Monthly Operating Rept for Sept 1992 for Re Ginna Nuclear Power Plant.W/921015 Ltr
ML17262B053
Person / Time
Site: Ginna Constellation icon.png
Issue date: 09/30/1992
From: Dodge R, Mecredy R
ROCHESTER GAS & ELECTRIC CORP.
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
NUDOCS 9210200504
Download: ML17262B053 (6)


Text

ycczI.FR<rFo pgvgauvrow ozMo pa.prox svsvzM

,g "\

/

ACCESSION NBR:9210200504 DOC.DATE:,92/09/30 NOTARIZED: NO DOCKET ¹ FACIL:50-;.244 Robert Emmet Ginna Nuclear Plant, Unit 1, Rochester G 05000244 AUTQ.NAME AUTHOR AFFILIATION DODGE,R.E. Rochester Gas & Electric Corp.

MECREDY,R.C. Rochester Gas & Electric Corp.

RECIP.NAME RECIPIENT AFFILIATION Monthly operating rept for Sept 1992 for Ginna Nuclear l

'UBJECT:

RE Power Plant.W/921015 ltr.

DISTRIBUTION CODE: ZE24D COPIES RECEIVED:LTR / ENCL SIZE:

TITLE: Monthly Operating Report (per Tech Spec )

NOTES:License Exp date in accordance with 10CFR2,2.109(9/19/72); 05000244 S RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD1-3 LA 3 3 PD1-3 PD 1 1 JOHNSONiA 1 1 INTERNAL: AEOD/DOA 1 1 AEOD/DSP/TPAB 1 1 NRR DLPQ LPEB10 1 1 NRR/DOEA/OEAB 1 1 G FI 01 1 1 RGN1 1 1 EXTERNAL: EG&G BRYCEiJ.H 1 1 NRC PDR 1 1 NSIC ~

1 1

~go p~>po pp (g p NOTE TO ALL "RIDS" RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK.

ROOM Pl-37 (EXT. 504-2065) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 14 ENCL 14

HgV y civvy uzztz I ~ t OAIIS

>'III(ij(jr'Zrieruu 4

I re:ill ZixrZ j $ VAlE ROCHESTER GAS AND ELECTRIC CORPORATION o 89 EAST AVENUE, ROCHESTER, N.Y. 14649.0001 TELEPHONE AREA CODE 7IE 546-2700 GINNA STATION October 15, 1992 US Nuclear Regulatory Commission Document Control Desk Washington, DC 20555

Subject:

Monthly Report for September, 1992 Operating Status Information R. E. Ginna Nuclear Power Plant Docket No. 50-244

Dear Sir:

Pursuant to our Technical Specification 6.9.1, attached herewith is the monthly operating status report for Ginna Station for the month of September, 1992.

Very truly yours, Robert C. Mec edy RCM/

Attachments cc:. Mr. Thomas T. Martin NRC (1) 2QO'8,08 9210200504 '720930 PDR ADOCK 05000244 R PDR

c OPERATING DATA REPORT DOCKET NO. 50-244 DATE Octo r 15 1992 COMPLETED BY Robert E. Dodge TELEPHONE 315 524-4446 ext. 396

%%RATING STATUS

1. Unit Name: R.E GINHA NUCLEAR P(NER PUUIT Notes: The unit operated at approx.
2. Reporting Period: Se tember 1992 97% reactor power level for
3. Licensed Thermal Power (Wt): 1520 the entire report period.
4. Nameplate Rating (Gross MWe): 490 5 ~ Design Electrical Rating (Het We): 470
6. MaxicLm Dependable Capacity (Gross MWe): 490
7. Maxiram Dependable Capacity (Het MWe): 470
8. If Changes Occur in Capacity Ratings (Items Humber 3 Through 7) Since Last Report, Give Reasons:
9. Power Level to Which Restricted, If Any (Net MWe):
10. Reasons For Restrictions, If Any:

