ML17251B074

From kanterella
Jump to navigation Jump to search
Insp Rept 50-244/88-06 on 880307-11.No Violations Noted. Major Areas Inspected:Cycle 18 Startup Physics Test,Licensee Response to NRC Info Notice 86-005 & Previous Unresolved Item
ML17251B074
Person / Time
Site: Ginna Constellation icon.png
Issue date: 04/26/1988
From: Collins T, Eapen P, Prividy L
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
To:
Shared Package
ML17251B073 List:
References
50-244-88-06, 50-244-88-6, IEIN-86-005, IEIN-86-5, NUDOCS 8805090373
Download: ML17251B074 (16)


See also: IR 05000244/1988006

Text

U.S.

NUCLEAR REGULATORY COMMISSION

REGION I

Report

No.

50-244/88-06

Docket No.

50-244

License

No.

DPR-18

Licensee:

Rochester

Gas

and Electric

Com an

49 East Avenue

Rochester

New York

14649

Facility Name:

R.

E. Ginna

Inspection At:

Ontario

New York

Inspection

Conducted:

March 7-11

1988

Inspectors:

Collins, Chief

Nuclear Performance

Section,

NRR

Reactor

Systems

Branch

date

/leonard J. Prividy, Reactor

Engineer

date

Approved by:

Dr.

P.

K. Eapen,

C ief

Special

Test Programs

Section,

EB,

DRS

date,

Ins ection

Summar

Ins ection

on March 7-11

1988

Re ort No. 50-244/88-06

~l

physics tests

including:

precritical tests; critical boron measurements,

moderator temperature coefficient measurements;

control rod worth measurement;

and

QA/QC role in startup physics testing.

A major portion of this inspection

involved actual test witnessing.

Licensee

responses

to

NRC Information Notice No. 86-05

and

one previous unresolved

item were also reviewed.

Results:

No violations were identified.

8805090373

880428

PDR

ADOCK 05000244

9

DCD

'

'

DETAILS

1.0

Persons

Contacted

"S. Adams,

Reactor

Engineer

'J.

Bodine, Nuclear Assurance

Manager

  • S. Spector,

Superintendent,

Ginna Station

  • J. Widay, Technical

Manager

USNRC

C. Marschall,

Senior Resident

Inspector

N. Perry,

Resident

Inspector

  • Denotes those

present at the exit interview on March ll, 1988.

The

inspector also contacted

other licensee

employees

during the course of

the inspection.

2.0

C cle

18 Startu

Testin

Pro

ram

The startup physics test

program

was conducted

in accordance

with PT-34.0,

Startup

Physics

Test Program,

Revision

16.

This procedure

outlined the

steps for the test program,

set initial conditions

and prerequisites,

specified calibration procedures

at appropriate

points,

and referenced

detailed tests

and data collections in separate

test procedures.

Initial

criticality for Cycle

18 was achieved

on March 9,

1988.

The Zero Power

Physics Testing

was completed

on March 10,

1988.

At the

end of the

inspection

on March 10,

1988, while attempting to increase

power to 25%,

the plant tripped

on low steam

generator

water level.

The inspector witnessed

several

of the startup physics tests

including

Rod Drop Measurements,

Initial Criticality, All Rods Out (ARO) Boron

Concentration

Measurement,

Moderator Temperature

Coefficient Measurement,

and Control

Rod Worth Testing.

Test results

and procedures

as well as

the Cycle

18 core management

report

and Reload Safety Evaluation were

reviewed to assess

the adequacy of the licensee's

physics test program.

The inspector

independently verified that the predicted

values

and

acceptance

criteria had been obtained

from "The Nuclear Design

and

Core Management of the

R.

E. Ginna Nuclear Reactor. Cycle 18," WCAP-

11713,

February,

1988.

The details

and findings of the inspection

are described

below.

3.0

C cle

18 Startu

Testin

- Precritical

Tests

and Reviews

The inspector witnessed

and reviewed calibration

and functional test

results to verify the following:

Procedures

were provided with detailed instructions;

Technical

content of the procedures

was sufficient to result in

satisfactory

component calibration

and test;

Instruments

and calibration equipment

used were traceable

to the

National

Bureau of Standards;

and,

Acceptance

and operability criteria were observed.

