:

2.

3.

4

5.

6.

Application of hydraulic model to the service water system (SWS)

SW pump discharge check valve single failure vulnerability

Basis for the SWS low pressure setpoint

Single failure vulnerabilities with open cross-connect valves

Resolution of preoperational test discrepancies

Technical Specification requirements for operable pumps

You submitted your response

in a letter dated April6, 1992. Our initial review found that each

of the outstanding issues in the inspection report was addressed

and there were no immediate

safety concern.

However, several action items required further review; in particular, the item

regarding the number of pumps required for post-loss-of-coolant-accident

(LOCA) recirculation

phase.

You submitted additional information between April9, 1992, and November 4, 1998, in

response to the action items. Our review identified an additional item regarding the licensing

basis for the cross-connection

and isolation valves. The review for all of the items have been

completed and are discussed

in the enclosed safety evaluation.

As an interim measure while the NRC continued to evaluate your analyses supporting the use

of only one SW pump during the recirculation phase, by letter dated April6, 1992, you

implemented compensatory measures

in the Ginna administrative controls. These measures

require operability of three SW pumps (while the reactor is at power) and provisions to utilize

the bus tie breaker between 480-v safeguards ac buses 17 and 18 during the recirculation

phase post-LOCA in order to provide power to two SW pumps from a single diesel generator.

The administrative controls requires that ifat least three SW pumps are not restored to

operable status within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />, then place the plant in hot shutdown within a completion time

of 6 hours6.944444e-5 days <br />0.00167 hours <br />9.920635e-6 weeks <br />2.283e-6 months <br /> and in cold shutdown within a completion time of 36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br />.

9902030i8i 990i29

PDR

ADQCK 05000244

P

'PDR

"~:> ~-"'>d~l.'

i- j I(

c l

~

1

L

gl

i

J I

P

<

t

a

january

29,

1999

Dr. Mecredy

-2-

Based on our findings regarding this issue, you can now remove the administrative controls

that required operability of three SW pumps and the provisions to utilize the bus tie breaker

between 480-v safeguards ac buses 17 and 18 during the recirculation phase post-LOCA in

order to provide power to two SW pumps from a single diesel generator.

Your operation may

continue in accordance with Technical Specifications.

This completes our effort on TAC

No. M84947.

Sincerely,

Original signed

by:

Guy S. Vissing, Senior Project Manager

Project Directorate l-1

Division of Reactor Projects - I/II

Office of Nuclear Reactor Regulation

Docket No. 50-244

Enclosure:

Safety Evaluation

ccw/encl: See next page

PUBLIC

DISTRIBUTION:

~Docket File

PDI-1 R/F

J. Zwolinski

S. Bajwa

S. Little

G. Vissing

G. Hubbard

D. Jackson

T. Harris (e-mail SE only)

OGC

ACRS

R. Blough, Region

I

DOCUMENT NAME: G:hGINNA)LTR84947.WPD

To receive

a copy of this docunent,

indicate in the box:

"C" = Copy without attachment/enclosure

"E" = Copy with

attachment/enclosure

"N" = No co

OFFICE

PM:PDI-1

GVissing:lcc

NAME

DATE

01/ %99

LA:PDI-

SLittl

01/

99

D:PDI-1

SBajwa

01/

/99

SPLB

LMarsh

01/

/99

OFFICIAL RECORD COPY

t

l ~

'M

january

29,

1999

j))

,~

Dr. Mecredy

-2-

Based on our findings regarding this issue, you can now remove the administrative controls

that required operability of three SW pumps and the provisions to utilize the bus tie breaker

between 480-v safeguards

ac buses 17 and 18 during the recirculation phase post-LOCA in

order to provide power to two SW pumps from a single diesel generator.

Your operation may

continue in accordance with Technical Specifications.

This completes our effort on TAC

No. M84947.

Sincerely,

Original signed

by:

4

Guy S. Vissing, Senior Project Manager

Project Directorate I-1

Division of Reactor Projects - I/II

Office of Nuclear Reactor Regulation

Docket No. 50-244

Enclosure:

Safety Evaluation

cc w/encl: See next page

PUBLIC

DISTRIBUTION:

Docket File

PDI-1 R/F

J. Zwoiinski

S. Bajwa

S. Little

G. Vissing

G. Hubbard

D. Jackson

T. Harris (e-mail SE only)

OGC

ACRS

R. Blough, Region

I

DOCUMENT NAME: G:LGINNA)LTR8494?.WPD

To receive

a copy of this docunent,

indicate in the box:

>>C>> >> Copy without attachment/enclosure

>>E>> = Copy with

attachment/enclosure

>>li>> >> Iio co

OFFICE

PII:PDI-1

TAHE

GViss ing: Icc

DATE

01/ &99

LA:PDI-

SLittl

01/

99

0:PD I.1

SBa

wa

01/

/99

SPLB

LHarsh

01/

/99

OFFICIALRECORD COPY

j

a

Dr. Mecredy

-2-

Based on our findings regarding this issue, you can now remove the administrative controls

that required operability of three SW pumps and the provisions to utilize the bus tie breaker

between 480-v safeguards ac buses 17 and 18 during the recirculation phase post-LOCA in

order to provide power to two SW pumps from a single diesel generator.

Your operation may

continue in accordance with the Technical Specifications.

This completes our effort on TAC

No. M84947.

Sincerely,

Guy S. Vissing, Senior Project Manager

Project Directorate I-1

Division of Reactor Projects - I/II

Office of Nuclear Reactor Regulation

Docket No. 50-244

Enclosure:

Safety Evaluation

cc w/encl: See next page

Dr. Robert C. Mecredy

Rochester Gas and Electric Company

R.E. Ginna Nuclear Power Plant

CC:

Peter D. Drysdale, Sr. Resident Inspector

R.E. Ginna Plant

U.S. Nuclear Regulatory Commission

1503 Lake Road

Ontario, NY 14519

Regional Administrator, Region

I

U.S. Nuclear Regulatory Commission

475 Allendale Road

King of Prussia, PA 19406

Mr. F. WilliamValentino, President

New York State Energy, Research,

and Development Authority

Corporate Plaza West

286 Washington Avenue Extension

Albany, NY 12203-6399

Charles Donaldson, Esquire

Assistant Attorney General

New York Department of Lalw

120 Broadway

New York, NY 10271

Nicholas S. Reynolds

Winston & Strawn

1400 S Street N.W.

Washington, DC 20005-3502

Ms. Thelma Wideman, Director

Wayne County Emergency Management

Office

Wayne County Emergency Operations Center

7336 Route 31

Lyons, NY 14489

Ms. Mary Louise Meisenzahl

Administrator, Monroe County

Office of Emergency Preparedness

111 West FaIls Road, Room 11

Rochester,

NY 14620

Mr. Paul Eddy

New York State Department of

Public Service

3 Empire State Plaza, 10th Floor

Albany, NY 12223

)

I