tA. g REGULATORY ORMATION DISTRIBUTION SYS 1 (RIDS)
ACCESSION NBR:8202240087 DOC ~ DATE: 82/02/18 NOTARI'ZED:
NO DOCKET FACIL:50-244 Robert Emmet Ginna Nuclear Planti Uni)t ii Rochester G
05000244 AUTH BYNAME AUTHOR AFF ILIATION MAIEReJ ~ Ee Rochester Gas 8 Electric Corp'EC IP ~ NAME RECIPIENT AFF IL'IATION CRUTCHF IELDi D, Operating Reactors Branch '5
SUBJECT:
Comments on NRC 811228 draf t safety evaluation per SEP Topic III 7Aicontainmeqt tendons, Resolution ofcomments ~should be specifically addressed in conjuction w/review'of containment tendon rept.
DISTRIBUTION CODE ~
A035S
'COPIES RECEIVED LTR
~
ENCL
~
SIZE ~
J D
TITLE: SEP Topics NOTES: 1 copy:SEP
- Sect, Ldr.
05000244 RECIPIENT ID CODE/NA'ME ACTION e ORB P5 BC 01 INTERNAL! IE 06 NRR/DE/HGEB 10 NRR/DL/SEPB 12 NRR/DS I/CS8 07
~COPIES LTTR ENCL 7
2 2
3 1
RECIPIENT ID ~CODE/NAME NRR/DE/ADMQE 13 NRR/DL/DRAB 11 N
AEB F ILE 04 COPIES LT'TR ENCL EXTERNAL: ACRS 14 NRC PDR 02 10 1
LPDR NTIS 03i5 93 TOTAL NUMBER OF COPIES REQUIRED:
LTTR ~
ENCL I
y N
N r.
a I
III
l t
1
'R ll
<</8/I2'iZII////
/l///
l/I
//Zl/I/////
ROCHESTER GAS AND ELECTRIC CORPORATION
~ 89 EAST AVENUE, ROCHESTER, N.Y. 14649 JOHN E. MAILER Vice President TELEPHONE AREA coDE 7ie 546-2700 February 18, 1982 Director of.Nuclear Reactor Regulation Attention:
Mr. Dennis M. Crutchfield, Chief Operating Reactors Branch No.
5 U.S. Nuclear Regulatory Commission Washington, D.C.
20555 BECrNEO iR FFB 2 3 19S2~
9 g g4N QRIKRl~
y mam~
Subject:
SEP Topic III-7.A, Inservice Inspection Including Prestressed Concrete Containment with Either Grouted or Ungrouted Tendons R. E. Ginna Nuclear Power Plant Docket No. 50-244
Dear Mr. Crutchfield:
Rochester Gas and Electric transmitted a letter relative to this SEP topic on February 3, 1982.
In that letter, we stated that any requirements relative to the Ginna containment tendons should be specified in conjunction with the NRC's review of the Containment Tendon Report, submitted by RG&E letter dated February 1, 1982.
RG&E has also reviewed the NRC's December 28, 1981 draft.
SER for this SEP topic, and has the following comments.
Resolution of these comments should be specifically addressed in conjunction with the review of the Containment Tendon Report.
1.
As noted in Section IV, Review Guidelines, the revised Regulatory Guide 1.35 is expected to be issued by mid to late 1982.
Changes to the Ginna surveillance program and Technical Specifications, if required, should be made at that time when implementation of the revised Regulatory Guide 1.35 on existing plants will be determined.
2.
In general, it appears that the additional requirements specified in the Conclusions section of this draft SER can be implemented.
However, the following clarifications apply.
a ~
It is expected that the acceptance bands for each tendon will be established prior to the next surveillance test (1983), rather than shortly after analyzing the Lehigh test results.
( I',-8202240087 8202i8
';I. '"PDR
- DOCH, 05000244
~ 'I'..P, i." 'PDR ",
~ ll C',
f
'I ll g
ROCHESTER GAS AND ELECTRIC Cu P.
February 18, 1982 Mr. Dennis M. Crutchfield SHEET NO.
b.
c The visual inspection of tendon anchorage assembly hardware which was conducted during the 1981 test included only those on top of the containment.
This would also apply to all future visual inspections.
It is noted that a report should be submitted to the NRC after each inspection.
RG&E considers it necessary to submit a report only if Technical Specifciation limits are not met.
Very, truly yours, Jo n E. Maier
i r3i y-.
1