The following items were witnessed

and reviewed

as noted:

3.1

C cle

18 Reload Safet

Evaluation

The inspector

reviewed the Reload Safety Evaluation

(RSE) prepared

by the fuel vendor (Westinghouse)

and noted that the applicable

burnup

range for the analysis

was 11,600

+500

MWD/MTU, and that

a

Cycle

17 burnup greater

than

11,400

MWD/MTU was necessary

to avoid

imposition of rod withdraw limitations for Cycle 18.

The rod

withdraw limits, if necessary,

would be

imposed to assure

that the

Moderator Temperature

Coefficient (MTC) remains within Technical

Specification Limits at all operating

power levels.

The inspector

determined that the actual

Cycle

17 burnup level

was

11,500

MWD/MTU

by reviewing the detailed core management

report (WCAP-11713).

This

burnup level (11,500

MWD/MTU) is both within the range of the

RSE

and greater

than the minimum burnup necessary

to avoid rod withdraw

limitations due to

MTC ~

The

RSE was forwarded

by the licensee's

offsite engineering staff

to the plant staff by memorandum

dated

February 2,

1988.

The Plant

Operations

Review Committee

(PORC) approved

the

RSE at Meeting

No.

024 on February

10,

1988.

No unacceptable

conditions were identified.

3.2

Control

Rod Checks

and Tests

The rod drop measurements

were performed in accordance

with procedure

RSSP-7.0,

Revision

12.

The inspector witnessed

the test performed

on March 8,

1988 and reviewed the test results.

The inspector deter-

mined that the

Rod Cluster Control Assembly drop times were well

below 1.8 seconds,

required

by the

TS.

The inspector

reviewed

several

visicorder traces

and verified that the drop times were

interpreted correctly.

'

The recently modified Microprocessor

Rod Position Indication (MRPI)

System

was being calibrated

and checked

per Procedure

No. SM-3797.7,

Revision 0,

on March 8,

1988.

The

MRPI system

was recently modified

to eliminate electrical

noise

problems.

The inspector

reviewed the

test data

and noted that it was satisfactory.

3.3

Reactor Coolant

S stem

RTD Calibration

Reactor Coolant

RTDs were cross calibrated

in accordance

with

Procedure

RSSP-8.0,

Revision

10,

on March 9,

1988.

The inspector

reviewed the calibration data

and noted that all calibration checks

were satisfactory.

4 '

C cle

18 Startu

Testin

- Postcritical

Tests

The inspector

reviewed selected

tests

and verified the following:

The tests

were

implemented

in accordance

with Cycle

18 Startup

Physics

Test Program;

Stepwise instructions of test

procedures

were adequately

provided

including Precautions,

Limitations and Acceptance Criteria in

Conformance with the requirements

of the Technical Specifications.

Appropriate measures

were taken if a test condition and/or test

result acceptance

criteria was not met;

Methods

and calculations

were clearly specified

and the tests

were

performed accordingly;

Review, approval,

and documentation

of the results

were in accordance

with the requirement of the

TS and the licensee's

administrative

controls;

and,

equality control

was active during test

and review.

4. 1

Initial Criticalit

and Critical Boron Measurements

Boron

End

Points

Prior to achieving initial criticality, the licensee

performed

a

reactivity computer checkout.

This was done by comparing the reacti-

vity computer outputs with established

curves of reactivity versus

period from a series of predefined

Control

Bank 0 movements.

The

licensee

measured

the All Rods

Out (ARO) critical boron concentra-

tions in accordance

with test procedure

PT 34. 1.

The boron

end point

for Banks

A+B+C+D inserted

was measured

in accordance

with procedure

PT 34.4.

The inspector witnessed

the conduct of the tests

and

reviewed the data'

The

ARO Boron

End Point was determined

as follows:

The reactor

was

brought to

a just critical state with only the

D rod bank not fully

withdrawn.

(The

D bank was withdrawn to about the

204 position in

this configuration.)

The reactivity worth of the

D bank at this

position

was then determined

by withdrawing the

D bank fully and

monitoring the flux increase

and startup rate.

The

D bank was then

'reinserted

to return the flux level to within the normal startup test

range.

Finally, the

D bank was returned to the 204 position

and the

reactor

was brought again to just critical, and the boron concentra-

tion was measured.

