Forwards Revised Re Ginna Nuclear Power Plant ISI Program for 1990-1999 Interval. ISI Program Represents App B to QA Manual
ML17262B150
Person / Time
Site: Ginna Constellation icon.png
Issue date: 01/25/1993
From: Mecredy R
ROCHESTER GAS & ELECTRIC CORP.
To: Andrea Johnson
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM), Office of Nuclear Reactor Regulation
Shared Package
ML17262B151 List:
References
NUDOCS 9302020307
Download: ML17262B150 (6)


Text

seem,z~r Do@Vs DCSx Vnoz SvSxxu REGULAT INFORMATION DISTRIBUTIO STEM (RIDS)

E ACCESSION NBR:9302020307 DOC.DATE: 93/01/25 NOTARIZED: NO DOCKET FACIL:50-244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G

05000244 AUTH.NAME AUTHOR AFFILIATION MECREDY,R.C.

Rochester Gas 6 Electric Corp.

RECIP.NAME RECIPIENT AFFILIATION Document Control Branch (Document Control Desk)

SUBJECT:

Forwards App B to QA Manual, "Inservice Insp Program for I

1990-1999 Interval R.E.

Ginna Nuclear Power Plant."

DISTRIBUTION CODE:

A047D COPIES RECEIVED:LTR ENCL Q SIZE:

TITLE: OR Submittal: Inservice Inspection/Testing/Relic from ASME Code S

COPIES LTTR ENCL 1

1 RECIPIENT ID CODE/NAME PD1-3 PD NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72).

RECIPIENT COPIES ID CODE/NAME LTTR ENCL PD1-3 LA 1

0 JOHNSONyA 2

2 05000244 D

INTERNAL: NRR/DET/ECMB 9H y'UDOCS-ABSTRACT OGC/HDS1 RES MILLMANyG EXTERNAL:

EGSrG BROWNyB NRC PDR 1

1 1

1 1

0 1

1 1

1 1

1 NRR/DET/EMEB 7E EG F~L 01 RES DSIR/EIB EGSG RANSOMEyC NSIC 1

1 1

0 1

1 1

1 1

1 1

1 D

D D

NOTE TO ALL"RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTETH CONTACI'HEDOCUMENT CONTROL DESK, ROOM Pl-37 (EXT. 504-2065) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEEDI D

TOTAL NUMBER OF COPIES REQUIRED:

LTTR 16 ENCL 13

I Cl V'

i II+ZZ Zistuttnt lasr oala&

~ 'Z7II uurZur ZZ::::

ROCHESTER GAS AND ELECTRIC CORPORATION o

89 EAST AVENUE, ROCHESTER N.Y. 14649-0001 ROBERT G MECREDY Vice Prertdent Ginna Nuclear Production January 25, i1993 TELEPHONE AREA CODE 71B 54e 2700 U.S. Nuclear Regulatory Commission Document Control Desk Attn:

Allen R. Johnson (Mail Stop 14D1)

PWR Project Directorate I-3 Washington, D.C.

20555

Subject:

Ref.(a):

Submittal of Appendix B to the Quality Assurance Manual Inservice Inspection Program for the 1990-1999 Interval R.E.

Ginna Nuclear Power Plant Docket No. 50-244 Letter from R.C. Mecredy, RG&E, to A.R. Johnson,

NRC,

Subject:

Submittal of Appendix B to the Quality Assurance Manual, dated August 10, 1992 (b):

Letter from Allen Johnson, NRC, to R.C. Mecredy, RG&E,

Subject:

RG&E's letters of April 24, 1991 and May 6, 1991 Regarding Revisions of the Ginna QA Manual, Appendix B, dated June 16, 1992 (c):

Letter from R.C. Mecredy, RG&E, to A.R. Johnson,

NRC,

Subject:

Inservice Inspection

Program, dated August 17, 1992

Dear Mr. Johnson:

The revised Inservice Inspection (ISI) Program for the 1990-1999 interval for the R.E.

Ginna Nuclear Power Plant is hereby submitted for your information.

The ISI Program represents Appendix B to the Quality Assurance Manual and supersedes our submittal made in Reference (a) in its entirety.

The attached ISI Program document has been reformatted for ease of use.

The Program consists of eleven (11) sections and a Table of Contents.

In this structure each section, which carries its own revision, may be revised independently from the other sections.

In addition, Supplements 1 and 2, to Appendix B, the "Inservice Inspection Program Plan" and the "Repair, Replacement and Modification Program", respectively, were developed for RG&E use in the implementation of the ISI Program.

As stated in our

letter, Reference (a), it is not our intention to submit the relatively frequent revisions to Supplements 1 and 2.

These supplements are available on site and are reviewed by the ANII r'Pt rP f.l~

'Tt302020307 930225 PDR ADOCK 05000244 PDR

c<'e l

lfkf 'q g V

and normally examined by NRC inspection staff during refueling outages.

Revisions to Sections 1-11 will be provided to NRC for information as they are revised.

In addition to the reformatting discussed

above, Appendix B to the QA Manual has been updated to reflect previously agreed upon changes as noted below:

1)

Relief Request No.

4 (Reactor Coolant Pump Case Welds and Intervals) was withdrawn as reflected in Section 2 of Appendix B to the QA Manual.

NRC letter, Reference (b),

found withdrawal of Relief Request No.

4 acceptable.

2)

As stated in the last paragraph of our letter, Reference (c),

RG&E has withdrawn Relief Request No.

3 (authorized Inspection Agency).

This change is reflected in Section 2

of Appendix B to the QA Manual.

3)

As noted in paragraph 2 of our letter, Reference (c),

RG&E agreed to delete the proposed exclusion for removing insulation, during hydrostatic tests, for bolted connections with ferrous steel fasteners used in piping systems for controlling boration.

Paragraph 1.10.3.2 of Section 1 of Appendix B to the QA Manual reflects this change.

Individual revisions of the attached sections of Appendix B are listed below.

Table of Section Section Section Section Section Section Section Section Section Section Section 2

3 4

5 6

7 8

9 10 11 Contents 1

ISI Program for 1990-1999 Interval ISI Relief Requests P&ID Boundary Drawings Code Tables Line List Allocation Tables Block Listing High Energy Program Snubber Program Seismic Support Program Additional Programs Revision Date 12/31/92 12/31/92 12/31/92 12/31/92 12/31/92 12/31/92 12/31/92 12/31/92 12/31/92 12/31/92 12/31/92 12/31/92 Very truly yours, GAH/268 Attachment Robert C. Mecre y

xc:

Mr. Allen R. Johnson (Mail Stop 14D1)

Project Directorate I-3 Washington, D.C.

20555 U.S. Nuclear Regulatory Commission Region I 475 Allendale Road King of Prussia, PA 19406 Ginna Senior Resident Inspector