Informs Util of Plans to Conduct Design Insp of Plant.Insp Will Be Conducted IAW NRC IP 93801, Safety Sys Functional Insp
ML17264A911
Person / Time
Site: Ginna 
Issue date: 06/09/1997
From: Dromerick A
NRC (Affiliation Not Assigned)
To: Mecredy R
ROCHESTER GAS & ELECTRIC CORP.
References
NUDOCS 9706120272
Download: ML17264A911 (5)


Text

Dr. Robert C. Mecredy Vice President, Nuclear Operations

- Rochester Gas and Electric Corporation 89 East Avenue Rochester, NY 14649 June 9

97

SUBJECT:

R.E.

GINNA NUCLEAR POWER PLANT DESIGN INSPECTION

Dear Dr. Mecredy:

The purpose of this letter is to inform you of our plans to conduct a design inspection of the R.E.

Ginna Nuclear Power Plant.

The inspection will be conducted in accordance with NRC Inspection Procedure (IP) 93801, "Safety System Functional Inspection."

For this inspection, we have selected the Component Cooling Water System and the Safety Injection System to perform our review.

We have scheduled the onsite portion of the inspection for the periods of July 7 through ll, 1997, July 21 through August 1,

1997, and August 11 through 15, 1997.

Your staff has indicated that there are no major conflicts with on-site activities during this period.

Mr. Jeffrey B. Jacobson, Team Leader, NRR, will interface with you and your staff regarding all matters related to this inspection.

The inspection will be performed using a team of five engineers from Stone

& Webster Engineering Corporation (SWEC) who have been contracted by the NRC for this purpose.

Mr. Robert B. Bradbury of SWEC who is part of the five person team will be the lead contractor engineer.

The inspection team will also be augmented by Mr.

Serge

Roudier, an inspector on loan to the NRC from the French Nuclear Safety Authority (DSIN).

We will be in contact with your staff regarding additional details for the inspection.

Should you have any questions, please contact Mr. Jacobson at (301) 415-2977 or me at (301) 415-3473; Sincerely,

/s/

cc:

See attached list Distribution:

Docket File PSIB R/F FPGillespie, NRR James T. Wiggins, RI Alexander W. Dromerick, Acting Director Project Directorate I-l Division of Reactor Projects I/II Office of Nuclear Reactor Regulation 0

RPZimmerman NRR Charles W. Hehl, RI Larry Doerflein, RI DOCUMENT NAME: G:GINNA)GINNA.ANN (see previous concurrences)

To receive a copy of this document, indicate in the box: "C" ~ Copy without enclosures E

~ Copy with enclosures "N" ~ No copy OFFICE DATE DISP NRR*

JJacobson 06/05/97 DISP NRR*

DPNorkin 06/05/97 DISP NRR*

RMGallo 06/06/97 OFFICIAL RECORD COPY DRPE NRR GVissin 06/C /97 DRP NRR ADromer'6/

/97

'rr706i20272 970609 PDR ADGCK 05000244 8

PDR

e q ~DR AECIj a~G 0

I

~o

++*++

UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C, 20M!F001 June 9, 1997 Dr. Robert C. Mecredy Vice President, Nuclear Operations Rochester Gas and Electric Corporation 89 East Avenue Rochester, NY 14649

SUBJECT:

R.E.

GINNA NUCLEAR POWER PLANT DESIGN INSPECTION

Dear Dr. Mecredy:

The purpose of this letter is to inform you of our plans to conduct.

a design inspection of the R.E. Ginna Nuclear Power Plant.

The inspection will be conducted in accordance with NRC Inspection Procedure (IP) 93801, "Safety System Functional Inspection."

For this inspection, we have selected the Component Cooling Water System and the Safety Injection System to perform our review.

We have scheduled the onsite portion of the inspection for the periods of July 7 through ll, 1997, July 21 through August 1,

1997, and August 11 through 15, 1997.

Your staff has indicated that there are no major conflicts with on-site activities during this period.

Mr. Jeffrey B. Jacobson, Team Leader, NRR, will interface with you and your staff regarding all matters related to this inspection.

The inspection will be performed using a team of five engineers from Stone 5 Webster Engineering Corporation (SWEC) who have been contracted by the NRC for this purpose.

Mr. Robert B. Bradbury of SWEC who is part of the five person team will be the lead contractor engineer.

The inspection team will also be augmented by Mr.

Serge

Roudier, an inspector on loan to the NRC from the French Nuclear Safety Authority (DSIN).

We will be in contact with your staff regarding additional details for the inspection.

Should you have any questions, please contact Mr. Jacobson at (301) 415-2977 or me at (301) 415-3036.

Sincerely, Alexan er W. Dromerick, Acting Director Project Directorate I-l Division of Reactor Projects I/II Office of Nuclear Reactor Regulation cc:

See attached list

I H

L~

C a

~C Dr. Robert C. Mecredy R.E.

Ginna Nuclear Power Plant CC:

Peter D. Drysdale.

Senior Resident Inspector R.E. Ginna Plant U.S. Nuclear Regulatory Commission 1503 Lake Road Ontario.

NY 14519 Regional Administrator, Region I U.S. Nuclear Regulatory. Commission 475 Allendale Road King of Prussia.

PA ~ 19406 Mr. F. William Valentino. President New York State

Energy, Research, and Development Authority Corporate Plaza West 286 Washington Avenue Extension
Albany, NY 12203-6399 Charlie Donaldson, Esq.

Assistant Attorney General New York Department of Law 120 Broadway New York, NY 10271 Nicholas ST Reynolds Winston 5 Strawn 1400 L St.

N.W.

Washington, DC 20005-3502 Ms. Thelma Wideman

Director, Wayne County Emergency Management Office Wayne County Emergency Operations Center 7336 Route 31 Lyons.

NY 14489 Ms. Mary Louise Meisenzahl Administrator.

Monroe County Office of Emergency Preparedness 111 West 'Fall Road, Room 11 Rochester, NY 14620 Mr. Paul Eddy New York State Department of Public Service 3 Empire State Plaza.

Tenth Floor Albany.

NY 12223

Jlf o t

S 7~

I