The boron concentration

was then adjusted

for the

equivalent

boron worth of the

D bank at position

204 and the

ARO

boron concentration

established.

The boron

end point for A+B+C+D banks inserted configuration

was

performed after determination of the individual bank worths discussed

in Section

4.3

~

The boron

end points are

summarized

below:

Confi uration

All Rods Out (ARO)

'+B+C+D Banks In

Predicted

Value

ppm)

1552 (+75)

1126 (+75)

Measured

Value

ppm

1560

1139

Ho unacceptable

conditions were identified.

4.2

Moderator

Tem erature Coefficient

The Moderator Temperature

Coefficient (MTC) was determined

in accord-

ance with the procedure

specified in

PT 34.2,

Revision 9.

The test

was witnessed

by the inspector

and involved

a slow heatup

and cool

down ( 10 degrees

F per hour) of the reactor coolant

system

and meas-

urement of the change

in reactivity as

a function of temperature.

The licensee

maintained

boron concentration

at

a constant

level

throughout

the test.

The parameter actually measured

is the Iso-

thermal

Temperature Coefficient (ITC).

ITC is defined

as the change

in reactivity for a unit change

in the moderator temperature

as well

as clad and fuel pellet temperatures.

Since

change

in reactivity at-

tributable to a change

in fuel

and cladding temperatures

is repre-

sented

by the Doppler (or fuel temperature)

coefficient, the

moderator

temperature coefficient can

be inferred from the

ITC

measurement

by subtracting

the value of the Doppler Coefficient from

the measured

ITC.

The measured

ITC at hot zero

power

(HZP) with all rods out (ARO) was

+2.8 pcm/degree

F at

547 degrees

F.

This is in reasonable

agreement

with the predicted

value of +2.93 pcm/degree

F.

The Doppler Coeffi-

cient (taken

from the fuel design report) is -1.9

pcm per degree

F

and the

MTC is therefore

+4.7

pcm per degree

F which is within the

Technical Specification

requirement of less

than +5.0

pcm per

degree

F at less

than

70% power.

The inspectors

noted that there

was

no lower bound acceptance

criteria

for the

MTC and

no acceptance

criteria on the difference

between

predicted

and measured

value of the

ITC (and therefore

MTC).

The

inspector discussed

how the licensee

assures

that the value of MTC

determined

from ITC measurement

is bounded

by that used in the Safety

Analysis for the Main Steam

Line Break (MSLB).

The concern

in the

MSLB analysis is that too negative of an

MTC can result in recriti-

cality due to the cooldown effects of the blowdown.

The licensee

indicated that the margin between

the analysis

value

and that pre-

dicted for the most negative point in cycle

(EOC) is large

enough

and

that the difference

between

the measured

and predicted

ITC would be

scrutinized.

The inspector

agreed that the margin was large

enough

for the current cycle.

The inspector also discussed

the lack of

acceptance

criteria for the difference

between

predicted

and measured

value of ITC or the lowerbound for the

MTC.

Inclusion of either of

the

above

acceptance

criteria will adequately

address

the

MSLB

concern.

The licensee

agreed

to modify test procedure

PT-34.2 for

future testing

by including

a lower limit in the

MTC acceptance

criteria'he

inspector

had

no further concerns.

4.3

Control

Rod Worth Measurement

The control rod reactivity worth measurements

were performed in

accordance

with test procedure

PT-34.3,

Revision 9.

The

following'esults

were noted:

Rod Bank

Predicted

Worth

pcm

Measured

Worth

Difference

~Pc IA

Control Bank

D

782 (+15%)

Control

Bank

C (D in)

1123

(+15%)

Control

Bank

B (C+D in)

788 (+15%)

Subtotal

(D+C+B)

2693

(+10%)

Control

Bank A (B+C+D in)

1535

(+15%)

Subtotal

(A+B+C+D)

4228 (+10%)

708

1005

692

2404

1522

3925

- 9.5

-10.6

-12.3

-10.8

- 0.9

- 7.7

As noted previously,

the predictions continue to be

on the low end

of the acceptance

criteria.

The inspector

had

no further questions.