This Month Yr.-to-gate Cunuiative

11. Hours In Report Period 720 6 575 200 681.45
12. Nwher of Hours Reactor Was Critical 720 5 424.71 158 755.67
13. Reactor Reserve Shutdown Hours 1 687.55 *
14. Hours Generator On-Line 720 5 328.75 156 034.13
15. Unit Reserve Shutdown Hours 8.5 *
16. Gross Thermal Energy Generated (MWH) 1 059 758 7 574 10S 220 788 621
17. Gross Electrical Energy Generated (HWH) 357 488 2 560 097 72 889 704
18. Net Electrical Energy Generated (MWH) 339 653 2 429 704 69 182 251
19. Unit Service Factor 100% 81.05% 77.91%
20. Unit Availability Factor 100% S1.05% 77.91%
21. Unit Capacity Factor (Using MDC Het) 100.37% 78.62% 74.69%
22. Unit Capacity Factor (Using DER Net) 100.37% 78.62% 74.69%
23. Unit Forced Outage Rate 2.85% 5.95/
24. Shutdowns Scheduled Over Next 6 Months (Type, Date and Duration of Each):

Refuelin and Maintenance - March 19 1993 45 da s

25. If Shut Down At End Of Report Period, Estimated Date of Startup:
26. Units In Test Status (Prior to Ccmnercial Operation): Forecast Achieved INITIAL CRITICALITY INITIAL ELECTRICITY CCMMERCIAL OPERATION
  • CUMULATIVE TOTAL COMMENCING JANUARY 1, 1975
    • CUMULATIVE TOTAL COMMEHCIHG NOVEMBER 8, 1969

e t t AVERAGE DAILY UNIT POWER LEVEL 50-244 DOCKET NO.

UNIT R.E. Ginna Nuclear Power Plant DATE Octobe 15 1992 COMPLETED BY Robert E. Do ge TELEPHONE 1 315 524-4446 ext. 396 MONTH Se tember 1992 DAY AVERAGE DAILY POWER LEVEL DAY AVERAGE DAILY POWER LEVEL (MWe-Net) (MWe-Net) 1~ 472 17. 471

2. 472 18. 473 3 ~ 472 19. 473 472 20. 474
5. 382 21. 474
6. 474 22. 474
7. 474 23. 475
8. 478 24. 475
9. 475 25. 475
10. 475 26. 477 473 27. 480
12. 473 28. 477
13. 472 29. 478
14. 473 30. 478
15. 473 31 ~
16. 473 INSTRUCTIONS On this format, list the average daily unit power level in MWe-Net for each day in the reporting month. Compute to the nearest whole megawatt.

1)O(:Kl:1'O. SO-244 UNITNAhtl'. R E. GINNA NUCLEAR POWER PLANT UNIT SHUTDOWN AND POWER REDUCTIONS

(:Oht P LI:.TI:D It Y ge REPORT MONTH ~~BR 1992 1.FI FpljONir 315 524 4446 ext 39 ohio o o C4 C

0 ocoo-00 ca l.icensee Ew 0

c 0 Ih C Cause 5 Corrective Ho. Date IA Event 0 0 D Action to a~ o 0 > lO Q 0

0 0 Prevent Recurrence A~ Report tx.'IA 4 IA tL C Q 0

O Cl 92-07 09-05-92 S 0 Planned maintenance on transmission lines.

3 F: Forced Reason: Method: Fxhibit G - Instructions St Scheduled A-Etluipment Failure (Explain) I-Manual for Preparation of Data B-Maintenance or Test 2-Manual Scram. Entry Sheets for Licensee C-Refueling 3-Automatic Scram. Event Report (LER) File (NUREG-D-Regulatory Restriction 4-Other (Explain) ol6I)

E&perator Training & License Exatnination F-Administrative G-Operational Error (Explain)

REV. 4/8$ 4949 Hither (Explain) Exhibit I - Same Source

NARRATIVE

SUMMARY

OP OPERATING EXPERIENCE DOCKET NO. 50-244 UNIT R.E. Ginna Nuclear Power Plant DATE October 15 1992 COMPLETED BY Robert E. Dodge TELEPHONE 1 315 524-4446 ext. 396 MONTH Se tember 1992 The unit operated at approximately 97% Reactor Power Level for the entire month of September, with the exception on September 5, 1992. A power reduction to 61% was initiated to perform mainten-ance on transmission lines and returned to full power that same day.