Monthly Operating Rept for Aug 1994 for Re Ginna Nuclear Power Plant.W/940909 Ltr
ML17263A774
Person / Time
Site: Ginna Constellation icon.png
Issue date: 08/31/1994
From: Ploof R, Widay J
ROCHESTER GAS & ELECTRIC CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9409200315
Download: ML17263A774 (6)


Text

REGULATORY INFORMATION DISTRIBUTION SYSTEM (RIDS)

DOCKET FACIL:50-244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G 05000244 AUTH. NAME AUTHOR AFFILIATION PLOOF,R.D. Rochester Gas & Electric Corp.

WIDAY',J.A. Rochester Gas & El'ectric Corp. P RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

Monthly ope Power Plan .W/940909 ttr.for Aug 1994 for RE Ginna Nuclear DISTRIBUTION CODE: IE24D COPIES RECEIVED:LTR ENCL SIZE- 0 TITLE: Monthly Operating Report (per Tech Specs NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72). 05000244 R RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD1-3 PD 1 1 JOHNSON A 1 1 INTERNAL: AEOD/SPD/RRAB 1 1 E=CE NEER=O 1 1 NRR/DORS/OEAB 1 1 NRR/PMAS/IRCB-E 1 . 1 RGN1 1 1 EXTERNAL: EG&G BRYCE,J.H 1 1 NOAC 1 1 NRC PDR 1 1 D

C U

NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE iVASTE! CONTACT TI.IE DOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 504-2083 ) TO ELlikIIVATEYOUR NAME FROiil DISTRIBUTION LISTS I'OR DOCUMENTS YOU DON"I'L'ED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 10 ENCL 10

t urzzzpt ~rim

~>~'ziipjgjx!/

9E/ ur~rzz ROCHESTERGASANDELECTRlCCORPORATION o 89EASTAVENUE ROCHESTER, N.Y. 1464Ml001 JOSEPH A. WIDAY TELEPHONE Rant Manager AREA CODE 716 546-2700 Glnno Nucleor Plont GINNA STATION September 9, 1994 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555

Subject:

Monthly Report for August, 1994.

Operating Status Information R. E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Sir:

Pursuant to our Technical Specification 6.9.1, attached herewith is the monthly operating status report for Ginna Station for the month of August, 1994.

Very truly yours, os h A. Wid lant Manager JAW:tjn Attachments c: Mr. Thomas T. Martin NRC (1)

$ A(~p ag eeoe200va5 eeoaza

~ .

PDR R=

ADOCK 05000244 PDR

OPERATING DATA REPORT DOCKET NO. 50-244 DATE: September 9, 1994 COMPLETED BY:

Ronald D. Ploof TELEPHONE (315) 524-4446 Ext.673 OE GS S

1. Unit N R.E. GINNA NUCLEAR POWER PLANT
2. Reporting Period: August, 1994
3. Licensed Thermal Power (MWt): 1520
4. Nameplate Rating (Gross MWe): 490
5. Design Electric Rating (Net MWe): 470
6. Maximum Dependable Capacity (Gross MWe): 490
7. Maximum Dependable Capacity (Not MWe): 470
8. If Changes Occur in Capacity Rating (Items Number 3 Through 7) Since Last Report, Give Reason:
9. Power Level to Which Restricted, If Any (Net MWe):
10. Reason For Restrictions, If Any:

This Month Yr.-to-Date Cumulative"

'1.

Hours in Reported Period 744.0 5831.0 217079.0

12. Number of hours Reactor Was Critical 445.0 4360.1 172886.6
13. Reactor Reserve Shutdown Hours 0.0 0.0 1688.0
14. Hours Generator On-line 439.0 4290.9 170042.9
15. Unit Reserve Shutdown Hours 0.0 0.0 8.5
16. Gross Thermal Energy Generated (MWH) 615679 6186292 '41142305
17. Gross Electrical Energy Generated (MWH) 201020 2083654 79767013
18. Net Electrical Energy Generated (MWH) 190335 1978467 75713840
19. Unit Service Factor (%) 59.0 73.6 78.3
20. Unit Availability Factor (%) 59.0 73.6 78.3
21. Unit Capacity Factor (using MDC Not) (%) 54.4 72.2 75.3
22. Unit Capacity Factor (using DER Not) (%) 54.4 72.2 75.3
23. Unit Forced Outago Rato (%) 41.0 9.5 5.8
24. Shutdowns Scheduled Over Noxt 6 Months (Typo, Date and Duration of Each):
25. If Shutdown At End of Report Period, Estimate Date of Startup:
26. Units in Test Status (Prior to Commercial Operation): Forcast Achieved INITIALCRITICALITY INITIALELECTRICITY COMMERCIAL OPERATION 0 CUMULATIVETOTAL COMMENCING JANUARY 1, 1975 00 CUMULATIVETOTAL COMMENCING NOVEMBER 8, 1969

AVERAGE DAILY UNIT POWER LEVEL DOCKET NO: 50-244 UNIT: R.E. Ginna Nuclear Power Plant DATE: Se tember 9 1994 COMPLETED BY:

Ronald Ploof TELEPHONE: 315 524-4446 Ext. 673 MONTH Au ust 1994 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 463 17.

2. 461 18.
3. 460 19.

460 20. -'8

5. 461 21.
6. 462 22. 46
7. 463 23. 176
8. 464 24. 435
9. 324 25. 466
10. -17 26. 463

-10 27. 463

-10

'2.

28. 464
13. 29. 464
14. 30. 465
15. 31. 466 16.

INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in reporting month. Compute to the nearest whole megawatt.

DOCKET NO. ~0 244 UNITNAMI: R.E. GINNA NUCLEAR POWER PLANT UNIT SHUTDOWN AND POWER REDUCTIONS COhIP LI'.1'I'.D BY Ron Ploof REPORT MONTH 1'I'. LI'.P I ION I'. 673 h

C o4 ~0 cta80 I.icensee C

4 lA Cause L Corrective 0 C 0 Ew 0 o 4 I 0 Event 4 0 O Action to No. Date 0 4 0 E 0 Vl 0 0 4 Report ¹ Prevent Recurrence I O ~ CL e'en o EA V

0 O

94=08 8/9/94 305 94-009 BQ PDP Excessive stress on piping caused weld to fail-. See LER 94-009 for corrective action.

3 F: Forced Reason: hlethod: Fxhibit G - Instructions S: Scheduled A-Equipment Failure (Explain) I-hlanua I for Preparation of Data 8-Maintenance or Test 2-Manual Scram. Entry Sheets for Licensee C-Refueling 3-Automatic Scram. Event Rcport (LER) I ilc (NI}RFG-D-Regulatory Restriction 4-Other (Explain) 01(il )

E-Operator Training & License Examination F-Administrative G-Operational Error (Explain)

Iltv. 4/8$ 4ses II-Other (Explain) Exhibit I - Same Source

~

NARRATIVE

SUMMARY

OF OPERATING EXPERIENCE DOCKET NO: 50-244 UNIT: R.E. Ginna Nuclear Power Plant DATE: Se tember 9 1994 COMPLETED BY:

Ronald Ploof TELEPHONE: 315 524-4446 Ext. 673 MONTH Au ust 1994 During the month of August the average power was 54'%n August 9 at 18: 58 the unit was taken of f to repair a crack in the SI System piping. The unit was placed back on line on August 22 at 11:59.