'

5.0

Control

Room Observations

and

A/

C Role in

C cle

18 Startu

Ph sics

~Teetin

The inspector

observed

good coordination of operations,

testing,

reactor

engineering

and

IKC personnel

during startup physics testing.

All per-

sonnel

interfaced well with licensee contractor

(Westinghouse)

personnel.

Communications

among the reactor operator,

reactor engineering

and

contractor

personnel

concerning

rod movements

were clear.

QA/QC involvement

was evident in the precritical testing concerning

MRPI

testing

and rod drop measurements.

QA/QC involvement was confined to an

administrative role during post-critical testing

due to lack of expertise

in this area.

However,

the inspector

was advised

by the Nuclear Assurance

Manager that

an individual with prior SRO qualifications

was scheduled

to

be in the

QA/QC organization

by April 1988.

No unacceptable

conditions were identified.

6.0

Licensee

Res

onse to IE Information Notice No. 86-05

Main Steam Safet

Valve

MSSV

Test Failures

and Rin

Settin

Adjustments

IE Information Notice No. 86-05 describes

a potentially .significant issue

concerning

MSSV ring settings.

The inspector

met with a lead engineer

in

the Mechanical

Engineering

group to determine

the licensee's

response

to

this issue.

The inspector determined that the eight (8)

MSSVs at Ginna

Station are Crosby type

6R10 safety valves which are the

same type

referred to in IE Information Notice No. 86-05.

The licensee

has conducted

an ongoing evaluation

concerning this issue

since shortly before their initial correspondence

to Crosby

on November

14,

1986.

In this correspondence,

the licensee

advised

Crosby of the

current ring settings for the eight (8) MSSVs.

The upper (guide) ring

setting

was +100 for six (6) valves

and +150 for the other

two (2) valves.

The lower (nozzle) ring setting

was -20 on all MSSVs.

Also, Crosby was

requested

to confirm the acceptability of these

settings

or provide

new

settings

which will ensure that the Ginna

MSSVs can achieve full capacity.

A series of correspondence

followed between

the licensee,

Crosby and

Westinghouse

which resulted

in a recommended

change

to the current ring

settings.

For the eight, (8) MSSVs, the upper

(guide) ring setting

was

adjusted

to -50 and the lower (nozzle) ring setting

was adjusted to -100.

The licensee

is currently active with a Westinghouse

Owners

Group sub-

committee to perform testing

and confirm the adequacy of these settings.

No unacceptable

conditions were identified.

'

7.0

Licensee Action on Previous

Ins ection Findin

s

(Open) Unresolved

Item (50-244/85-09-01)

Predictions of Control

Rod Worth.

During

a Reactor

Physics Startup Test inspection for Cycle

15 (IR 85-09),

the inspector

noted that the individual bank worth measurements

were

on

the low end of the acceptance

criteria.

The licensee

experienced

the

same

anomaly during its cycle

16 and cycle, 17 startups.

The licensee

indicated that its engineering staff has

been working with Westinghouse

for the past

3 years to determine

the cause

of the relatively poor rod

worth predictions.

Westinghouse

representatives

assisting

in the

Cycle

18 startup testing

suggested

that the concern

may be attributable

to the boron dilution rate

(40 gpm) used during the previous

rod worth

tests,

which may have

been

too high.

The licensee,

therefore,

modified

his Cycle

18 rod worth test strategy to reduce

the boron dilution rate

by

a factor of 2.

The control

rod reactivity worth measurements

were

performed in accordance

with test procedure

PT-34.3,

Revision 9.

During

the course of the rod worth tests,

the boron dilution rate

was reduced

even .further (.to about

14 gpm).

However,

as

can

be

seen

from the results

given in Section

4 '

of this report,

the predictions continue to be

on the

low end of the acceptance

criteria.

i

Since the errors

have continued for several

cycles,

the licensee staff

postulated that the Westinghouse

model

may include inaccuracies

for some

core configurations particularly with regard to the weaker control banks.

This item continues

to remain unresolved

and will be reviewed in a future

inspection.

~Efl

The inspector discussed

the inspection findings at an exit meeting

on

March ll, 1988.

(See

paragraph

1 for attendees.)

No written material

was provided to the licensee

by the inspector at any

time during this inspections

The licensee

representatives

did not indicate

that this inspection

involved any proprietary information.

I