December 12, 1990 Docket No. 50-244 Dr. Robert C. Hecredy Vice President, Nuclear Production Rochester Gas

& Electric Corporation 89 East Avenue Rochester, New York 14649

Dear Dr. Hecredy:

SUBJECT:

UNINPLEthENTED GENERIC SAfETY ISSUES AT R.E.

GINNA NUCLEAR POWER PLANT On April 25, 1990 the staff issued Generic Letter 90-04 which requested infor-mation concerning the implementation status of certain generic safety issues (GSIs) at your facility.

Based on your response to this Generic Letter, dated July 9, 1990, our own records and discussions viith your staff, we have updated our database on GSI implementation status.

The results of this effort were presented to the Commission at a meeting on October 25, 1990.

The enclosure to this letter summarizes the staff's understanding of the current status of those GSIs which remain unimplemented at R.E. Ginna Nuclear Power Plant.

We appreciate the assistance you provided in responding to Generic Letter 90-04 and we encourage your timely completion of those GSIs listed in the enclosure.

Please contact me if you have any questions or comments about the enclosed information.

Sincerely, Original Signed By:

Enclosure:

As stated Allen R. Johnson, Project Manager Project Directorate I-3 Division of Reactor Projects - I/II Office of Nuclear Reactor Regulation cc w/enclosure:

See next page DISTRIBUTION: Docket:File; NRC&Local PDRs, PDI-3 r/f, SVarga, EGreenman, HRushbrook, CECEC, ACRE(10),

RE R 11, till ll R

1

, AJ R

3 PDI-3/PH 9

PDI

/DIR NR ok AJohnson RWessman 90 A. /yh /90 h~/l~/90 CU ENT NAME: GINNA GSI LETTER 9012140108 901212 PDR ADOCK 05000244 P

PDC

~+I'"

1

/

c

'JJ. $

Dr. Robert C. Mecredy Ginna CC:

Thomas A. Moslak, Senior Resident Inspector R.E.

Ginna Plant U.S. Nuclear Regulatory Commission 1503 Lake Road

Ontario, New York 14519 Regional Administrator, Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, Pennsylvania 19406 i

Hs.

Donna Ross Division of Policy Analysis 5 Planning New York State Energy Office Agency Building 2 Empire State Plaza

Albany, New York 12223 Char lie Donaldson, Esq.

Assistant Attorney General New York Department of Law 120 Broadway New York, New York 10271 Nicholas S. Reynolds Winston K Strawn 1400 L St.

N.W.

Washington, DC 20005-3502

A g ~

vl

ENCLOSURE UNINPLENENTED GSIs AT R.E.

GINNA NUCLEAR POWER PLANT GSI NO.

51 (L913) 67.3.3 (A017) 75 8093)

A TITLE Improving the Reliability of Open-Cycle Service Water Systems Improved Accident Monitoring Items 4.5.2

& 4.5.3 Reactor Trip System Reliability - Test Alternatives and Intervals (System Functional Testing).

PROJECTED IMPLEMENTATION DATE 4/30/91 To be determined 2/15/91 RERARKS The RG&E letter of January 29, 1990, addresses the five issues that were documented in GL 89-13.

Those issues not already being addressed by,,

present programs require implementation of certain main-

tenance, procedure writing and testing actions.

RG&E letter to NRC of July 12, 1990, responds to all open issues of Regulatory Guide 1.97.

NRC Safety Evaluation (SE) to RG&E of December 4, 1990 found plant instrumentation acceptable with five exceptions.

RG&E is yet to schedule imple-mentation dates based on the December 4, 1990 SE.

RG&E provided agreement with Westinghouse Owners Group reports concerning the interval for testing of reactor trip system.

NRC is currently reviewing the RG&E response letter of October 4, 1990.